EVERGLADES NATIONAL PARK

REHABILITATE ANHINGA BOARDWALK

AND TRAIL AT ROYAL PALM

PMIS 158014 AND 187638

PROJECT NUMBER PI 14-0001

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

FEBRUARY 2015

PI-14-0001

PMIS 158014/187638 TABLE OF CONTENTS

REHABILITATE ANHINGA BOARDWALK AND TRAIL AT ROYAL PALM

FEBRUARY 2015

TABLE OF CONTENTS

DIVISION 01 GENERAL REQUIREMENTS

01 10 00 ....................................... SUMMARY OF WORK

01 14 00 ....................................... SCHEDULE AND PUBLIC ACCESS

01 33 00 ....................................... SUBMITTALS

01 35 00 ....................................... ACCIDENT PREVENTION

01 40 00 ....................................... QUALITY REQUIREMENTS

01 51 00 ....................................... TEMPORARY SERVICES

01 57 00 ....................................... TEMPORARY CONTROLS

01 77 00 ....................................... PROJECT CLOSEOUT

DIVISION 02 EXISTING CONDITIONS

02 40 00 ....................................... DEMOLITION

DIVISION 03 CONCRETE

03 30 00 ....................................... CONCRETE

DIVISIONS 04 TO 05 NOT USED

DIVISION 06 WOOD, PLASTICS, AND COMPOSITES

0610 00 ........................................ ROUGH CARPENTRY

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 58 00 ....................................... ROOFING

DIVISIONS 08 TO 26 NOT USED

DIVISION 26 ELECTRICAL

26 01 00 ....................................... ELECTRICAL MATERIALS AND METHODS

DIVISIONS 27 TO 30 NOT USED

DIVISION 31 EARTHWORK

31 10 00 ....................................... SITE CLEARING, DEMOLITION, AND EARTHWORK

DIVISION 32 EXTERIOR IMPROVEMENTS

32 12 00 ....................................... TRAIL PAVEMENT AND BASE COURSE

DIVISIONS 33 TO 48 NOT USED

PI-14-0001 01 10 00-1

PMIS 158014/187638 SUMMARY OF WORK

SECTION 01 10 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this project consists of providing all labor, materials, and equipment to demolish and reconstruct the Anhinga Boardwalk and Trail as shown on attached drawings 160/122,495.

B. The Anhinga trail and boardwalk is located at the Royal Palm Area of Everglades National Park. It is located 4.5 miles inside the national park entrance on State Road 9336.

C. The Anhinga Boardwalk and Trail are one of the most heavily visited attractions in the park. Time is of the essence in getting the boardwalk and trail replaced and back in service in as little time as necessary.

D. The work will be constructed under a single contract.

1.2 USE OF PREMISES

A. Seasonal Shutdown: No work will be allowed during the heavy visitor season (Nov 15 to April 15).

In the event this project is not completed before the heavy visitor season, the Contractor shall demobilize from the site and resume work after April 15 whether additional contract time is approved or not. Before demobilizing, the Contractor shall complete work sufficiently so the visiting public will have full access to the trail and boardwalk without encountering any dangerous or unsafe conditions. The contract time will be suspended during the shutdown and resume in April when the work resumes.

B. There is no water access to the site. Watercraft or floating work platforms can only access the site from the Trail. Moving any watercraft from the trail to the water shall be done without any ground disturbing activities. Motorized watercraft will not be allowed on the project site.

C. No vehicles or vehicle mounted equipment can access the boardwalk section of the trail.

D. Use of Site: Limit use of the premises to the area immediately adjacent to the work site. Do not disturb portions of the site beyond the work area.

1. Preservation of Natural Features:

a. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

b. Provide temporary barriers to protect existing trees and plants and root zones.

c. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed on roots and branches that interfere with construction.

d. Do not fasten ropes, cables, or guys to existing trees.

e. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

2. Preservation of Cultural Resources:

PI-14-0001 01 10 00-2

a. No known archeological resources are in the area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor will immediately stop work in the area of discovery and notify the Contracting Officer.

b. The existing stone retaining wall along the water behind the Visitor Center is historic.

Work along the wall demolishing the existing asphalt and installing new asphalt shall be done in such a manor at the prevent damage to the wall. Equipment will be operated with enough clearance between the machine and the wall to insure the wall is not struck or damaged. Removal and replacement of the asphalt within 12 inches of the wall shall be done by hand.

E. Storage of Materials: Confine storage of materials to the immediate work area and the designated staging area in the parking lot.

F. Construction Camp: Establishment of a camp within the park will not be permitted.

1.3 WORK RESTRICTIONS

A. Wildlife:

1. At no time will harassing or feeding of any wildlife be tolerated.

2. Any excavation left open at night shall be thoroughly checked in the morning for reptiles.

Reptiles (especially snakes) frequently crawl into open excavations at night. If found, notify the Contracting Officer to arrange relocation of the animal.

3. Alligators: The Anhinga Trail is a popular site for wildlife especially alligators. Depending on water conditions and time of year, the area may be heavily populated by alligators. Although alligators generally shy away from people, their behavior can be unpredictable. For the safety of workers on this project, the following guidelines shall be adhered to:

a. Do not approach within 12 feet of an alligator on land.

b. No workers shall be in the water at night or at dawn and dusk until the area is well lit by sunlight.

c. No worker shall be in the water alone. A group of workers will less likely encourage the curiosity of an alligator.

d. Whenever workers are present in the water, a spotter (not in the water) shall be designated to watch the area for alligators coming close to the work area.

4. Eastern Indigo Snake: The Eastern Indigo Snake is known to inhabit the area of this project.

The snake is an endangered species and is protected by law. Do not to injure, harm, harass or kill this species. Cease work and immediately contact the Contracting Officer if a snake is found within the project site.

B. On-Site Work Hours: Work shall be performed during daylight hours. Requests for any work outside those hours must be submitted for approval at least 48 hours in advance. The Contractor is allowed to work on weekends and holidays to expedite completion of the work.

C. Existing Utilities

1. Existing Utilities: Notify Contracting Officer of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

PI-14-0001 01 10 00-3

D. Hurricanes: The government requires closing of operations between 72 and 48 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. All project materials will be adequately secured or removed from the site within that time frame.

1.4 PRECONSTRUCTION CONFERENCE:

A. Before start of construction, the Contracting Officer will arrange an on-site meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contractor, park rules and regulations, construction schedule, shop drawings, and project closeout requirements.

1.5 FIELD VERIFICATION:

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the Contracting Officer before work is to be performed. Any work that is performed without notifying the Contracting Officer will be done at the contractor's own expense.

1.6 CONSTRUCTION MATERIALS:

A. All materials, including borrow and aggregates, shall be Contractor furnished from outside the park.

PART 2 - PRODUCTS Not used.

PART 3 - EXECUTION Not used.

END OF SECTION

PI-14-0001 01 14 00-1

PMIS 158014/187638 SCHEDULE AND PUBLIC ACCESS

SECTION 01 14 00

SCHEDULE AND PUBLIC ACCESS

PART 1 - GENERAL

1.1 SUMMARY

A. This section outlines the coordination between the contractor’s work and closing sections, or all of the trail and boardwalk to the public. Anhinga Trail and Boardwalk is one of the most heavily visited areas in the park and it is essential that the work be completed in a timely manner so that it may be reopened to the public without unnecessary delays.

1.2 WORK AND SCHEDULE CONSIDERATIONS

A. Sheet 2 of the Project Drawings shows the entire site, including the parking lot and staging area.

Designated construction Areas 1 through 4 are delineated on Sheet 2, and phasing of work in those areas is described below.

B. The visitor center, public restrooms, parking area, and Gumbo Limbo Trail shall remain open to the public for the duration of the project.

C. The road crossing between the designated staging area in the parking lot and the trail crossing at the east end of the Gumbo Limbo trail shall remain open to traffic (vehicle and/or pedestrian) except for short closures when materials or equipment must cross from the staging area to the work area. A flag man shall be used to stop traffic at the crossing, when necessary, and to protect/warn pedestrians along Anhinga trail when transporting materials to or from the boardwalk. The parking lot curb shall be protected from damage when transporting materials

D. During the solicitation process, contractors shall provide proposals to accomplish the work under two different scenarios: 1) Allowing visitors use of the trail and boardwalk during the project, and

2) Not Allowing visitors’ use of the trail and boardwalk during the project. The time allowed, and target times estimated, are described below. Contractor proposals should include proposed times to accomplish each portion of the project.

E. Under Scenario #1 (allowing visitors), Construction Area 1 shall be completed first, before work begins on Construction Area 2. Under Scenario #2 (no visitors), the order of work on the boardwalk may be proposed by the contractor for consideration by the government, with no required order of accomplishment. The target time for accomplishment of work in Area 1 under Scenario #1 is 90 calendar days, and under Scenario #2 is 60 calendar days. The contractor’s proposal may vary from the target durations, and should be so described in proposals for consideration.

F. No work on the asphalt trail (Construction Area 3) may begin until all work in Construction Areas 1 and 2 is completed. Visitors will NOT be allowed access to the trail during this portion of the project, regardless of Scenario followed. Construction Area 3 work should be completed within a maximum of 14 calendars day from starting.

G. Area 4 (adjacent to the Visitor Center) shall be the final area of work, after Construction Area 3 is completed. This area shall be completed within 5 calendar days of starting.

PI-14-0001 01 14 00-2

PMIS 158014/187638 SCHEDULE AND PUBLIC ACCESS

PART 2 - PRODUCTS Not used.

PI-14-0001 01 33 00-1

PMIS 158014/187638 SUBMITTALS

SECTION 01 33 00

SUBMITTALS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of submittal requirements before and during construction.

B. All submittals shall be transmitted electronically. One copy in PDF or MS Word format is required.

If the file sizes are too large to email, the Government will provide the Contractor access to its file transfer web site.

1.2 PRE-CONSTRUCTION SUBMITTALS:

A. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted. The schedule should be broken down into sections of work not exceeding two weeks each.

B. Submit a Schedule of Values showing the breakdown of the Contract amount into appropriate units of work. Include general condition costs, overhead, and profit in each part of the work and not as separate items. The Schedule of Values will form the basis for progress payments as provided for in the General Provisions.

C. Submit a safety plan per Spec Section 01 35 00. No on-site work will be permitted before the safety plan is received.

D. Quality Control plan per Spec Section 01 40 00.

1.3 MATERIAL SUBMITTALS:

A. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.

B. As specified in the individual sections, forward submittals to the Contracting Officer at least 14 days before need for approval.

C. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

D. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.

E. Contracting Officer's Review:

PI-14-0001 01 33 00-2

PMIS 158014/187638 SUBMITTALS

1. Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.

2. The returned submittal will be marked in one of three ways as defined below:

a. APPROVED: Acceptable with no corrections.

b. APPROVED WITH NOTATIONS: Only minor corrections or clarifications are needed and no further review is required. The Contractor shall address all review comments when proceeding with the work.

c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

PART 2 - PRODUCTS Not used.

PI-14-0001 01 35 00-1

PMIS 158014/187638 ACCIDENT PREVENTION

SECTION 01 35 00

ACCIDENT PREVENTION

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2 SUBMITTALS

A. Accident Prevention Program: Before on-site work begins, submit a written accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:

1. Name of responsible supervisor to carry out the program.

2. Site specific information including emergency response contact information and location of the nearest emergency room.

3. Weekly safety meetings.

4. First aid procedures.

5. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Needs to include measures taken to deal with visitors at trail crossings, material transported from the staging area to site, and visitors in the work area, etc.

6. Training, both initial and continuing.

7. Planning for possible emergency situations, such as hurricanes, floods, fires, cave-ins, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

8. Housekeeping: Section 01 57 00.

9. Fire Protection: Section 01 51 00.

B. Emergency Action Safety Plan

1. Contractor shall also be required to have an Emergency Action Safety Plan for securing his equipment and materials in the event of an approaching Tropical Storm or Hurricane Event and for the safe removal of personnel working at thesite.

a. The Emergency Action Safety Plan should include requirements and details for the

Contractor to secure his materials and equipment the work site, and evacuate the Park when notified by the Park's Incident Command Team.

b. Evacuation plans shall be consistent with existing Emergency Evacuation Plans for the Everglades National Park. Typically, notice is given within 100-hrs of potential landfall, as determined by the park (only), and personnel must be evacuated at least 24-hrs before such potential landfall.

c. The procedure shall identify the timing and procedure for the safe evacuation of personnel from the construction work site.

d. Evacuation plans shall be consistent with existing Emergency Evacuation Plans for Everglades National Park.

PI-14-0001 01 35 00-2

C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

D. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

1.3 QUALITY ASSURANCE:

A. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees:

1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

1.4 ACCIDENT REPORTING:

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident.

B. Other Accidents: The contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

PART 2 - PRODUCTS

2.1 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

2.2 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

PI-14-0001 01 35 00-3

2.3 BARRIERS: Section 01 57 00.

PART 3 - EXECUTION

3.1 EGRESS

A. Provide and maintain adequate egress at all times in accordance with the Life Safety Code (NFPA 101-94). No corridor, aisle, door, or exit shall be obstructed or used in a manner that interferes with egress.

3.2 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.3 TRAINING:

A. First Aid: Provide adequate training to ensure prompt and efficient first aid.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

PI-14-0001 01 40 00 - 1

PMIS 158014/187638 QUALITY REQUIREMENTS

SECTION 01 40 00 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. The quality of all work shall be the responsibility of the Contractor.

1.2 SUBMITTALS

A. Quality Control Plan:

1. After contract award and before the Pre-Construction conference, submit for approval a written

Contractor Quality Control (CQC) plan.

2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.

4. No change in the approved plan may be made without written concurrence by the Contracting

Officer.

B. Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report. Quality Control Supervisor shall utilize the forms attached at the end of this Section.

C. If the CQC plan and Quality Control Daily Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is accepted and implemented, or may retain payments for work completed on days there are no Quality Control Daily Reports.

1.3 QUALITY CONTROL

A. The Contractor's on-site superintendent may also perform the duties of the Quality Control Supervisor.

B. The Contractor is responsible for all testing and inspections. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance are in compliance with applicable specifications, drawings, and those required by the Building Code.

C. Re-testing/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and re-inspecting, for construction that replaced work that failed to comply with the Contract Documents.

PI-14-0001 01 40 00 - 2

PART 2 - PRODUCTS

2.1 QUALITY CONTROL PLAN

A. The Quality Control Plan shall include:

1. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

2. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

3. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

4. Methods of performing, documenting, and enforcing quality control of all work.

5. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

PART 3 - EXECUTION

3.1 DOCUMENTATION

A. Maintain Quality Control Daily Reports (attached) of quality control activities and tests. Provide copies to the Contracting Officer weekly.

3.2 ENFORCEMENT

A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.

PI-14-0001 01 40 00 - 3

CONTRACTOR'S QUALITY CONTROL DAILY REPORT

REPORT NO. _________ SHEET 1 OF _________

PROJECT

CONTRACT NO.

DATE

PARK

CONTRACTOR'S REPRESENTATIVE ON THE JOB

WEATHER (Rain, Snow, Cloudy, Windy, etc.)

RAINFALL

Inches

TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)

MAX.

MIN.

1. PRIME CONTRACTOR

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

HRS. WORKING

YES NO Comments

WORK PERFORMED BY PRIME CONTRACTOR:

MATERIALS DELIVERED OFFICIAL VISITORS TO SITE

2A. SUBCONTRACTOR, _____________________________________________: (If more than one subcontractor use copies of following page.)

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

WORK PERFORMED BY SUBCONTRACTOR:

3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)

4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)

Type and Location of Testing: ____________________________________________________________________________________

5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING

REQUIRED:

6. REMARKS:

7. CERTIFICATION:

I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above. ____________________________________________________________ Contractor's Quality Control Representative

PI-14-0001 01 40 00 - 4

SUBCONTRACTOR WORK CONTINUED:

CONTRACT NO. REPORT NO. _______

SHEET ____ OF ____

2 SUBCONTRACTOR,

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

2 SUBCONTRACTOR,

JOB

NO.

UNITS

JOB

NO.

UNITS

JOB

NO.

UNITS

YES NO COMMENTS

PI-14-0001 01 51 00-1

PMIS 158014/187638 TEMPORARY SERVICES

SECTION 01 51 00

TEMPORARY SERVICES

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of providing temporary services required for contractor's performance of the work of this contract.

PART 2 - PRODUCTS

2.1 GENERAL

A. Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

2.2 SANITARY FACILITIES

A. Sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, sturdy enclosures.

2.3 FIRE PROTECTION EQUIPMENT:

A. UL Class 2A, 2 1/2 gallon water type stored-pressure extinguisher and UL Class 10, Type I 15-pound B:C carbon dioxide extinguisher.

PART 3 - EXECUTION

3.1 ELECTRICITY AND LIGHTING:

A. Electricity is not available on-site.

B. Temporary Electrical: Temporary electrical work shall meet requirements of NFPA 70-1996 (NEC), Article 305.

C. When temporary connections are removed, restore existing utility services to their original condition.

3.2 TELEPHONE

A. Landline telephone is not available on site.

PI-14-0001 01 51 00-2

PMIS 158014/187638 TEMPORARY SERVICES

3.3 WATER:

A. Water for construction is not available on-site.

B. Furnish cool, potable water for construction personnel in locations convenient to work stations.

3.4 SANITARY FACILITIES:

A. The Contractor shall not use the restroom facilities provided for the public.

B. Place in the designated Contractor’s staging area.

C. Maintain and clean toilet facilities at least weekly.

D. Completely remove sanitary facilities on completion of work.

3.5 FIRE PREVENTION AND PROTECTION:

A. Responsible person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.

B. Fire Extinguishers: Travel distance from any work station to the nearest extinguisher shall not exceed 75 feet and one extinguisher on each vehicle or piece of equipment.

C. Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids within 50 feet of a structure. Provide adequate ventilation during use of volatile or noxious substances.

D. Spark Arresters: Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the U. S.

Forest Service.

E. Smoking: Smoking is not permitted in the work site except in the staging area. Smoking is prohibited near any combustible materials.

F. Hot Work: The Contractor shall obtain a hot work permit before performing hot work such as welding and acetylene torch cutting. The permit form is available from the Contracting Officer and shall be submitted to the Contracting Officer for signature by the Park Structural Fire Coordinator.

The permit will require the hot work area to be free of non-combustibles and to have a fire extinguisher available. Hot work will not be allowed in the following areas:

1. In areas not authorized by the Park Structural Fire Coordinator or his/her designee

2. In sprinklered buildings while such protection is impaired

3. In the presence of explosive atmospheres (that is, where mixtures of flammable gases, vapors, liquids, or dusts with air exist)

4. In explosive atmospheres that can develop inside unclean or improperly prepared drums, tanks, or other containers and equipment that have previously contained such materials

PI-14-0001 01 57 00-1

PMIS 158014/187638 TEMPORARY CONTROLS

SECTION 01 57 00

TEMPORARY CONTROLS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of providing temporary controls.

PART 2 - PRODUCTS

2.1 BARRIERS

A. Material may be new or used, but shall be suitable for intended purpose.

B. Fencing

1. Safety Barrier Fence: Orange plastic fence, minimum height, 4 feet.

2. Fences and barriers shall be structurally adequate and neat in appearance.

C. Barricades And Signs

1. Manual on Uniform Traffic Control Devices (MUTCD), Part VI, 1988 edition.

D. Lumber

1. Free of nails, large knot holes and splinters.

E. Barrier Tape

1. Banner Guard, imprinted with "CAUTION: CONSTRUCTION AREA", manufactured by Reef

Industries, Inc., Houston, Texas, or approved equal.

2.2 TEMPORARY SILT FENCES

A. Silt fence fabric shall extend from at least 4 inches belowground to at least 15 inches aboveground.

Stakes shall be installed at least 12 inches into the ground and extend above the top of the fabric.

B. Stakes shall be a wood with minimum dimensions of 1.5 inches square or other material of equivalent strength. Spacing of stakes shall be a maximum of 6 feet.

C. Fabric: Use a geotextile fabric made from woven or nonwoven fabric, meeting the following physical requirements:

Minimum grab tensile strength 90 pounds Minimum Trapezoidal Tear strength 35 pounds Minimum permittivity 0.5 sec-1

PI-14-0001 01 57 00-2

2.3 FLOATING TURBIDITY BARRIERS

A. Turbidity barriers shall be a constructed of 18 ounce nylon reinforced PVC fabric (300 psi test).

Flotation shall be provided by closed cell solid plastic with enough buoyancy to support the fabric in the water conditions anticipated at the site.

PART 3 - EXECUTION

3.1 PROTECTION OF TREES AND PLANTS TO REMAIN

A. Review site with the Contracting Officer and identify vegetation required to be removed. Trees to remain shall be protected.

3.2 HOUSEKEEPING

A. Keep project neat, orderly, and in a safe condition at all times.

B. Limit food and eating to the staging area in the Parking Lot.

C. All trash shall be pickup immediately.

D. Anything dropped into the water shall be retrieved and disposed of. This applies whether the item sinks or floats.

E. Provide enough containers for collecting construction debris and construction materials to be recycled.

F. Keep volatile wastes in covered containers.

G. Utilize excavated material as soon as possible.

3.3 DISPOSAL

A. All soil and rock removed shall be disposed of on-site at shown on the drawings.

B. All other removed material becomes the property of the Contractor and shall be disposed of outside the park.

C. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the park. Do not burn or bury refuse inside the park.

3.4 AIR AND WATER POLLUTION CONTROL

A. Temporary Silt Fences:

1. Complete the installation of any sediment control device prior to the commencement of any earthwork.

PI-14-0001 01 57 00-3

2. Inspect all temporary silt fences immediately after each rainfall and at least daily during prolonged rainfall. Immediately correct any deficiencies. Remove sediment deposits when the deposit reaches approximately 1/2 of the volume capacity of the temporary silt fence.

B. Turbidity Barriers: Place the barriers prior to the commencement of any in-water or shoreline work.

Barriers shall remain in place until completion of the work. Barriers shall completely enclose the work area. Barriers shall be set so the bottom edge of the barrier is approximately 12 inches above the bottom of the water.

C. Dust control: The Contractor shall take all reasonable measures to reduce dust nuisances to persons and to prevent damage to vehicles, buildings, existing vegetation or any other property near the project work site. Reasonable measures include watering materials during demolition, watering exposed soils, and covering stock piles.

D. Do not dispose of volatile wastes or oils in storm or sanitary drains.

E. Secure trash and other debris to prevent washing or blowing off the job site.

3.5 PROTECTION OF PUBLIC

A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

B. Erect and maintain barricades, lights, danger signals, and warning signs in accordance with

MUTCD-1988.

C. Illuminate barricades and obstructions at night; keep safety lights burning from sunset to sunrise.

D. Adequately barricade and post open cuts in or adjacent to thoroughfares.

E. Protect pedestrian traffic by guardrails or fences.

F. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.

G. Erect and maintain sufficient detour signs at road closures and along detour routes.

3.6 BARRIER TAPE

A. Install where directed by Contracting Officer. Keep a minimum of two rolls on site at all times.

3.7 REMOVAL

A. Completely remove barriers no longer needed when approved by Contracting Officer.

PI-14-0001 01 77 00-1

PMIS 158014/187638 PROJECT CLOSEOUT

SECTION 01 77 00

PROJECT CLOSEOUT

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of final cleanup and final inspection procedures.

PART 2 - PRODUCTS

2.1 CLEANING MATERIALS:

A. As recommended by the manufacturer of surface to be cleaned.

PART 3 - EXECUTION

3.1 CLEANING

A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish.

Restore or refinish surfaces that are damaged due to work of this contract to original condition.

Remove grease, dirt, stains, foreign materials, and labels from finished surfaces. Pick up all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.

3.2 PROJECT RECORD DRAWINGS:

A. Maintain one complete full size set of contract drawings and one full size set of vendor supplied drawings. Clearly mark changes, deletions, and additions using National Park Service drafting standards to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue.

B. Keep record drawings current. Make record drawings available to the Contracting Officer for inspection at the time of monthly progress payment requests. If project record drawings are not current, the Contracting Officer may retain an appropriate amount of the progress payment.

C. On completion of the total project, submit complete record drawings. Include all shop drawings, sketches, and additional drawings that are to be included in the final set, with clear instructions showing the location of these drawings.

PI-14-0001 01 77 00-2

PMIS 158014/187638 PROJECT CLOSEOUT

3.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request. If the work schedule is phased, inspections will be scheduled accordingly.

B. When work is determined to be substantially complete, Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

C. If work is not determined to be substantially complete, Contracting Officer will notify contractor in writing. After completing work, contractor shall resubmit certification and request a new final inspection.

3.4 ACCEPTANCE OF THE WORK

A. After all deficiencies have been corrected, a Letter of Acceptance will be issued.

PI-14-0001 02 40 00-1

PMIS 158014/187638 DEMOLITION

SECTION 02 40 00

DEMOLITION

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of demolition and removal of pavements, slabs, structures, and portions of abandoned utilities.

1.2 QUALITY ASSURANCE

A. Comply with safety requirements for demolition, ANSI A10.6-90.

1.3 PROJECT CONDITIONS

A. Keep dust to a minimum at removal site and on haul roads. Use sprinklers or water trucks as necessary.

B. Ensure safety of persons in demolition area. Provide temporary barricades as required.

PART 2 - PRODUCTS

2.1 SELECT BACKFILL

A. Fine, readily compactable soil or granular material, free from frozen lumps, stones larger than 2 inches, highly plastic clay, and organic or other objectionable material. Excavated material meeting this requirement shall be used before importing material.

PART 3 - EXECUTION

3.1 WOOD STRUCTURE DEMOLITION

A. Completely remove wood structures including pulling all piles and posts.

3.2 ASPHALT DEMOLITION

A. The Contractor shall grind up the existing asphalt into aggregate base type material and spread across the trail before paving. The ground up material shall be less than 1.5 inches in diameter and be fine enough to be spread and compacted to a smooth surface.

PI-14-0001 02 40 00-2

PMIS 158014/187638 DEMOLITION

3.3 SALVAGE

A. Items to be Reused:

1. Camera and associated equipment on the covered boardwalk platform.

2. Benches along the boardwalk.

3. Placards, signs and, display panels attached to the boardwalk railings or any other material being demolished.

B. Carefully clean and store items to be salvaged or reused.

PI-14-0001 03 30 00-1

PMIS 158014/187638 CAST-IN-PLACE CONCRETE

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 DESCRIPTION

A. This work shall consist of placing cast in place concrete.

1.2 QUALITY ASSURANCE

A. General:

1. Work shall conform to all requirements of ACI 301, except as modified by the requirements of these Contract Documents.

2. Substitute the term "Contracting Officer" for the terms "Owner," "Architect/Engineer," and

"Engineer/Architect" wherever used in ACI 301.

B. Concrete:

1. Furnish concrete under Option C, ASTM C94, whereby the manufacturer assumes full responsibility for the selection of the proportions for the concrete mixture within the general parameters specified in this section.

C. Testing:

1. The Contractor shall be responsible for all concrete testing, including testing identified as being the responsibility of the "Owner" in ACI 301.

2. The Contractor shall make two test cylinders for each day concrete is placed. Cylinders shall be broken at a certified testing laboratory and results provided to the Contracting Officer within 48 hours of the break.

D. Rebar:

1. Rebar details not shown on the contract drawings shall conform to CRSI Manual of Standard

Practice.

1.3 SUBMITTALS

A. As specified in Section 01 33 00.

B. Provide the concrete mix design including the: strength; water cement ratio; weight per cubic yard of cement, aggregates, and water; sieve analysis of aggregates; and product information on any admixtures used.

PART 2 - PRODUCTS

2.1 FORMWORK AND FORM ACCESSORIES

A. Form Facing Materials:

PI-14-0001 03 30 00-2

PMIS 158014/187638 CAST-IN-PLACE CONCRETE

1. Forms in contact with concrete shall produce a smooth form finish.

2. Footings that are to be buried may be placed against compacted earth formed sides.

2.2 REINFORCEMENT

A. Reinforcing Bars: ASTM A767, Grade 60.

2.3 CONCRETE

A. Cementitious Material Content: Cementitious material may be a blend of portland cement and fly ash. Minimum cementitious material content, 564 pounds per cubic yard.

1. Portland Cement: ASTM C150.

2. Fly Ash: ASTM C618-95, Class F. Fly ash not to exceed 15 percent of total cementitious material content by weight.

B. Maximum Size of Coarse Aggregate: 3/4 inch.

C. Slump: 3 to 4 inches unless a water reducing admixture is used. If a water reducing admixture is used, the slump can be higher but must be in the range specified on the approved Concrete Mix Design.

D. Maximum Water - Cementations Material Ratio: 0.50.

E. Strength: 28-day compressive strength shall be a minimum of 4,000 psi.

F. Maximum Concrete Temperature: The temperature of concrete at time of delivery shall not exceed 80 degrees Fahrenheit.

G. Chloride Ion Content: Chlorides are not permitted.

PART 3 - EXECUTION

3.1 GENERAL

A. Notify Contracting Officer at least 24 hours in advance of any concrete placement. Do not place concrete until Contracting Officer has accepted pre-placement activities.

B. All tools, supplies, equipment and materials are to be on site before beginning placement of concrete.

Keep a spare vibrator, of the appropriate size, on the job site during all concrete placing operations.

3.2 The forms can be removed and the structure backfilled once the concrete strength is determined to be at least 50% of the 28-day design strength specified in this section.

PI-14-0001 06 10 00-1

PMIS 158014/187638 ROUGH CARPENTRY

SECTION 06 10 00

ROUGH CARPENTRY

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of rough carpentry work.

1.2 SUBMITTALS

A. As specified in Section 01 33 00.

B. Samples: Decking showing face texture and color. Deck Screws showing head color.

C. Manufactures Literature: Composite Decking and deck screws.

D. Warrantee: Provide manufacture’s written warrantee for the composite decking.

E. Certification: Manufactures certification that the lumber and piles are treated to the retention specified.

1.3 QUALITY ASSURANCE

A. Identify lumber and plywood by official grade mark.

B. Lumber: Grade stamp containing, where applicable, symbol of grading agency, rules under which graded, mill number or name, grade of lumber, species or species grouping, and condition of seasoning.

C. Plywood: APA grade trademark, including type, grade, class, identification or span rating, and inspection and testing agency mark.

1.4 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Store materials a minimum of 6 inches above ground in area protected from weather. Protect with waterproof covering allowing adequate air circulation. Do not store seasoned materials in wet or damp environments.

PART 2 - PRODUCTS

2.1 LUMBER

A. PS-20.

PI-14-0001 06 10 00-2

1. Moisture Content: 19 percent maximum (dry) at time of manufacture for lumber 2 inches or less in thickness.

2. Surfacing: S4S, unless otherwise specified.

3. Dimensions: All dimensions are nominal.

4. Species: Southern Pine.

5. Structural:

a. All lumber except 6x6 piles: No 1 Grade

b. 6x6 Piles: No 2 Grade.

6. Treatment: CCA Retention 0.40 lbs/cf

2.2 PLYWOOD

A. Roof Sheathing: PS-1, APA Rated Sheathing C-C Exterior.

2.3 COMPOSITE WOOD DECKING

A. Reclaimed wood and polyethylene plastic with additives for coloring and inhibiting fungal/algal growth; free from toxic chemicals. Product shall be Moisture Shield as manufactured by Advanced Environmental Recycling Technologies or approved equal.

B. Color and Surface texture: Cape Cod Gray with Wood grain embossed finish.

C. The product shall be suitable for direct ground or water contact.

D. Characteristics:

1. Hardness: 1,352 lbf; ASTM D143

2. Thermal expansion coefficient: 2.0 x 10¯5 in/in/°F; ASTM D1037

3. Fastener withdrawal:

a. Screw: 474.4 lbf; ASTM D1761

4. Static coefficient of friction:

a. Dry: 0.59/0.64; ASTM D2394

b. Wet: 0.92/0.84; ASTM D2394

5. Fungus resistance, white and brown rot: Very Resistant; ASTM D2017

6. Termite resistance: Highly Resistant; AWPA E-1

7. Compressive Strength: 962 lb/in²; ASTM D1621

8. Compressive Modulus: 21,926 lb/in² ; ASTM D1621

9. Deformation at Maximum Load: 0.1629 in; ASTM D1621

10. Modulus of rupture: 2,500 lb/in²; ASTM D7032.

11. Flexural Stress: 250 lb/in² design; ASTM D7032

12. Modulus of elasticity: 268,000 lb/in²; ASTM D7032. 100,000 lb/in² design.

13. Vicat Softening Temperature: 242°F; ASTM D1525

2.4 ROUGH HARDWARE

A. Bolts: ASTM A307, Hot Dip Galvanized per ASTM F2329 or A153.

B. Wood Construction Connectors: Simpson Strong Tie or approved equal. Approved equal shall be of the same metal thickness and have the same allowable loads at the Simpson Model Specified.

Connectors shall be hot-dip galvanized per ASTM A123. Fasteners shall be hot-dip galvanized per

ASTM A153.

PI-14-0001 06 10 00-3

C. Deck Screws: Star Drive C-Deck Screws as manufactured by Screw Products, Inc., Gig Harbor WA. Size: #10 x 2-3/4”. Material: 305 Stainless Steel. Head designed for Composite lumber to eliminate mushrooming and leave a smooth, flush and countersunk finish. Head color shall be grey to match decking.

D. Cable and Cable Hardware: ASTM A475 Galvanized.

E. Utility Pole Anchor: Wedge Style Anchor, Galvanized, Hubbell Power Systems or approved equal.

F. Miscellaneous Hardware: Hot Dipped Galvanized.

PART 3 - EXECUTION

3.1 GENERAL INSTALLATION

A. Install rough carpentry work as shown.

B. Limit the amount of sawdust and lumber scrapes falling into the water as practically possible.

1. Decking and lumber shall be precut before installation whenever possible.

2. Precutting shall be done over a solid surface or over decking covered by a tarp to catch sawdust and small scraps before it falls into the water.

3. Scrapes and sawdust should be picked up and disposed of daily.

3.2 PILES

A. Drive piles using an air operated post driver Model PD-200 as manufactured by Rhino Tools Kewanee, Illinois, or approved equal. The driver shall weigh approximately 200 lbs and deliver up to 1700 blows per minute using a reciprocating piston striking directly on the post or drive cap.

Drive pile to refusal using the equipment specified. The pile shall be plumb to within 1 inch in 10’.

Piles less than 16’ long shall be installed without splices.

B. Where the soil is too shallow for the pile to penetrate at least 2 feet into soil. The pile must penetrate at least nine inches into the limestone rock. The rock can either be broken up with a pneumatic hammer before driving the pile or the limestone excavated, pile installed, and then backfilled with gravel.

3.3 BOLTS

A. Bolt holes shall be a minimum of 1/32” to a maximum of 1/16” larger that the diameter of the bolt.

B. Washers not less than standard cut shall be placed between the wood and bolt head and between the wood and nut.

C. Minimum edge distance (edge of board to center of bolt) shall be:

1. 1.5 times the diameter of the bolt (Loading Parallel to Grain)

2. 4 times the diameter of the bolt (Loading Perpendicular to Grain)

D. Minimum end distance (end of board to center of bolt)

1. 4 times the diameter of the bolt (Loading Perpendicular to Grain)

2. 4 times the diameter of the bolt (Compression Loading Parallel to Grain)

PI-14-0001 06 10 00-4

3. 7 times the diameter of the bolt (Tension Loading Parallel to Grain)

3.4 DECKING

A. Install composite decking in accordance with manufacturer’s instructions.

B. Cut, drill, and rout composite wood using carbide tipped blades.

C. Do not locate fasteners closer than 1 inch from edges.

D. Install with a 3/8” to 1/2” gap between boards (side by side).

E. Install with a gap of 1/8” end to end.

F. Except for the platforms where the width exceeds 16 feet, a single board shall span the entire width of the boardwalk.

G. End to end butt joints on the platforms shall be aligned with the under laying double joists. Joints shall be staggered so no two joints are adjacent.

3.5 ROOF SHEATHING

A. Follow recommendations of APA. Install plywood with face grain perpendicular to supports, and with end joints staggered and located over supports. Allow 1/8 inch space between panel ends and edges. Support edge joints with plywood panel clips centered between each support.

PI-14-0001 07 56 00-1

PMIS 158014/187638 ASPHALT ROOFING

SECTION 07 58 00

ASPHALT ROOFING

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of furnishing and installing a self-adhering rolled roofing system.

1.2 SUBMITTALS

A. As specified in Section 01 33 00.

B. Manufacturer's catalog cuts and installation recommendations for the rolled roofing.

1.3 PRODUCT HANDLING

A. Deliver roofing in manufacturer's original, unopened, protective packaging. Comply with manufacturer's recommendations for protection.

1.4 GUARANTEE

A. Furnish a written 10-year minimum warranty on roofing products. Before beginning work, report to Contracting Officer if any specification requirements conflict with shingle manufacturer's warranty requirements.

PART 2 - PRODUCTS

2.1 ROLL ROOFING SYSTEM

A. Two layer self-adhering roofing system. Liberty SBS self-adhering Roofing system Manufactured by GAF or approved equal.

1. Base Sheet: Liberty Base/Ply sheet, Thickness 0.068 inches.

2. Cap sheet: Liberty Cap sheet, thickness 0.157.

2.2 METAL EDGING

A. 28-gauge galvanized steel. Provide prefinished or field paint to a dark brown or dark bronze color.

If field painted, apply a primer and two coats of paint.

PI-14-0001 07 56 00-2

PMIS 158014/187638 ASPHALT ROOFING

2.3 BIRD SPIKES

A. Stainless steel, up to 4 inches long, 180 degree protection. Premium Nixalite Model H or approved equal.

PART 3 - EXECUTION

3.1 INSPECTION

A. Surface to which the roofing is to be applied shall be even, smooth, sound, clean, and dry. Do not begin roofing work until surface deficiencies have been corrected.

3.2 DRIP EDGE

A. Install at top edge, eaves, and rakes using roofing nails 9 inches on center.

3.3 ROOFING

A. Install per manufactures recommendations.

3.4 BIRD SPIKES

A. Install to roof with adhesive. Install per manufactures recommendations.

PI…