This statement of work document outlines requirements for architectural and engineering services to design replacement cladding for a sterilization building at a Veterans Affairs medical center. The selected firm will provide site investigation, design development, construction documents, specifications, cost estimates, and construction period services including site visits. Key deliverables include schematic designs at 25% and 35% completion, and design development drawings and specifications at 65%, 95%, and 100% completion. The selected firm must incorporate all applicable VA design standards and codes, obtain necessary surveys, and have fire protection engineering plans certified. Construction period services are also required through project completion, including assistance with questions, submittal reviews, clarifications, site visits, and as-built drawings. The opportunity is associated with solicitation number 36C25623R0135 to replace cladding at the sterilization building of the Veterans Healthcare System of the Ozarks in Fayetteville, Arkansas for the Department of Veterans Affairs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 564-23-601_SITE MAP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work To Design
Replace Cladding Building 40 Sterilizer Project No. 564-23-601 Veterans Healthcare System of the Ozarks (VHSO), Fayetteville AR A. General Information A 1.0 Project Background, Description and Scope of Work Provide Architect/Engineer professional services to include site investigation, design development, construction documents, specifications, cost estimates, construction period services and construction site visits. VHSO has a requirement to design a project to remove and replace the existing internal and external sheet metal siding on the Sterilizer Building (B-40). Additionally, the project must replace the roofing sheet metal, all insulation, and develop an improved air flow design within the Sterilizer Building. The A/E must incorporate current design and construction best practices to update, modernize, and/or replace existing systems, infrastructure, and equipment as needed.
PERIOD OF PERFORMANCE
The delivery date for this contract shall be 180 days from Notice to Proceed. Performance time to include VA review of each submission as identified.
LOCATION
Veterans Healthcare System of the Ozarks Fayetteville AR Campus 1100 N College Ave.
Fayetteville, AR 72703
TERMS OF THE SOLICITATION
A. The term “responsibility,” used in the instructions that follow, includes architectural and engineering design, cost, schedule, and construction responsibility for completion of this project in accordance with the documents of this SOW. It is the responsibility of the Design Offeror or A/E to provide complete Design Documents (drawings and specifications) for a fully functional project. Omissions in this SOW and Technical Requirements do not relieve the Design Offeror from providing a complete and fully functioning project.
B. The terms “Design Team”, “Design Offeror”, or “A/E” refers to the successful design team. The design team shall consist of a Service Connected (Disabled) Veteran Owned Small Business architectural/engineering firm and all associated consultants and subcontractors.
C. The term “Design Team” or “engineer” refers to registered/licensed Architects and Engineering professionals.
D. The terms “the work and project” refers to the all site investigation, site survey, calculations, testing and design for documents to design and construct the subject project.
E. The term “VA” refers to the Veterans Healthcare System of the Ozarks, Fayetteville AR Campus F. The COR (Contracting Officer’s Representative) for this project is Josh Smith at 479-387-2871. josh.smith@va.gov G. The Contracting Officer for this project is TBD.
QUALITY ASSURANCE/QUALITY CONTROL (QA/QC)
The Design Offeror or A/E shall develop, execute, and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort. The A/E shall provide an outline of the actions that the firm will take during the design process to ensure a quality finished design is achieved.
COST ESTIMATE
A detailed estimate of construction cost (using RS Means or equivalent) and Market Study/Survey shall be provided with each design submission.
DRAWINGS
This project will utilize the latest version AutoCAD. All VA design guides and requirements can be found online at: http://www.cfm.va.gov/TIL/. Where conflicts occur between VA standards and model codes, the most stringent requirement shall govern.
SITE AND TOPOGRAPHY SURVEY
For this project a topographic survey is NOT required.
GEOTECHNICAL SURVEY
A geotechnical survey of the area is NOT required.
UTILITY SURVEY
During the design phase, the A/E will coordinate with VHSO Staff to obtain utility information to facilitate the design. Otherwise, what is not obtained shall be surveyed to extent necessary by the A/E. A/E shall procure any services required to adequately test and determine the capacity of the existing utility system.
ASBESTOS ABATEMENT SURVEY
An asbestos abatement survey of the area is NOT required.
FIRE PROTECTION ENGINEER REVIEW & CERTIFICATION
The A/E shall have the design plans and specifications reviewed by a registered Fire Protection Engineer (FPE) to ensure the design proceeds in accordance with Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) codes. The FPE’s review comments shall be provided along with each design submittal starting with the 65% Design Development drawings. With the Final 100% Construction Documents submittal, provide a FINAL certification letter from a registered FPE stating that the FINAL plans and specifications are in compliance with the current LSC and NFPA codes.
SEISMIC DESIGN
Seismic design is NOT required.
PHYSICAL SECURITY & BLAST DESIGN
NOT required for this design effort.
COMMISSIONING
Commissioning is not required for this design.
GOVERNMENT FURNISHED INFORMATION
The following is a list of government furnished information found on the VA’s Technical Information Library (TIL) website (http://www.cfm.va.gov/TIL/) to be used for this project, as applicable:
HVAC Design Manual for New, Replacement, Addition and Renovation of Existing VA Facilities
PG-18-1
Master Construction Specifications
PG-18-3
Design and Construction Procedures
PG-18-4
Standard Details and CAD Standards
PG-18-10
Design Manuals (by discipline)
PG-18-12
Design Guides (graphical, by function)
PG-18-15
Minimum Requirements for A/E Submissions
NOTE: Utilize the latest version of guidance at time of design award.
NOTE: The design effort shall not be limited to the documents referenced.
The AE shall utilize and design to all applicable standards on the VA TIL. Reference http://www.cfm.va.gov/TIL/ NOTE: The AE must submit a schedule for approval by VA showing completion dates of each deliverable within 15 days of NTP.
A 2.0 Design Deliverables
OBVAMC Design Submissions – Statement of Task:
1. Schematic Design
2. 35% Design Development (DD)
3. 65% Design Development (DD)
4. 95% Design Development (DD)
5. 100% Construction Documents (CD)
NOTE 1: Additional detailed design submission requirements can be found in VA Guide PG-18-15.
NOTE 2: The VA staff shall have a minimum of 16 calendar days to review and coordinate each AE design submissions. If the VA workload does not allow for a thorough review within the 16 calendar day timeframe, the AE shall not proceed to the next design phase until comments have been received from the VA. The AE will be entitled to a time only contract extension for the number of VA review days beyond 16 calendar days.
1. 25% Schematic Design: Investigate and survey project site. Verify any VA provided data. AE is responsible for collecting all data required for the design. The A/E is responsible for measuring and collecting actual field data that may be required. The A/E shall collaborate with VA staff/end user to develop conceptual and viable design options to meet the intended scope of work. The A/E shall develop schematic drawings and design options for review. This schematic design phase is an iterative process and requires close coordination back and forth with the VA COR/Project manager. The preliminary schematic design/layout will most likely require adjustment until a final plan/layout is officially approved by the hospital and COR. Dimensions, areas, spaces, etc. will need to be indicated clearly on the drawings. With respect to space, the AE needs to identify the size of the existing space, the space VA standard and proposed space for review and consideration. The AE shall work with the VA staff/COR until an acceptable plan is developed and approved in writing by the VA/COR. The AE final deliverables for this phase are (hard and electronic copies):
a. VHSO Approved Plan
b. Preliminary Cost Estimate (RS Means, Cost Works)
c. List of probable Specification Sections for this project
2. 35% Design Development: These drawings shall be at the largest scale possible and shall show the architectural layout of each floor, approximate room dimensioning/square footage, room identification, fire exists, chases, columns and other pertinent information necessary to provide information that will carry the design to the next review.
a. Drawings & Specifications: Provide one 22”x34” size D set, three 17”x22” size C sets and one unbound 11”x17” size B set of preliminary construction drawings. Provide one set of preliminary specifications indicating all of the AE proposed edits in a 3-hole punch binder. Drawings and specifications to indicate potential deductive bid alternates and any phasing requirements. Also, provide electronic copies (Drawings PDF format, Specifications in Word format).
b. Cost Estimate: Provide a detailed cost estimate indicating labor, material and equipment cost in RS Means or equivalent format. Estimate shall include Prime Contractors Overhead, Profit, Bond, and Labor Burden. Estimate shall indicate feasible deductive bid alternates to bring the construction cost within the allotted construction budget. This cost estimate shall be submitted in one hard copy with the Design Analysis and as an electronic copy.
c. Design Analysis: Provide a design analysis for each discipline indicating the design rational, thought process and design calculations (including actual field test and test date). Provide a summary of deductive bid alternates. Provide an initial review by the Fire Protection Engineer and their comments on the 25% design documents. Provide a draft preliminary detailed submittal register. Provide a list, by discipline, on what outstanding data or feedback is required from the Veterans Healthcare System of the Ozarks (VHSO). Provide one hard copy of the Design Analysis and one electronic copy.
NOTE: The AE shall not proceed with the 65% design without written concurrence from the VA COR.
3. 65% Design Development: This submission of drawings, specifications and cost estimate shall be very close to complete. This review by the VA shall be to validate that 35% comments were incorporated into the project. The construction documents should be sufficiently developed to cover all work items to be addressed by the project. No major items missing from this submission. The VAMC review of these documents should result in very minor comments to allow for the next 95% submission. AE shall provide a list of questions by discipline on anything that’s needed from the VA to continue and fully develop the next 95% design submission. Additionally, the AE shall provide minutes from the last design review meeting and shall provide responses to all VA comments noted or identified during the last review submission.
a. Drawings & Specifications: Submit in the same manner as the 35% DD submittal.
b. Cost Estimate & Design Analysis: Submit in the same manner as the 35% DD submittal.
c. FPE Certification: Provide review by the Fire Protection Engineer and indicate their comments.
4. 95% Design Development: This submission of drawings, specifications and cost estimate shall be complete. This review by the VA shall be to validate that 65% comments were incorporated into the project. There shall be nothing missing from the construction documents. The VAMC review of these documents should result in very minor comments to allow for the next submission to be final. If the comments of this set of documents results in numerous comments, then a 99% review or a check set of certain elements of the design may be required before the AE shall proceed to the 100% Final Construction Documents.
a. Drawings & Specifications: Submit in the same manner as the 65% DD submittal.
b. Cost Estimate: Submit in the same manner as the 65% DD submittal.
c. FPE Certification: Provide review by the Fire Protection Engineer and indicate their comments.
5. 100% Construction Documents: This submission shall incorporate all project requirements and previous comments. These documents shall be ready for bidding.
a. Drawings & Specifications: ALL ENGINEERS AND ARCHITECTS PROFESSIONAL “STAMPS” SHALL BE ON THIS SET OF DOUMENTS. Provide one 22”x34” size D set, four 17”x22” size C sets and two 11”x17” size B sets of FINAL construction drawings (one set of the 11”x17” size drawings to be unbound). Provide two sets of FINAL fully edited specifications (specs in a 3-hole punch notebook, printed on both sides of the paper). Drawings and specifications to indicate potential deductive bid alternates and any phasing requirements. Provide electronic copies of the entire package (Construction Drawings and Specifications). The drawings shall be as both AutoCAD and scanned individual PDF files per drawing. The specifications shall be in separate Word and separate PDF files for each specification section. Coordinate the naming & numbering of the files with the COR. Also, provide a PDF file for each complete volume of the specifications.
b. Cost Estimate: Submit FINAL cost estimate in the same manner as previous submittal.
c. FPE Certification: Provide a FINAL certification letter from a registered Fire Protection Engineer stating that the FINAL plans and specifications are in compliance with the current Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) codes.
Construction Period Services (CPS): AE shall provide full post design services construction period service IAW the Special Provisions of this contract.
· PRE-AWARD: CPS’s to include assistance with questions, request for information (RFI’s), meeting conference calls, clarifications and addendums during the construction solicitation phase. The AE must participate in pre-construction meetings.
· POST-AWARD: CPS’s also include full support through the construction phase to include but not limited to, assisting with questions, clarifications, inspections, reviewing and responding to RFI’s and review/coordination of contract modifications/change orders. Designing and estimating of design omissions. The AE will participate in weekly construction meetings.
· POST-AWARD SITE VISITS: CPS’s shall also include a minimum of 7 Site Visits during the construction phase of the project. Type and discipline of site visit shall be determined at the time of need by the COR.
· ASBUILTS: AE shall also incorporate contractor’s as-built/redline drawings on the latest version of AutoCAD and provide both electronic and two hard copy sets. Hard copy sets of as-built drawings shall consist of two 22”x34” size set, five 17”x22” size sets and two 11”x17” size sets.