P02 -SSN Draft RFI PITC End of Row Expansion.docx

DOCX document 185 KB Posted

Attached to
7G21--24-HW0106 PITC End of Row Expansion - New Buy (VA-24-00083647)
Solicitation number
36C10A24Q0103
Issued by

About this file

This document is a Performance Work Statement (PWS) for a federal contract opportunity related to a data center expansion project at the Philadelphia Information Technology Center (PITC) for the Department of Veterans Affairs (VA) Office of Information & Technology (OIT).

The VA requires materials and installation services for a fiber optic and copper Category 6A (CAT6A) structured cabling solution to support a 56-cabinet data center expansion. Key objectives include installing fiber and copper infrastructure between the end-of-row cabinets, core switches, and server cabinets, as well as providing testing, documentation, and warranty support. The PWS provides detailed technical requirements, standards, and deliverables. The period of performance is 150 business days from the date of award. This is a pre-solicitation notice, and the VA is requesting feedback on the draft PWS from interested contractors by June 12, 2024. The anticipated NAICS code is 238210 (Electrical Contractors and Other Wiring Installation Contractors).

View the file

Other files

File Type Posted
36C10A24Q0103.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PITC End of Row Expansion TAC Number: VA-24-00083647

PERFORMANCE WORK STATEMENT (PWS)

DEPARTMENT OF VETERANS AFFAIRS

Office of Information & Technology Infrastructure Operations (IO)

PITC End of Row Expansion

Date: May 24, 2024

VA-24-00083647

PWS Version Number: 1.0

Contents

1BACKGROUND4
2APPLICABLE DOCUMENTS4
3SCOPE OF WORK7
3.1End of row cabinets to core switches:7
3.2End of row cabinets to server cabinets:8
3.3Acronym definitions8
4PERFORMANCE DETAILS9
4.1PERFORMANCE PERIOD9
4.2PLACE OF PERFORMANCE10
4.3TRAVEL10
5SPECIFIC TASKS AND DELIVERABLES10
5.1PROJECT MANAGEMENT10
5.1.1CONTRACTOR PROJECT MANAGEMENT PLAN10
5.1.2REPORTING REQUIREMENTS11
5.1.3KICK OFF MEETING11
5.2SITE SURVEY12
5.3MATERIALS12
5.4INSTALLATION REQUIREMENTS13
5.4.1Task 1, Core installation - Core Switch to End of Row Cabinets13
5.4.2Task 2, End of Row to Intra-row Cabinets13
5.5Tools13
5.6Testing14
5.7As-Built Drawings15
5.8WARRANTY15
6GENERAL REQUIREMENTS15
6.1ENTERPRISE AND IT FRAMEWORK15
6.1.1VA TECHNICAL REFERENCE MODEL15
6.1.2FEDERAL IDENTITY, CREDENTIAL, AND ACCESS MANAGEMENT (FICAM)16
6.1.3INTERNET PROTOCOL VERSION 6 (IPV6)17
6.1.4TRUSTED INTERNET CONNECTION (TIC)18
6.1.5STANDARD COMPUTER CONFIGURATION18
6.1.6VETERAN FOCUSED INTEGRATION PROCESS (VIP)18
6.1.7PROCESS ASSET LIBRARY (PAL)19
6.1.8AUTHORITATIVE DATA SOURCES19
6.2SECURITY AND PRIVACY REQUIREMENTS20
6.2.1POSITION/TASK RISK DESIGNATION LEVEL(S)20
6.2.2CONTRACTOR PERSONNEL SECURITY REQUIREMENTS20
6.3METHOD AND DISTRIBUTION OF DELIVERABLES22
6.4PERFORMANCE METRICS23
6.5FACILITY/RESOURCE PROVISIONS24
6.6GOVERNMENT FURNISHED PROPERTY25
6.7SHIPMENT OF HARDWARE OR EQUIPMENT25
ADDENDUM A – ADDITIONAL VA REQUIREMENTS, CONSOLIDATED26
ADDENDUM B – VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY LANGUAGE33
N/A34

BACKGROUND

The Department of Veterans Affairs (VA), Office of Information & Technology (OIT), Infrastructure Operations (IO), National Data Center Operations & Logistics (NDCOL), Philadelphia Information Technology Center (PITC) strives to provide high quality, effective, and efficient Information Technology (IT) services to those responsible for providing care to the Veterans at the point-of-care as well as throughout all the points of the Veterans’ health care in an effective, timely and compassionate manner. VA depends on Information Management/Information Technology (IM/IT) systems to meet mission goals.

The VA requires materials and installation service for a fiber optic and copper Category 6A (CAT6A) structured cabling solution for a fifty-six (56) cabinet data center expansion in the PITC Data Center. The contractor shall adhere to VA’s Infrastructure Standard for Telecommunications Spaces; a copy of which will be provided during the site survey.

APPLICABLE DOCUMENTS

In the performance of the tasks associated with this Performance Work Statement, the Contractor shall comply with the following:

1. 44 U.S.C. § 3541-3549, “Federal Information Security Management Act (FISMA) of 2002”

2. “Federal Information Security Modernization Act of 2014”

3. Federal Information Processing Standards (FIPS) Publication 140-2, “Security Requirements For Cryptographic Modules”

4. FIPS Pub 199. Standards for Security Categorization of Federal Information and Information Systems, February 2004

5. FIPS Pub 200, Minimum Security Requirements for Federal Information and Information Systems, March 2016

6. FIPS Pub 201-2, “Personal Identity Verification of Federal Employees and Contractors,” August 2013

7. 10 U.S.C. § 2224, "Defense Information Assurance Program"

8. Carnegie Mellon Software Engineering Institute, Capability Maturity Model® Integration for Development (CMMI-DEV), Version 1.3 November 2010; and Carnegie Mellon Software Engineering Institute, Capability Maturity Model® Integration for Acquisition (CMMI-ACQ), Version 1.3 November 2010

9. 5 U.S.C. § 552a, as amended, “The Privacy Act of 1974”

10. Public Law 109-461, Veterans Benefits, Health Care, and Information Technology Act of 2006, Title IX, Information Security Matters

11. 42 U.S.C. § 2000d “Title VI of the Civil Rights Act of 1964”

12. VA Directive 0710, “Personnel Security and Suitability Program,” June 4, 2010, https://www.va.gov/vapubs/index.cfm

13. VA Handbook 0710, Personnel Security and Suitability Program, May 2, 2016, https://www.va.gov/vapubs/index.cfm

14. VA Directive and Handbook 6102, “Internet/Intranet Services,” August 5, 2019

15. 36 C.F.R. Part 1194 “Information and Communication Technology Standards and Guidelines,” January 18, 2017

16. Office of Management and Budget (OMB) Circular A-130, “Managing Federal Information as a Strategic Resource,” July 28, 2016

17. 32 C.F.R. Part 199, “Civilian Health and Medical Program of the Uniformed Services (CHAMPUS)”

18. NIST SP 800-66 Rev. 1, An Introductory Resource Guide for Implementing the Health Insurance Portability and Accountability Act (HIPAA) Security Rule, October 2008

19. Sections 504 and 508 of the Rehabilitation Act (29 U.S.C. § 794d), as amended, January 18, 2017

20. Homeland Security Presidential Directive (12) (HSPD-12), August 27, 2004

21. VA Directive 6500, “VA Cybersecurity Program,” January 24, 2019

22. VA Handbook 6500, “Risk Management Framework for VA Information Systems – Tier 3: VA Information Security Program,” March 10, 2015

23. VA Handbook 6500.2, “Management of Breaches Involving Sensitive Personal Information (SPI)”, July 28, 2016

24. VA Handbook 6500.3, “Assessment, Authorization, And Continuous Monitoring Of VA Information Systems,” February 3, 2014

25. VA Handbook 6500.5, “Incorporating Security and Privacy into the System Development Lifecycle”, March 22, 2010

26. VA Handbook 6500.6, “Contract Security,” March 12, 2010

27. VA Handbook 6500.8, “Information System Contingency Planning”, April 6, 2011

28. VA Handbook 6500.11, “VA Firewall Configuration”, August 22, 2017

29. OI&T Process Asset Library (PAL), https://www.va.gov/process/ . Reference Process Maps at https://www.va.gov/process/maps.asp and Artifact templates at https://www.va.gov/process/artifacts.asp

30. One-VA Technical Reference Model (TRM) (reference at https://www.va.gov/trm/TRMHomePage.aspx)

31. VA Directive 6508, “Implementation of Privacy Threshold Analysis and Privacy Impact Assessment,” October 15, 2014

32. VA Handbook 6508.1, “Procedures for Privacy Threshold Analysis and Privacy Impact Assessment,” July 30, 2015

33. VA Handbook 6510, “VA Identity and Access Management”, January 15, 2016

34. VA Directive and Handbook 6513, “Secure External Connections”, October 12, 2017

35. VA Directive 6300, Records and Information Management, September 21, 2018

36. VA Handbook, 6300.1, Records Management Procedures, March 24, 2010

37. NIST SP 800-37 Rev 1, Risk Management Framework for Information Systems and Organizations: A System Life Cycle Approach for Security and Privacy, December 2018

38. NIST SP 800-53 Rev. 4, Security and Privacy Controls for Federal Information Systems and Organizations, January 22, 2015

39. OMB Memorandum, “Transition to IPv6”, September 28, 2010

40. VA Directive 0735, Homeland Security Presidential Directive 12 (HSPD-12) Program, October 26, 2015

41. VA Handbook 0735, Homeland Security Presidential Directive 12 (HSPD-12) Program, March 24, 2014

42. OMB Memorandum M-06-18, Acquisition of Products and Services for Implementation of HSPD-12, June 30, 2006

43. OMB Memorandum 04-04, E-Authentication Guidance for Federal Agencies, December 16, 2003

44. OMB Memorandum 05-24, Implementation of Homeland Security Presidential Directive (HSPD) 12 – Policy for a Common Identification Standard for Federal Employees and Contractors, August 5, 2005

45. OMB memorandum M-11-11, “Continued Implementation of Homeland Security Presidential Directive (HSPD) 12 – Policy for a Common Identification Standard for Federal Employees and Contractors, February 3, 2011

46. OMB Memorandum, Guidance for Homeland Security Presidential Directive (HSPD) 12 Implementation, May 23, 2008

47. Federal Identity, Credential, and Access Management (FICAM) Roadmap and Implementation Guidance, December 2, 2011

48. NIST SP 800-116 Rev 1, Guidelines for the Use of Personal Identity Verification (PIV) Credentials in Facility Access, June 2018

49. OMB Memorandum M-07-16, Safeguarding Against and Responding to the Breach of Personally Identifiable Information, May 22, 2007

50. NIST SP 800-63-3, 800-63A, 800-63B, 800-63C, Digital Identity Guidelines, December 2017

51. NIST SP 800-157, Guidelines for Derived PIV Credentials, December 2014

52. NIST SP 800-164, Guidelines on Hardware-Rooted Security in Mobile Devices (Draft), October 2012

53. Draft National Institute of Standards and Technology Interagency Report (NISTIR) 7981 Mobile, PIV, and Authentication, March 2014

54. VA Memorandum, VAIQ #7100147, Continued Implementation of Homeland Security Presidential Directive 12 (HSPD-12), April 29, 2011 (reference https://www.voa.va.gov/documentlistpublic.aspx?NodeID=514)

55. IAM Identity Management Business Requirements Guidance document, May 2013, (reference Enterprise Architecture Section, PIV/IAM (reference https://www.voa.va.gov/documentlistpublic.aspx?NodeID=514)

56. VA Memorandum “Personal Identity Verification (PIV) Logical Access Policy Clarification,” July 17, 2019, https://www.voa.va.gov/DocumentView.aspx?DocumentID=4896

57. Trusted Internet Connections (TIC) Reference Architecture Document, Version 2.2, Federal Interagency Technical Reference Architectures, Department of Homeland Security, June 19, 2017, https://www.dhs.gov/sites/default/files/publications/TIC_Ref_Arch_v2.2_2017.pdf

58. OMB Memorandum M-08-05, “Implementation of Trusted Internet Connections (TIC), November 20, 2007

59. OMB Memorandum M-08-23, Securing the Federal Government’s Domain Name System Infrastructure, August 22, 2008

60. VA Memorandum, VAIQ #7497987, Compliance – Electronic Product Environmental Assessment Tool (EPEAT) – IT Electronic Equipment, August 11, 2014 (reference Document Libraries, EPEAT/Green Purchasing Section, https://www.voa.va.gov/documentlistpublic.aspx?NodeID=552)

61. Sections 524 and 525 of the Energy Independence and Security Act of 2007, (Public Law 110–140), December 19, 2007

62. Section 104 of the Energy Policy Act of 2005, (Public Law 109–58), August 8, 2005

63. Executive Order 13834, “Efficient Federal Operations”, dated May 17, 2018

64. Executive Order 13221, “Energy-Efficient Standby Power Devices,” August 2, 2001

65. VA Directive 0058, “VA Green Purchasing Program”, July 19, 2013

66. VA Handbook 0058, “VA Green Purchasing Program”, July 19, 2013

67. Office of Information Security (OIS) VAIQ #7424808 Memorandum, “Remote Access”, January 15, 2014, https://www.voa.va.gov/DocumentListPublic.aspx?NodeId=28

68. Clinger-Cohen Act of 1996, 40 U.S.C. §11101 and §11103

69. “Veteran Focused Integration Process (VIP) Guide 3.2”, December 2018, https://www.voa.va.gov/DocumentView.aspx?DocumentID=4371

70. VA Memorandum “Proper Use of Email and Other Messaging Services”, January 2, 2018, https://www.voa.va.gov/DocumentListPublic.aspx?NodeId=28

SCOPE OF WORK

The Contractor shall provide all materials and labor for an End of Row Structured Cabling Topology which consists of installing fiber optic and copper infrastructure, to support the End of Row Expansion. This includes fifty-six (56) cabinets standing in four (4) rows. Each row is separated by four (4) foot aisles. The structured cabling will include fiber connections to each of eight (8) end of row cabinets, fiber connections from each end of row cabinet to each of cabinets within each of the four (4) rows, as well as Category 6A (CAT6A) unshielded twisted pair copper connections to each cabinet.

End of row cabinets to core switches:

The vendor shall install as follows, each of eight (8) end of row cabinets will require twenty-four (24) fiber pairs and twenty-four (24) copper cables connected to core switches in distant cabinets. The fiber trunk cables will terminate into 1U fiber panels at the end of row cabinet and into a 1U fiber panel enclosure at core switch cabinets. The Cat6A copper bundles will terminate into 1U copper KMJ style patch panels in the end of row cabinets and in the core switch cabinet.

End of row cabinets to server cabinets:

Each of forty-eight (48) server cabinets (cabinets 2 through 13 in each row) require seventy-two (72) fiber pairs and a forty-eight (48) port CAT6A copper bundle connected to end of row cabinets. End of row cabinets 1 and 14, will provide thirty-six (36) fiber pairs and a twenty-four (24) port CAT6A copper connecting to cabinets 2 through 13. All fiber trunk cables will terminate into 1U fiber panel. The Cat6A copper bundles will terminate into 1U copper KMJ style patch panels.

Acronym definitions The following table has been provided for acronym and their meaning referenced throughout this PWS.

Acronym
Definition
ANSI
American National Standards Institute
DC
Direct Current
EIA
Electronic Industries Alliance
FSS
Facilities Standards Service
GbE
Gigabit Ethernet
Gb/s
Gigabit per second
ICC
Intermediate Cross Connect
IEC
International Electrotechnical Commission
IEEE
Institute of Electrical and Electronics Engineers
IT
Information Technology
ITOPS
IT Operations and Services
LAN
Local Area Network
MPO
Multi-Fiber Push On
NDCOL
National Data Center Operations and Logistics
NEC®
National Electrical Code®
NEMA
National Electrical Manufacturers Association
NFPA
National Fire Protection Association
NIC
Network Interface Card
OIT
Office of Information and Technology
OM
Optical Multimode
PBB
Primary Bonding Busbar
PDU
Power Distribution Unit
PVC
Polyvinyl Chloride
RBB
Rack Bonding Busbar
RBC
Rack Bonding Conductor
RCDD
Registered Communications Distribution Designer
RDC
Regional Data Center
RDC
Remote Distribution Cabinet
RU
Rack Unit
SBB
Secondary Bonding Busbar
SM
Single-mode
TBB
Telecommunication Bonding Backbone
TEBC
Telecommunications Equipment Bonding Conductor
TIA
Telecommunications Industry Association
TIL
Technical Information Library
TR
Telecommunications Room
UL
Underwriters Laboratories Inc
UTP
Unshielded Twisted Pair
VA
Department of Veterans Affairs

PERFORMANCE DETAILS

PERFORMANCE PERIOD

The Period of Performance (POP) for materials and installation shall be completed within 150 business days from date of Award. Actual POP will be as stated in the issued VA Award letter.

Any work at the Government site shall not take place on Federal holidays, weekends or after business hours unless directed by the Contracting Officer (CO).

There are eleven (11) Federal holidays set by law (USC Title 5 Section 6103) that VA follows:

Under current definitions, five are set by date:

New Year's DayJanuary 1
JuneteenthJune 19
Independence DayJuly 4
Veterans DayNovember 11
Christmas DayDecember 25

If any of the above falls on a Saturday, then Friday shall be observed as a holiday. Similarly, if one falls on a Sunday, then Monday shall be observed as a holiday.

The other six are set by a day of the week and month:

Martin Luther King's BirthdayThird Monday in January
Washington's BirthdayThird Monday in February
Memorial DayLast Monday in May
Labor DayFirst Monday in September
Columbus DaySecond Monday in October
ThanksgivingFourth Thursday in November

PLACE OF PERFORMANCE

Tasks under this PWS shall be performed in a VA facility located at:

Philadelphia Information Technology Center (PITC) 5000 Wissahickon Ave, Philadelphia, PA 19144

TRAVEL

The Government does not anticipate travel to perform the tasks associated with this effort.

SPECIFIC TASKS AND DELIVERABLES

The Contractor shall perform the following:

PROJECT MANAGEMENT

CONTRACTOR PROJECT MANAGEMENT PLAN

The Contractor shall deliver a Contractor Project Management Plan (CPMP) that lays out the Contractor’s approach timeline, and tools to be used in execution of the contract. The CPMP should take the form of both a narrative and graphic format that displays the schedule, milestones risks, and resource support. The CPMP shall also include how the Contractor shall coordinate and execute planned, routine, and ad hoc data collection reporting requests as identified within the PWS. The initial baseline CPMP shall be concurred upon and updated in accordance with Section B of the contract. The Contractor shall update and maintain the VA PM approved CPMP throughout the POP.

Deliverable:

A. Contractor Project Management Plan

REPORTING REQUIREMENTS

The Contractor shall provide the COR with weekly Progress Reports in electronic form in Microsoft Word and Project formats. The report shall include detailed instructions/explanations for each required data element, to ensure that data is accurate and consistent. These reports shall reflect data as of the last day of the preceding week.

The Weekly Progress Reports shall cover all work completed during the reporting period and work planned for the subsequent reporting period. The report shall also identify any problems that arose and a description of how the problems were resolved. If problems have not been completely resolved, the Contractor shall provide an explanation including their plan and timeframe for resolving the issue. The report shall also include an itemized list of all Information and Communication Technology (ICT) deliverables and their current Section 508 conformance status. The Contractor shall monitor performance against the CPMP and report any deviations. It is expected that the Contractor will keep in communication with VA accordingly so that issues that arise are transparent to both parties to prevent escalation of outstanding issues.

The Contractor shall conduct weekly status teleconference meetings to provide VA Project Manager with the status of task. In advance of each weekly status teleconference, the contractor will provide a weekly progress report.

Deliverable:

A. Weekly Progress Report B. Weekly Status Teleconference

KICK OFF MEETING

A technical kickoff meeting shall be held within seven (7) calendar days after award. The Contractor shall coordinate the date, time, and location (can be virtual) with the Contracting Officer (CO), the VA PM, as the Co-Chairperson, the Contract Specialist (CS), and the COR. The Contractor shall provide a draft agenda to the CO and VA PM at least three business days prior to the meeting. Upon Government approval of a final agenda, the Contractor shall distribute to all meeting attendees. During the kickoff-meeting, the Contractor shall present, for review and approval by the Government, the details of the intended approach, work plan, and project schedule. The Contractor shall distribute the meeting minutes of the kickoff meeting to the CO, COR and all attendees within three calendar days after the meeting.

Deliverable:

A. Meeting minutes

SITE SURVEY

The Contractor shall conduct a pre-bid site survey at the location indicated in section 4.2 of this PWS to identify any unique site considerations, potential installation issues that may affect the implementation of the solution, and to verify material list including cable lengths and any other specific requirements before submitting a proposal. The VA will provide floor plans which will identify each cabinet involved in the project and the anticipated cable pathway to be used.

Site surveys are schedule for TBD. (5) five business days prior to the scheduled site survey dates. The Contractor must provide the following details on the attendees including: First Name, Last Name, Company Name, and Prime Contractor company name represented if not the Prime.

Upon arrival at the VA facility, each Contractor representative must provide a government issued photo identification and review the guidelines for accessing a secure federal building. Each Contractor representative must sign a Confidentiality of Sensitive Information Non-disclosure Agreement before they will be allowed onto the datacenter floor.

MATERIALS

The Contractor shall provide all cabling installation in accordance with VA’s Infrastructure Standard for Telecommunications Spaces, a copy of which will be provided during the site survey period. The following is a list of VA approved material guidelines to consider when developing the design solution.

1) CAT6A cables and components shall be unshielded twisted pair. Cat 6A cabling is specified in standard ANSI/TIA-1179.

2) All cabling system components shall be of the same performance category across each entire channel. Components typically may not be mismatched with respect to performance category. For example, where copper telecommunications cabling is used, all components – channel cabling, patch panels, jacks, receptacles, and patch cabling – shall have the same category designation. However, mixed environments are acceptable when supporting a planned upgrade path. For instance, Category 6A (Cat 6A) U/UTP patch cords can be used with Cat 6 patch panels knowing that the performance of the entire channel is at the capability level of the lowest performing component until the upgrade plan is complete.

3) Communications cabling must not be painted. Paint, plaster, cleaners, abrasives, corrosive residues, or other contaminants may result in an undetermined alteration of the cable properties.

4) Optical Multimode-4 and -5 (OM4 and OM5) rated 850 nm laser- enhanced multi-cable fiber cable assemblies pre-terminated with MPO connectors are required. One cassette shall be used to provide LC interfaces at both ends of the horizontal or backbone link and will support one or two 12-strand cable assemblies or one 24-strand cable assembly for a total capacity of 6 or 12 duplex LC interfaces. Cassettes shall also be used to breakout 24- strand MPO fiber cables into three MPO connections of eight fiber strands.

5) Unused materials shall be submitted to the on-site POC before leaving the site. The miscellaneous line shall be used to provide and install cabling and ensure compliance with all installation requirements. The Contractor’s response to solicitation shall include a list of miscellaneous items required with a description of the need/use for each item listed and the quantity. Contractor is required to detail the types and quantities of materials and supplies to be used, how they will be used as part of vendor's installation methodology and approach for each location as applicable.

INSTALLATION REQUIREMENTS

Task 1, Core installation - Core Switch to End of Row Cabinets

a) The Contractor shall install and label all fiber cables, fiber patch cables, CAT6A cables, cabinet enclosures and patch panels in sequential order and any other equipment required to complete cabling job. The Contractor shall label all cables in adherence to VA’s Infrastructure Standard for Telecommunications Spaces. A copy of these standards well be provided during the sites survey.

b) The Contractor shall provide and install any cable management supply needed to keep cables in a neat and orderly fashion.

Task 2, End of Row to Intra-row Cabinets

a) The Contractor shall install and label all fiber cables, fiber patch cables, CAT6A cables, cabinet enclosures and patch panels in sequential order and any other equipment required to complete cabling job. The contractor shall label all cables in adherence to VA’s Infrastructure Standard for Telecommunications Spaces.

b) The Contractor shall provide and install any cable management supply needed to keep cables in a neat and orderly fashion.

Tools The Contractor is responsible for using their own tools, ladders and supplies to perform the installation.

Testing The Contractor shall perform cable testing as required by VA’s Telecommunications Infrastructure Standards listed below, to demonstrate that all installed equipment and cabling meets VA and industry standard specifications. The testing shall include every cable connection that is ran. The Contractor shall correct any material related installation issues and perform a retest to show the issue has been resolved.

a) The contractor shall test unshielded twisted pair cabling and components using the following standards.

a. ANSI/TIA-1152-A, Requirements for Field Test Instruments for Balanced Twisted-Pair Cabling

b. ANSI/TIA-568.0.D, Generic Telecommunications Cabling Standard

c. ANSI/TIA-568-1.D, Commercial Building Telecommunications Cabling Standard

d. ANSI/TIA-568-C.2, Balanced Twisted Pair Telecommunications Cabling and Components Standard

e. ANSI/TIA-606-C, Administration Standard for Commercial Telecommunications Infrastructure.

b) The contractor shall test fiber optic cabling and components using the following standards.

a. ANSI/TIA/EIA-455-1: Cable Flexing for Fiber Optic Interconnecting Devices

b. ANSI/TIA/EIA-455-2: Impact Test Measurements for Fiber Optic Devices

c. TIA/EIA-455-4: Fiber Optic Component Temperature Life Test

d. TIA/EIA-455-5: Humidity Test Procedure for Fiber Optic Components

e. TIA-455-6: Cable Retention Test Procedure for Fiber Optic Cable Interconnecting Devices

f. ANSI/TIA/EIA-455-8: Measurement of Splice or Connector Loss and Reflectance Using an OTDR

g. TIA-455-13: Visual and Mechanical Inspection of Fiber Optic Components, Devices, and Assemblies

h. TIA-455-21: Mating Durability Of Fiber Optic Interconnecting Devices

i. TIA/EIA-455-34: Interconnection Device Insertion Loss Test

j. TIA/EIA-455-36: Twist Test For Fiber Optic Connecting Devices

k. TIA-455-78: Optical Fibers Part 1-40: Measurement Methods and Test Procedures – Attenuation

l. ANSI/TIA-455-107: Determination of Component Reflectance or Link/System Return Loss Using a Loss Test Set

m. ANSI/TIA/EIA-455-171: Attenuation by Substitution Measurement for Short-Length Multimode Graded-Index and Single-Mode Optical Fiber Cable Assemblies

n. ANSI/TIA/EIA-455-185: Strength of Coupling Mechanism for Fiber Optic Interconnecting Devices

o. ANSI/TIA/EIA-455-188: Low-Temperature Testing of Fiber Optic Components

The Contractor shall capture and provide the results of the cable test information in a Cable Installation Test Reports for both fiber optic and copper cables to be delivered in pdf or excel format.

Deliverables:

A. Fiber Optic Cable Installation Test Report B. Copper Cable Installation Test Report

As-Built Drawings The Contractor shall provide as-built drawings to include the following:

· All equipment installed by vendor in each cabinet

· Rack elevation drawings for each rack

· Cable routes and termination points for each cable run The vendor shall provide a listing of all cables installed which shall include the rack location, rack unit (RU) number and port numbers for each cable installed. VA will supply room and floor diagrams for the as-built drawings to be generated by the Contractor.

Deliverable:

A. As-Built Drawings

WARRANTY

The Contractor shall warrant parts a minimum of three (3) years covering defects in materials and workmanship.

GENERAL REQUIREMENTS

ENTERPRISE AND IT FRAMEWORK

VA TECHNICAL REFERENCE MODEL

The Contractor shall support the VA enterprise management framework. In association with the framework, the Contractor shall comply with OI&T Technical Reference Model (VA TRM). The VA TRM is one component within the overall Enterprise Architecture (EA) that establishes a common vocabulary and structure for describing the information technology used to develop, operate, and maintain enterprise applications. Moreover, the VA TRM, which includes the Standards Profile and Product List, serves as a technology roadmap and tool for supporting OI&T. Architecture & Engineering Services (AES) has overall responsibility for the VA TRM.

FEDERAL IDENTITY, CREDENTIAL, AND ACCESS MANAGEMENT (FICAM)

The Contractor shall ensure Commercial Off-The-Shelf (COTS) product(s), software configuration and customization, and/or new software are Personal Identity Verification (PIV) card-enabled by accepting HSPD-12 PIV credentials using VA Enterprise Technical Architecture (ETA), https://www.ea.oit.va.gov/EAOIT/VA_EA/Enterprise_Technical_Architecture.asp, and VA Identity and Access Management (IAM) approved enterprise design and integration patterns, https://www.oit.va.gov/library/recurring/edp/index.cfm. The Contractor shall ensure all Contractor delivered applications and systems comply with the VA Identity, Credential, and Access Management policies and guidelines set forth in the VA Handbook 6510 and align with the Federal Identity, Credential, and Access Management Roadmap and Implementation Guidance v2.0.

The Contractor shall ensure all Contractor delivered applications and systems provide user authentication services compliant with the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-63-3, VA Handbook 6500 Appendix F, “VA System Security Controls”, and VA IAM enterprise requirements for direct, assertion based authentication, and/or trust based authentication, as determined by the design and integration patterns. Direct authentication at a minimum must include Public Key Infrastructure (PKI) based authentication supportive of PIV card and/or Common Access Card (CAC), as determined by the business need.

The Contractor shall ensure all Contractor delivered applications and systems conform to the specific Identity and Access Management PIV requirements set forth in the Office of Management and Budget (OMB) Memoranda M-04-04, M-05-24, M-11-11, and NIST Federal Information Processing Standard (FIPS) 201-2. OMB Memoranda M-04-04, M-05-24, and M-11-11 can be found at: https://obamawhitehouse.archives.gov/sites/default/files/omb/assets/omb/memoranda/fy04/m04-04.pdf, https://obamawhitehouse.archives.gov/sites/default/files/omb/assets/omb/memoranda/fy2005/m05-24.pdf, and https://obamawhitehouse.archives.gov/sites/default/files/omb/memoranda/2011/m11-11.pdf respectively. Contractor delivered applications and systems shall be on the FIPS 201-2 Approved Product List (APL). If the Contractor delivered application and system is not on the APL, the Contractor shall be responsible for taking the application and system through the FIPS 201 Evaluation Program.

The Contractor shall ensure all Contractor delivered applications and systems support:

1. Automated provisioning and are able to use enterprise provisioning service.

2. Interfacing with VA’s Master Veteran Index (MVI) to provision identity attributes, if the solution relies on VA user identities. MVI is the authoritative source for VA user identity data.

3. The VA defined unique identity (Secure Identifier [SEC ID] / Integrated Control Number [ICN]).

4. Multiple authenticators for a given identity and authenticators at every Authenticator Assurance Level (AAL) appropriate for the solution.

5. Identity proofing for each Identity Assurance Level (IAL) appropriate for the solution.

6. Federation for each Federation Assurance Level (FAL) appropriate for the solution, if applicable.

7. Two-factor authentication (2FA) through an applicable design pattern as outlined in VA Enterprise Design Patterns.

8. A Security Assertion Markup Language (SAML) implementation if the solution relies on assertion based authentication. Additional assertion implementations, besides the required SAML assertion, may be provided as long as they are compliant with NIST SP 800-63-3 guidelines.

9. Authentication/account binding based on trusted Hypertext Transfer Protocol (HTTP) headers if the solution relies on Trust based authentication.

10. Role Based Access Control.

11. Auditing and reporting capabilities.

12. Compliance with VIEWS 00155984, PIV Logical Access Policy Clarification https://www.voa.va.gov/DocumentView.aspx?DocumentID=4896.

The required Assurance Levels for this specific effort are Identity Assurance Level 3, Authenticator Assurance Level 3, and Federation Assurance Level 3.

INTERNET PROTOCOL VERSION 6 (IPV6)

The Contractor solution shall support the latest Internet Protocol Version 6 (IPv6) based upon the directives issued by the Office of Management and Budget (OMB) on August 2, 2005 (https://obamawhitehouse.archives.gov/sites/default/files/omb/assets/omb/memoranda/fy2005/m05-22.pdf) and September 28, 2010 (https://obamawhitehouse.archives.gov/sites/default/files/omb/assets/egov_docs/transition-to-ipv6.pdf). IPv6 technology, in accordance with the USGv6 Profile, NIST Special Publication (SP) 500-267 (https://nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication500-267.pdf), the Technical Infrastructure for USGv6 Adoption (https://www.nist.gov/programs-projects/usgv6-program), and the NIST SP 800 series applicable compliance (https://csrc.nist.gov/publications/sp) shall be included in all IT infrastructures, application designs, application development, operational systems and sub-systems, and their integration. In addition to the above requirements, all devices shall support native IPv6 and/or dual stack (IPv6 / IPv4) connectivity without additional memory or other resources being provided by the Government, so that they can function in a mixed environment. All public/external facing servers and services (e.g. web, email, DNS, ISP services, etc.) shall support native IPv6 and/or dual stack (IPv6/ IPv4) users and all internal infrastructure and applications shall communicate using native IPv6 and/or dual stack (IPv6/ IPv4) operations. Guidance and support of improved methodologies which ensure interoperability with legacy protocol and services in dual stack solutions, in addition to OMB/VA memoranda, can be found at: https://www.voa.va.gov/documentlistpublic.aspx?NodeID=282.

TRUSTED INTERNET CONNECTION (TIC)

The Contractor solution shall meet the requirements outlined in Office of Management and Budget Memorandum M08-05 mandating Trusted Internet Connections (TIC) (https://obamawhitehouse.archives.gov/sites/default/files/omb/assets/omb/memoranda/fy2008/m08-05.pdf), M08-23 mandating Domain Name System Security (NSSEC) (https://obamawhitehouse.archives.gov/sites/default/files/omb/assets/omb/memoranda/fy2008/m08-23.pdf), and shall comply with the Trusted Internet Connections (TIC) Reference Architecture Document, Version 2.0 https://www.dhs.gov/sites/default/files/publications/TIC_Ref_Arch_v2.2_2017.pdf.

STANDARD COMPUTER CONFIGURATION

The Contractor IT end user solution that is developed for use on standard VA computers shall be compatible with and be supported on the standard VA operating system, currently Windows 10 (64bit), Internet Explorer 11 and Office 365 ProPlus. Applications delivered to VA and intended to be deployed to Windows 10 workstations shall be delivered as a signed .msi package with switches for silent and unattended installation and updates shall be delivered in signed .msp file formats for easy deployment using System Center Configuration Manager (SCCM) VA’s current desktop application deployment tool. Signing of the software code shall be through a vendor provided certificate that is trusted by VA using a code signing authority such as Verizon/Cybertrust or Symantec/VeriSign. The Contractor shall also ensure and certify that their solution functions as expected when used from a standard VA computer, with non-admin, standard user rights that have been configured using the United States Government Configuration Baseline (USGCB) and Defense Information Systems Agency (DISA) Secure Technical Implementation Guide (STIG) specific to the particular client operating system being used.

VETERAN FOCUSED INTEGRATION PROCESS (VIP)

The Contractor shall support VA efforts IAW the Veteran Focused Integration Process (VIP). VIP is a Lean-Agile framework that services the interest of Veterans through the efficient streamlining of activities that occur within the enterprise. The VIP Guide can be found at https://www.voa.va.gov/DocumentView.aspx?DocumentID=4371. The VIP framework creates an environment delivering more frequent releases through a deeper application of Agile practices. In parallel with a single integrated release process, VIP will increase cross-organizational and business stakeholder engagement, provide greater visibility into projects, increase Agile adoption and institute a predictive delivery cadence. VIP is now the single authoritative process that IT projects must follow to ensure development and delivery of IT products

PROCESS ASSET LIBRARY (PAL)

The Contractor shall perform their duties consistent with the processes defined in the OIT Process Asset Library (PAL). The PAL scope includes the full spectrum of OIT functions and activities, such as VIP project management, operations, service delivery, communications, acquisition, and resource management. PAL serves as an authoritative and informative repository of searchable processes, activities or tasks, roles, artifacts, tools and applicable standards and guides to assist the OIT workforce, Government and Contractor personnel. The Contractor shall follow the PAL processes to ensure compliance with policies and regulations and to meet VA quality standards. The PAL includes the contractor onboarding process consistent with Section 6.2.2 and can be found at https://www.va.gov/PROCESS/artifacts/maps/process_CONB_ext.pdf. The main PAL can be accessed at www.va.gov/process.

AUTHORITATIVE DATA SOURCES

The VA Enterprise Architecture Repository (VEAR) is one component within the overall Enterprise Architecture (EA) that establishes the common framework for data taxonomy for describing the data architecture used to develop, operate, and maintain enterprise applications. The Contractor shall comply with the department’s Authoritative Data Source (ADS) requirement that VA systems, services, and processes throughout the enterprise shall access VA data solely through official VA ADSs where applicable, see below. The Information Classes which compose each ADS are located in the VEAR, in the Data & Information domain. The Contractor shall ensure that all delivered applications and system solutions support:

1. Interfacing with VA’s Master Veteran Index (MVI) to provision identity attributes, if the solution relies on VA user identities. MVI is the authoritative source for VA user identity data.

2. Interfacing with Capital Asset Inventory (CAI) to conduct real property record management actions, if the solution relies on real property records data. CAI is the authoritative source for VA real property record management data.

3. Interfacing with electronic Contract Management System (eCMS) for access to contract, contract line item, purchase requisition, offering vendor and vendor, and solicitation information above the micro-purchase threshold, if the solution relies on procurement data. ECMS is the authoritative source for VA procurement actions data.

4. Interfacing with HRSmart Human Resources Information System to conduct personnel action processing, on-boarding, benefits management, and compensation management, if the solution relies on personnel data. HRSmart is the authoritative source for VA personnel information data.

5. Interfacing with Vet360 to access personal contact information, if the solution relies on VA Veteran personal contact information data. Vet360 is the authoritative source for VA Veteran Personal Contact Data.

6. Interfacing with VA/Department of Defense (DoD) Identity Repository (VADIR) for determining eligibility for VA benefits under Title 38, if the solution relies on qualifying active duty military service data. VADIR is the authoritative source for Qualifying Active Duty military service in VA.

SECURITY AND PRIVACY REQUIREMENTS

POSITION/TASK RISK DESIGNATION LEVEL(S)

In accordance with VA Handbook 0710, Personnel Security and Suitability Program, the position sensitivity and the level of background investigation commensurate with the required level of access for the following tasks within the PWS are:

Position Sensitivity and Background Investigation Requirements by Task

Task Number
Tier1 / Low Risk
Tier 2 / Moderate Risk
Tier 4 / High Risk
5.1
|X|
|_|
|_|
5.2
|_|
|X|
|_|
5.3
|X|
|_|
|_|
5.4
|_|
|X|
|_|
5.5
|_|
|X|
|_|
5.6
|_|
|X|
|_|
5.7
|X|
|_|
|_|
5.8
|_|
|X|
|_|

The Tasks identified above and the resulting Position Sensitivity and Background Investigation requirements identify, in effect, the Background Investigation requirements for Contractor individuals, based upon the tasks the particular Contractor individual will be working. The submitted Contractor Staff Roster must indicate the required Background Investigation Level for each Contractor individual based upon the tasks the Contractor individual will be working, in accordance with their submitted proposal.

CONTRACTOR PERSONNEL SECURITY REQUIREMENTS

Contractor Responsibilities:

1. The Contractor shall prescreen all personnel requiring access to the computer systems to ensure they maintain the appropriate Background Investigation, and are able to read, write, speak and understand the English language.

Within 3 business days after award, the Contractor shall provide a roster of Contractor and Subcontractor employees to the COR to begin their background investigations in accordance with the PAL template artifact. The Contractor Staff Roster shall contain the Contractor’s Full Name, Date of Birth, Place of Birth, individual background investigation level requirement (based upon Section 6.2 Tasks), etc. The Contractor shall submit full Social Security Numbers either within the Contractor Staff Roster or under separate cover to the COR. The Contractor Staff Roster shall be updated and provided to VA within 1 day of any changes in employee status, training certification completion status, Background Investigation level status, additions/removal of employees, etc. throughout the Period of Performance. The Contractor Staff Roster shall remain a historical document indicating all past information and the Contractor shall indicate in the Comment field, employees no longer supporting this contract. The preferred method to send the Contractor Staff Roster or Social Security Number is by encrypted e-mail. If unable to send encrypted e-mail, other methods which comply with FIPS 140-2 are to encrypt the file, use a secure fax, or use a traceable mail service.

1. The Contractor should coordinate with the location of the nearest VA fingerprinting office through the COR. Only electronic fingerprints are authorized. The Contractor shall bring their completed Security and Investigations Center (SIC) Fingerprint request form with them (see paragraph d.4. below) when getting fingerprints taken.

b. The Contractor shall ensure the following required forms are submitted to the COR within 5 days after contract award:

1) Optional Form 306

2) Self-Certification of Continuous Service

3) VA Form 0710

4) Completed SIC Fingerprint Request Form The Contractor personnel shall submit all required information related to their background investigations (completion of the investigation documents (SF85, SF85P, or SF 86) utilizing the Office of Personnel Management’s (OPM) Electronic Questionnaire for Investigations Processing (e-QIP) after receiving an email notification from the Security and Investigation Center (SIC).

The Contractor employee shall certify and release the e-QIP document, print and sign the signature pages, and send them encrypted to the COR for electronic submission to the SIC. These documents shall be submitted to the COR within 3 business days of receipt of the e-QIP notification email. (Note: OPM is moving towards a “click to sign” process. If click to sign is used, the Contractor employee should notify the COR within 3 business days that documents were signed via e-QIP).

1. The Contractor shall be responsible for the actions of all personnel provided to work for VA under this contract. In the event that damages arise from work performed by Contractor provided personnel, under the auspices of this contract, the Contractor shall be responsible for all resources necessary to remedy the incident.

1. A Contractor may be granted unescorted access to VA facilities and/or access to VA Information Technology resources (network and/or protected data) with a favorably adjudicated Special Agreement Check (SAC), completed training delineated in VA Handbook 6500.6 (Appendix C, Section 9), signed “Contractor Rules of Behavior”, and with a valid, operational PIV credential for PIV-only logical access to VA’s network. A PIV card credential can be issued once your SAC has been favorably adjudicated and your background investigation has been scheduled by OPM. However, the Contractor will be responsible for the actions of the Contractor personnel they provide to perform work for VA. The investigative history for Contractor personnel working under this contract must be maintained in the database of OPM.

1. The Contractor, when notified of an unfavorably adjudicated background investigation on a Contractor employee as determined by the Government, shall withdraw the employee from consideration in working under the contract.

Failure to comply with the Contractor personnel security investigative requirements may result in loss of physical and/or logical access to VA facilities and systems by Contractor and Subcontractor employees and/or termination of the contract for default.

Identity Credential Holders must follow all HSPD-12 policies and procedures as well as use and protect their assigned identity credentials in accordance with VA policies and procedures, displaying their badges at all times, and returning the identity credentials upon termination of their relationship with VA.

Deliverable:

A. Contractor Staff Roster

METHOD AND DISTRIBUTION OF DELIVERABLES

The Contractor shall deliver documentation in electronic format, unless otherwise directed in Section B of the solicitation/contract. Acceptable electronic media include: MS Word 2000/2003/2007/2010, MS Excel 2000/2003/2007/2010, MS PowerPoint 2000/2003/2007/2010, MS Project 2000/2003/2007/2010, MS Access 2000/2003/2007/2010, MS Visio 2000/2002/2003/2007/2010, AutoCAD 2002/2004/2007/2010, and Adobe Postscript Data Format (PDF).

PERFORMANCE METRICS

Performance Objective The table below defines the Performance Standards and Acceptable Levels of Performance associated with this effort.

Performance Standard
Acceptable Levels of Performance
A. Technical / Quality of Product or Service
1. Demonstrates understanding of requirements

2. Efficient and effective in meeting requirements

3. Meets technical needs and mission requirements

4. Provides quality services/products

5. Incorporates “ease of use” Human Centered Design principles in any software developed.

Satisfactory or higher

B. Project Milestones and Schedule
1. Established milestones and project dates are met

2. Products completed, reviewed, delivered in accordance with the established schedule

3. Notifies customer in advance of potential problems Satisfactory or higher

C. Cost & Staffing
1. Currency of expertise and staffing levels appropriate to perform tasks required

2. Personnel possess necessary knowledge, skills and abilities to perform tasks Satisfactory or higher

D. Management
1. Integration and coordination of all activities to execute effort
Satisfactory or higher

The COR will utilize a Quality Assurance Surveillance Plan (QASP) throughout the life of the contract to ensure that the Contractor is performing the services required by this PWS in an acceptable level of performance. The Government reserves the right to alter or change the surveillance methods in the QASP at its own discretion. A Performance Based Service Assessment will be used by the COR in accordance with the QASP to assess Contractor performance.

FACILITY/RESOURCE PROVISIONS

The Government will provide office space, telephone service and system access when authorized contract staff work at a Government location as required in order to accomplish the Tasks associated with this PWS. All procedural guides, reference materials, and program documentation for the project and other Government applications will also be provided on an as-needed basis.

The Contractor shall request other Government documentation deemed pertinent to the work accomplishment directly from the Government officials with whom the Contractor has contact. The Contractor shall consider the COR as the final source for needed Government documentation when the Contractor fails to secure the documents by other means. The Contractor is expected to use common knowledge and resourcefulness in securing all other reference materials, standard industry publications, and related materials that are pertinent to the work.

VA may provide remote access to VA specific systems/network in accordance with VA Handbook 6500, which requires the use of a VA approved method to connect external equipment/systems to VA’s network. Citrix Access Gateway (CAG) is the current and only VA approved method for remote access users when using or manipulating VA information for official VA Business. VA permits CAG remote access through approved Personally Owned Equipment (POE) and Other Equipment (OE) provided the equipment meets all applicable 6500 Handbook requirements for POE/OE. All of the security controls required for Government furnished equipment (GFE) must be utilized in approved POE or OE. The Contractor shall provide proof to the COR for review and approval that their POE or OE meets the VA Handbook 6500 requirements and VA Handbook 6500.6 Appendix C, herein incorporated as Addendum B, before use. CAG authorized users shall not be permitted to copy, print or save any VA information accessed via CAG at any time. VA prohibits remote access to VA’s network from non-North Atlantic Treaty Organization (NATO) countries. The exception to this are countries where VA has approved operations established (e.g. Philippines and South Korea). Exceptions are determined by the COR in coordination with the Information Security Officer (ISO) and Privacy Officer (PO).

This remote access may provide access to VA specific software such as Veterans Health Information System and Technology Architecture (VistA), ClearQuest, PAL, Primavera, and Remedy, including appropriate seat management and user licenses, depending upon the level of access granted. The Contractor shall utilize government-provided software development and test accounts, document and requirements repositories, etc. as required for the development, storage, maintenance and delivery of products within the scope of this effort.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .