This document provides an Independent Government Cost Estimate (IGCE) template for a construction project at the Salt Lake City VA Medical Center. The IGCE breaks down estimated costs by division and includes labor and material estimates. It provides a preliminary design for renovations and expansion of EHRM training and administrative space.

The project requires design and construction services for expanding existing network connectivity infrastructure. The design team must complete construction documents, including drawings, specifications, and commissioning. The period of performance for design is 238 calendar days. The solicitation will be set aside 100% for Service-Disabled Veteran-Owned Small Businesses. The contracting agency is the VA Technology Acquisition Center in Austin. Responses are due by June 14, 2021. The IGCE template provides a framework for estimating project costs by division to support the solicitation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMATION

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEETSHEET NO.1OF26SHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

V.A. MEDICAL CENTERNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, Jeremiahx1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMNOTESTOTAL
ABCD
DIVISION 0-SPECIAL SECTIONS$ - 0
DIVISION 1-GENERAL REQUIREMENTS$ - 0
DIVISION 2-EXISTING CONDITIONS$ - 0
DIVISION 3-CONCRETE$ - 0
DIVISION 4-MASONRY$ - 0
DIVISION 5-METALS$ - 0
DIVISION 6-WOOD AND PLASTIC$ - 0
DIVISION 7-THERMAL AND MOISTURE PROTECTION$ - 0
DIVISION 8-DOORS AND WINDOWS$ - 0
DIVISION 9-FINISHES$ - 0
DIVISION 10-SPECIALTIES$ - 0
DIVISION 11-EQUIPMENT$ - 0
DIVISION 12-FURNISHINGS$ - 0
DIVISION 13-SPECIAL CONSTRUCTION$ - 0
DIVISION 14-CONVEYING EQUIPMENT$ - 0
DIVISION 21-FIRE SUPPRESSION$ - 0
DIVISION 22-PLUMBING$ - 0
DIVISION 23-HEAT, VENTILATING, AND AIR CONDITIONING$ - 0
DIVISION 26-ELECTRICAL$ - 0
DIVISION 27-COMMUNICATIONS$ - 0
DIVISION 28-ELECTRONIC SAFETY AND SECURITY$ - 0
DIVISION 31-EARTHWORK$ - 0
DIVISION 32-EXTERIOR IMPROVEMENTS$ - 0
DIVISION 33-UTILITIES$ - 0
DIVISION 34-TRANSPORTATION$ - 0
SUB-TOTAL$ - 0
OVERHEAD@10.00%$ - 0
PROFIT@10.00%$ - 0
BONDS@3.00%$ - 0
PROJECT TOTAL:$ - 0

VA FORM 10-6238

&A

&D

Div 0 Special Sections

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.2OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VA0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 0 Special Sections
$0.00$0.00$0
Hr$0.00$0.00$0
Hr$0.00$0.00$0
Hr$0.00$0.00$0
Hr$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&A

&D

Div 1 General Requirements

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.3OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Divison 1 General Requirements
$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

Div 2 Existing Conditions

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.4OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 2 Existing Conditions
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&A

&D

Div 3 Concrete

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.5OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 3 Concrete
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&A

&D

Div 4 Masonry

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.6OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 4 Masonry
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&A

&D

Div 5 Metals

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.7OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 5 Metals
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&A

&D

Div 6 Wood & Plastic

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.8OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99xNO DESIGNPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 6 Wood & Plastic
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&A

&D

Div 7 Thermal & Moisture Protec

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.9OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 7 Thermal & Moisture Protection
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 8 Doors & Windows

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.10OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 8 Doors & Windows
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 9 Finishes

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.11OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 9 Finishes
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 10 Specialties

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.12OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 10 Specialties
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 11 Equipment

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.13OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 11 Equipment
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 12 Furnishings

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.14OF26SHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 12 Furnishings
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 13 Special Construction

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.15OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 13 Special Construction
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions$0.00Small Business Utilization$0.00$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Division 14 Conveying Equipment

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.16OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 14 Conveying Equipment
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 21 Fire Suppression

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.17OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 21 Fire Suppression
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 22 Plumbing

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.18OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 22 Plumbing
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 23 HVAC

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.19OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 23 Heat, Ventilating, and Air Conditioning
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 26 Electrical

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.20OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 26 Electrical
-$0.00$ - 0$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 27 Communications

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.21OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 27 Communications
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 28 Electronic Safety & Secu

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.22OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 28 Electronic Safety & Security
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 31 Earthwork

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.23OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 31 Earthwork
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 32 Exterior Improvements

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.24OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
Salt Lake City VACOMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 32 Exterior Improvements
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 33 Utilities

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.25OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 33 Utilities
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

Div 34 Transportation

DATE
CONSTRUCTION PROGRAM - ESTIMATE WORKSHEET12/31/99SHEET NO.26OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

Dec-99V.A. MEDICAL CENTERDec-99NO DESIGNXPRELIMINARY
0COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
Percy, JeremiahX1DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 34 Transportation
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0
VA FORM 10-6238

&D

File details come from the government source that posted it. Updated .