This document is a Statement of Work (SOW) for installing outdoor pavilions at the VA Roseburg Healthcare System in Roseburg, Oregon. The project involves trench excavation, power and lighting installation for three pavilions, and complete construction management. The total project scope includes providing all necessary supervision, labor, materials, and equipment, with a project timeline of 180 days from the Notice to Proceed.
Key project details include bi-weekly project meetings, on-site contractor representation, and mandatory HIPAA training for all personnel. The estimated project value ranges between $250,000 and $500,000, targeting small businesses with NAICS code 238190 (Other Foundation, Structure, and Building Exterior Contractors) and a small business size standard of $19 million. The project is being managed by the Department of Veterans Affairs Veterans Health Administration, Veterans Integrated Service Network 20, with the work located at 913 NW Garden Valley Blvd, Roseburg, OR 97471.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P01-653-25-104 Install Outdoor Pavilions 100P Specification Set.pdf | ||
| 36C26026R0010.docx | DOCX document | |
| P01-653-25-104 Install Outdoor Pavilions 100P Drawing Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUPPLEMENT B
STATEMENT OF WORK
Install Outdoor Pavilions Project Number 653-25-104
BACKGROUND:
The project is located at the VA Roseburg Healthcare System main campus 913 NW Garden Valley Blvd. Roseburg, OR 97471. In this project, the contractor shall install power, lighting and three pavilions. The Contractor shall provide all supervision, labor, materials and equipment for this project. See attached drawings and specifications for further details on this project.
1.0 DESCRIPTION OF WORK
The following items are intended to indicate the general scope of work for the project. The contractor shall complete all work included in the contract documents provided in this solicitation.
· Trench excavation and backfill for footing and utility installation.
· Install power and lighting for pavilions on pads 1 and 4.
· Purchase and install three pavilions.
1.0.1 Project Management: This project will require a high level of coordination with VA staff. Regularly scheduled project meetings shall be required in order to facilitate this communication.
1.0.2 Construction Inspection: The Contractor shall develop and implement a Quality control plan that includes project inspection for the duration of the construction period of the project in accordance with specification.
1.0.3 Construction: The Contractor shall provide all supervision, labor, materials and equipment for demolition and installation in construction project areas.
1.1 Life Safety: When life safety is impacted, the Contractor shall design interim life safety measures as part of the construction documents.
1.2 Project Management
1.2.1 Project meetings shall be held on a bi-weekly basis or more frequently if needed.
1.2.2 The contractor shall plan and coordinate the project meetings.
1.2.3 VA meeting room facilities may be utilized for project meetings. The Contractor shall coordinate with Facilities Management Service (Building 10) for use of VA facilities.
1.2.4 The Contractor shall have an authorized representative on site at all times during project construction. The authorized representative shall have the authority to receive instruction from the Government and direct the actions of Contractor employees and all subcontractors.
1.2.5 Health Insurance Portability and Accountability Act of 1996 (HIPAA) training will be required for all contractor and subcontractor personnel. This training will be conducted by Roseburg VAHCS and all participants will be required to sign the HIPAA agreement.
1.2.
Deliverables 1.2.1.
After Task Order Award a Kickoff meeting will be held and a Notice to Proceed (NTP) will be issued within 10 days of the Kickoff meeting. After which the contractor will have a total of 180 days to complete the project (Including submittals, material lead time and closeout documents).
1.3.
References
The following criteria shall be used to develop the design (including but not limited to):
Technical Information Library http://www.cfm.va.gov/TIL/
Design Manuals
PG-18-10
Design Guides
PG-18-12
Applicable NFPA Codes, and VA Fire Safety Criteria
AFGE Master Agreement