P01 Class II Precautions - Abate Cental Chase FINAL.pdf

PDF 176 KB Posted

Attached to
Z1DA--CON Project 667-18-111 Abate Central Chase / Replace Fire Main Federal contract opportunity
Solicitation number
36C25622R0084
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document outlines infection control precautions for a construction project at the Overton Brooks VAMC. The project involves abatement of asbestos in the central chase crawl space. Required precautions during construction include active means to reduce airborne dust, misting work surfaces to control dust, sealing unused doors, blocking and sealing air vents if HVAC is removed or isolated, placing dust mats at entrances and exits, removing or isolating HVAC in work areas, tightly covering and cleaning containers used to transport construction waste, utilizing a designated construction route when removing debris, and restoring HVAC where work was performed upon completion. Additional requirements upon project completion are terminal cleaning once work is fully finished and maintaining control measures until all work is complete. Exceptions must be approved by the Infection Prevention program manager.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--CON Project 667-18-111 Abate Central Chase / Replace Fire Main, newest first.
File Type Posted
36C25622R0084 0001.docx DOCX document
RFIs - Abate Central Chase.pdf PDF
S04 site visit sign in sheet 667-18-111.pdf PDF
WD - LA20220031 MOD 3 DATED 6-24-2022.txt TXT text file
36C25622R0084 EXHIBIT D R1.docx DOCX document
36C25622R0084 EXHIBIT B R1.docx DOCX document
36C25622R0084 EXHIBIT A R1.docx DOCX document
P01 ICRA - Abate Central Chase Replace Water Main ICRA FINAL.pdf PDF
36C25622R0084 EXHIBIT E R1.docx DOCX document
Construction Risk Assessment- Abate Central Chase.pdf PDF
P01 20200508 IFC Specifications.pdf PDF
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.docx DOCX document
36C25622R0084 EXHIBIT F R1.docx DOCX document
36C25622R0084 EXHIBIT C R1.docx DOCX document
P11 ILSM- Abate Central Chase - revised.pdf PDF
P01 20200508 IFC Drawings.pdf PDF
P09 Final SOW - Abate Central Chase Replace Fire Main.docx DOCX document
36C25622R0084 Solicitation.docx DOCX document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VAMC Infection Control Precautions for Class II Projects

Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.

PROJECT: BW Crawl Space Asbestos Abatement Precautions

During Construction Project Upon Completion of Project

C la ss

II

1. Provide active means to reduce airborne dust from dispersing into atmosphere.

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents if the HVAC system is removed or isolated.

5. Place dust mat at entrance and exit of work area

6. Remove or isolate HVAC system in areas where work is being performed if required to prevent contamination of adjacent areas.

7. Construction Waste

a. Transport in tightly covered container,

b. Containers without tight fitting solid lids must have covering taped in place BEFORE transport outside the project area,

c. Outside of containers must be cleaned when visibly soiled

8. When removing construction debris, utilize only the designated construction route.

1. Wipe work surfaces with cleaner/disinfectant.

2. Contain and transport construction waste as outline for “During Construction”.

3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

4. Upon completion, restore HVAC system where work was performed.

5. Schedule Terminal Clean once work is complete

Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case by case basis.

Preliminary Final

X Vickie L. Moore Infection Prevention Program Manager

4/13/2022

X Vickie L Moore Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager Signed by: VICKIE L. MOORE 193380

File details come from the government source that posted it. Updated .