Construction Risk Assessment- Abate Central Chase.pdf
PDF 272 KB Posted
- Attached to
- Z1DA--CON Project 667-18-111 Abate Central Chase / Replace Fire Main Federal contract opportunity
- Solicitation number
- 36C25622R0084
About this file
This document contains a construction risk assessment and checklist for federal contract opportunity number 36C25622R0084 to solicit project 667-18-111 for abatement of the central chase and replacement of the fire main at a Veterans Affairs medical center. The assessment identifies various safety, health, environmental, and operational risks associated with the project and required control measures. Key risks addressed include asbestos abatement, lead paint, respiratory protection, waste disposal, dust control, negative air pressure, hot work permitting, electrical safety lockout/tagout, emergency response coordination, signage, and fall protection. Inspections are required at least daily from the construction safety officer and weekly from the VA safety team. Specialized training is mandated for infection control, asbestos abatement, and respiratory protection. Approval signatures are required from multiple stakeholders including the project manager, safety officers, and infection control prior to commencement of work.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Risk Assessment and Exposure Control Checklist
Project: 667-18-111 Abate Central Chase Date: 03/29/2022
Hazard Concern (Y/N?)
Control Measure Remarks
Security Issues Site Security Y Contractor to keep work area secure Identification of Contractors Y Every contractor to obtain ID and wear ID at all times Appropriate parking Y Off Site or utilize parking at Stoner Storage of Materials Y Contractor to secure material in assigned room Change of locks? Access to site Y Traffic Control N Hours of Work Y Normal business hours during weekday and daytime weekend hours for majority of work. Coordinate night work with COR.
IH Issues/GEMS/NEPA Asbestos Y Per contract Neg Air exhaust to outside Haz Com: Chemicals used/SDS Required Y Contractor to maintain SDS Sheets Spills N Monitor, seal any floor penetrations Air Pressure Relationships-Vapors/Fumes Y Contractor to maintain negative pressure within construction area.
Contractor required to install an appropriate magnehelic gauge to identify pressure within construction area. Gauge must be visible outside of construction area
Lead Paint N Respiratory Protection Y If a specific activity requires it. P100
Respirator - Abatement Waste disposal Y Must remove daily in clean covered carts. Use freight elevators as needed. Report waste diversion monthly.
Do not put in VA dumpster at Back Dock.
Recycling Y As appropriate.
NEPA (See NEPA Compliance Checklist) N
Infection Control Issues (see ICRA) Dust Y Maintain cover carts, walk-off mats, and negative air. Routinely mop corridor and elevator lobby during demolition phase Proximity of air intakes N Proximity of patients Y Water leaks/Mold/Mildew N Negative Air Y Negative air machines with filter Exhaust to outside, replace filters when dirty Risk of TB transmission to contractors N Will not be working in a high-risk patient area.
Potential for potable water contamination N
Patient Safety Issues
Hazard Concern (Y/N?)
Control Measure Remarks
Access to construction site by patients Y Contractor to keep work area secure. Storeroom door lock w/ door closer
Engineering Issues Utility Interruption Y Coordinate w/ COR and VA staffing Vibration / Noise Y Intermittent & minor Will monitor Electrical Safety Y Contractor to utilize lockout tagout controls. Coordinate w/ VA Electrical Staff Welding/Cutting – Hot Work Y Coordinate all HOT work with the COR. Open/Close permits daily.
Frequency of Inspections Y Superintendent present at all times during work. 30hr
OSHA
Construction Safety Team Weekly Rounds.
Critical Barriers N Coordination with staff in vicinity Y All employee notification and department leaders notifications Contractor to notify COR weeks in advance
Fire Protection Issues Penetrations Y Fire Caulk Smoking N Absolutely not allowed.
ILSM (see ILSM Evaluation) Y Ref to ILSM. Contractor to provide fire extinguisher inside construction areas.
Fire watch Y Actions taken by hospital to facilitate HOT Work Burn
Permit
Disruption to fire protection systems Y Deactivate smoke detectors, tape and bag during dust producing work elements
Coordinate w/ VA fire safety
Safety Issues Trenching/Shoring N Scaffolding N Tool safety Y Follow manufacture guidance on proposed tool usage Contractor to secure PPE Y As work activity requires. Cloth mask or face covering requires in all
VA occupied spaces during COVID epidemic
Cranes N Fall Protection Y Tie off when in chase Coordinate Tie-off points with safety Confined space N Hand and Power tools Y As required. Follow manufacture guidance on proposed tool usage.
Emergency Response to/from site Y Educate staff on access to & from site.
Signage Y Identify “Construction Area” and ensure all required signs are displayed
LOTO Y Electrical work, coordinate with COR. Must meet requirements of OSHA standards.
EMS Issues Pest control within construction areas N No food in work area, remove debris daily.
Dust Control Y Walk off mats as required. Mop corridor/elevator lobby when needed Waste Disposal Y Remove daily in covered carts.
Specialized Training Requirements
Team Members to Conduct Inspections: D=Daily W=Weekly AN=As needed O=Other
Construction Safety Officer D W AN Infection Control D W AN Safety Spec D W AN GEMS D W AN Safety Officer D W AN
Approval Signatures:
Project Mgr./M&O/COR/CSO
Patient Safety
Chief Engineer/Facility Safety Officer
GEM’s (if applicable)
Infection Prevention (if no ICRA)
Safety Manager
| 2022-03-29T13:21:11-0500 | |
| ARCHIE A. LANHAM 244999 |
| 2022-04-05T15:16:01-0500 | |
| PAUL M. CELLI 3377041 |
| 2022-04-14T07:51:50-0500 | |
| JOSEPH L. HEDDINGS 3389785 |