This memorandum documents the use of other than full and open competition for an acquisition under the simplified acquisition threshold. The Department of the Navy Military Sealift Command solicitation seeks a Morgan Model 11522 Hydraulic Marine Crane from Morgan Marine as the only responsible source. As the original equipment manufacturer, Morgan Marine owns the proprietary drawings for this critical ship equipment. The crane replacement supports the Military Sealift Command's standardization initiative and is required by October 31, 2024 to support mission dive operations on the USNS Grasp, as the installed cranes are at the end of their service lives. Procuring anything other than the same make and model would require extensive redesign efforts and does not support the planned shipyard period for replacement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined_Synopsis_Solicitation.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 Ver 2.0 (01 June 2018)
Date: 16 January 2024
MEMORANDUM
Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION UNDER
THE SIMPLIFIED ACQUISITION THRESHOLD
Ref: (a) PR Number(s): _______________________________________________
I. BACKGROUND:
1. In considering the references, FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contacting Officers may solicit from one source if the Contracting Officer determines that, under the circumstances of the contract action, only one source is reasonably available (e.g., urgency, exclusive licensing, brand-name, or industrial mobilization).
2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition because only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
1. Provide a description of the item or service required, to include
a) the name of the required source or brand name
Morgan Model 11522 Hydraulic Marine Crane
b) the required delivery date/period of performance and
_____31 October 2024________________________________________________________________
c) its intended use.
___Supports mission dive operations for the Salvage ship USNS Grasp______________________
2. List the source(s) or known vendor(s) who are able to provide the above described item or service.
______Morgan Marine________________________________________________________________
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION IS BASED
ON THE FOLLOWING (select all that apply):
A. ___X_ Only one responsible source (select all that apply):
1. __X___ RESTRICTIVE RIGHTS: the source has established proprietary rights, limited rights in data, patent rights, copyrights, or secret processes in the item or service.
a. Explain what is subject to the restrictive rights. Morgan Marine owns the drawings.
Morgan Marine is the OEM.
2 Ver 2.0 (01 June 2018)
b. ____________________________________________________________ Morgan Marine owns the drawings as the OEM.
2. _____ EXCLUSIVE LICENSING AGREEMENTS: The item or service is only available from the Original Equipment Manufacturer (OEM), or there is ONLY ONE authorized distributor or technical representative for the OEM.
a. Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.
b. Identify the distributor / authorized technical representative for the item or service.
Provide evidence of the exclusive licensing agreement as an attachment to this document.
(NOTE: If there is more than one distributor / authorized technical representative, then use Part B Brand Name.)
3. ___X__ OTHER REASON:
a. __X___ CRITICAL SHIP EQUIPMENT: The required item is critical ship equipment, the failure of which poses a hazard to the ship, the crew or the environment.
i. QMS Procedure Number: __ N0750-100.00-AQ ___________________
b. ___X__ STANDARDIZATION / BRAND NAME: Per MSCs standardization initiative, additional units or replacement items.
i. Identify Make / Model Number(s): __see below_________________
ii. Identify other vessels with this Make / Model:
_USNS SALVOR______________________________________________
c. __X__ FORM, FIT, AND FUNCTION: Item is direct replacement parts / components for existing equipment and must be compatible in terms of form, fit, and function with existing equipment / configurations.
i. Identify Make / Model of existing equipment:
3 Ver 2.0 (01 June 2018)
___ Morgan Model 11522 Hydraulic Marine Crane __________________
ii. Describe how the equipment must be compatible with the existing configuration.
_Morgan Marine is the OEM and the only known source of supply for this critical mission equipment. The USNS Grasp was designed to operate with this make/model crane.
The installed cranes are at the end of their service lives, and require replacement. Procuring the same make/model supports a straightforward crane replacement. Procuring other than the same make/model would require extensive engineering redesign effort, and doesn t support the planned replacement shipyard period.
d. _____ OTHER:
4. _____ UNUSUAL AND COMPELLING URGENCY: The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits. Urgent requirements are supplies or services that will result in work stoppage, or are mission critical and the routine processing time would injure the Government. The determination that the procurement for the above is an urgent and compelling requirement is based on the following:
a. Date on which the requirement was identified: ______________________________
b. Required delivery date / Period of Performance: _____________________________
c. If the difference between a. and b. is more than one week, explain the delay in submitting the requirement.
d. Estimated production lead time: ______________________________
e. Explanation of why delivery / commencement of services by the date required is needed: (explain the impact to the mission, any special circumstances or conditions, etc.)
f. CASREP Number: _________________________________________
IV. ANTICIPATED DOLLAR VALUE OF PROCURMENT: