This document is a Performance Work Statement (PWS) for a federal contract opportunity to provide Original Equipment Manufacturer (OEM) training on Oshkosh vehicles to Army mechanics at Fort Carson, Colorado.
The PWS outlines the specific training requirements, which include courses on maintenance and troubleshooting for the HEMTT, JLTV, FMTV, and HETA1 Oshkosh vehicle platforms. The contractor shall provide the training materials and instructors, while the government will furnish the classroom facilities, vehicles, and equipment. The contract will be a firm-fixed price type with a 12-month period of performance. The government reserves the right to vary the quantities up to 30% to meet operational requirements, and may make multiple awards. The contractor shall maintain an effective quality control program to ensure compliance with the PWS. Performance will be monitored through a Quality Assurance Surveillance Plan.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources sought oshkosh oem.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.5.1 Quality Control: The contractor shall maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.
1.5.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. Each location will contain a COR (Contracting Officer Representative) who will evaluate and inspect the quality of each item under their direct control.
1.5.3 Recognized Federal Holidays: The contractor shall NOT be required to perform services on holidays.
New Year's Day Martin Luther King Jr. Birthday President's Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
1.5.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of 0800hrs – 1600 hrs. Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS.
1.5.5 Place of Performance: The work to be performed under this contract will be performed at Ft. Carson, CO.
1.5.6 Type of Contract: The government will award a Firm-Fixed Price Contract.
1.5.7 Security Requirements: Contractor personnel performing work under this contract do not need Security clearance at time of the proposal submission.
1.5.7.1 PHYSICAL Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use.
At the close of each work period, government facilities, equipment, and materials shall be secured.
1.5.7.2 Antiterrorism and Operations Security Requirements
AT Level I training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://jkodirect.jten.mil.
Access and general protection/security policy and procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
For contractors requiring Common Access Card (CAC). Before CAC Issuance the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with inquires (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards. Procedures using the National Crime Information Center Interstate Identification Index (NCIC-11I) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/ facility access and local security policies and procedures (provided by government representative),or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
For contracts that require a formal OPSEC program. The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per ARS30-l.
For contracts that require OPSEC Training. Per AR 520-1, al contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty and annually thereafter.
Per AR 530-1, Operations Security: new contractor employees and/or contracts of a specific duration requiring access to Fort Carson must complete Level I OPSEC training within 30 calendar days of their reporting for duty. All contractor employees must complete annual OPSEC awareness training. Contracts of a specific duration that exceed one year must complete annual OPSEC Level I training. OPSEC level I awareness training is available at the following website:
https://securityawareness.usalearning.gov/opsec/
1.5.8 Key Control: N/A
1.5.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.
The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced.
Appropriate action shall be taken to resolve outstanding issues. Minutes shall be taken by the contractor. These meetings shall be at no additional cost to the government.
1.5.10 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions:
assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract:
issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.5.11 Key Personnel: The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 0700 hrs – 1700 hrs, Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.
1.5.12 Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.
1.5.13 Contractor Travel should be included in budgetary estimate that will include lodging and per diem.
1.5.14 Other Direct Costs: N/A
1.5.15 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer.
All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.5.16 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.5.17 PHASE IN /PHASE OUT PERIOD N/A
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations.
This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor.
The Government does not have privity of contract with the subcontractor.
2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OEM Original Equipment Manufacturer PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: The Government will provide licensed individuals for vehicles and equipment that need to be Oshkosh OEM Training
3.2. Facilities: The Government will provide shop bays for three vehicles near the classroom for the duration of the class.
3.3. Utilities: The government will provide electrical outlets for the equipment needed for computers or other devices need to assist in training
3.4. Equipment: The government will provide vehicles to the contractor that will be utilized for the training.
3.5. Materials: The Government will provide shop tools and PPE as necessary for respective level of training.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1. Contractor Furnished Items. Everything included in this paragraph and its subparagraphs is basic to the contract and should be included in the overhead of the Contractor.
4.1.1. The Contractor shall provide all labor, supervision, transportation, vehicles, supplies, equipment, materials, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS
4.2. Materials. The Contractor shall provide materials to meet the performance of this contract such as but not limited to: training material, training aids, Training Support Packets.
4.3. Equipment. N/A
4.4. Responsibilities of the Contractor.
4.4.1. The Contractor shall provide a safe working environment for key consultants and all persons in his/her employ as prescribed by 29 CFR 1910 “Occupational Health and Safety”. The Contractor shall be responsible for all damages to persons and property that occur in connection with the work and service under this contract, without recourse again the government.
4.4.2. Contractor shall exercise extreme caution to protect building finishes, private property military property, etc., from damage during the performance of these contract requirements. Contractor shall be responsible for all loss or damage or whatever kind and nature to all government property, while in the performance of these contract requirements, which results in whole or in part from the negligence or missions of contractor, any of his subcontractors or any employee, agent or any representative of the contractor or subcontractor(s).
4.4.3. The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, 50 State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor agrees to comply with federal, state, and local public health regulations and also will comply with DoD and Army Public Health Regulations and guidance.
PART 5
SPECIFIC TASKS
5. Specific Tasks:
5.1. Equipment: N/A
5.2. Equipment Requirements: N/A
5.2.1 The equipment shall be able to operate in Ft. Carson. Each piece of equipment shall have a necessary safety equipment if applicable (ie. Fire extinguisher).
5.2.2 Regulatory Markings: N/A
5.2.3 Equipment Condition: Each item of equipment or property furnished under this contract shall be in safe operational condition and shall comply with the Federal Safety Standards, the American National Standards and State Safety Regulations applicable to this equipment or property. If the Contracting Officer or their representative determines that any item of equipment or property furnished is not suitable for performance under this contract, the Contracting Officer shall promptly inform the contractor in writing.
5.3 Quantity: The Government reserves the right to vary quantities by +/- 30% due to operational requirements and to make multiple awards to meet said requirements. The Government also reserves the right to increase or decrease the POP dates due to mission requirements. In the event changes occur, the Contracting Officer (KO) will notify the Contractor within 24 hours to make adjustments accordingly. The Government shall not be charged for decreasing quantities or POPs due to mission changes. Any changes shall be prorated at the calculated daily amount to adjust for increasing or decreasing requirements.
5.4 Familiarization Training: Each instructor should be familiarized on each Oshkosh platform that training will be conducted on.
5.5 Delivery Instructions: All equipment shall be delivered to the specified Ft. Carson, CO locations no later than 1000 MST on the day before the POP. Delivery of equipment must be coordinated with the COR prior to delivery to confirm delivery times and location. The Contractor shall allow adequate time for a joint visual inspection. All set up must be complete and equipment ready for use at time of delivery.
NOTE: Increased installation security may delay Contractors’ delivery time. It is the Contractors’ responsibility to plan and prepare prior to the beginning of the POP to gain access to the post.
5.6 Pre-Inspection Requirements: The Contractor shall coordinate with the COR to assure all service confirmations prior to arrival. At time of service, the Contractor shall complete a joint pre-inspection with the COR verifying that contractors are in the correct location and are operational in accordance with the contract requirements. Contractor must be present until these joint inspections are complete.
5.7 Post-Inspections Requirements: N/A
5.8. Emergency Services: The Contractor shall be available by phone to provide 24 hour emergency repair and/or replacement services for the equipment used for cleaning and sterilization, including all weekends and holidays, at the Contractor’s expense. The Contractor shall provide emergency services upon notification from the KO and have repaired or replaced the equipment within eight (8) hours. All repairs, replacement, delivery and pick-up costs not due to Government negligence shall be at no additional cost to the Government. Repairs shall be on-site at the equipment’s location.
5.9 Removal of Equipment: The Contractor shall coordinate with the COR for removal of equipment at the end of the POP. The Contractor shall remove all contracted/leased equipment from the installation within 48 hours after the POP. Should equipment remain in place beyond 48 hours, the Government is not liable for usage, theft, loss, damage or replacement costs due to the Contractor's negligence to take possession of owned items. If for any reason the Contractor is unable to pick-up equipment, notify the KO in writing 24 hours prior to scheduled pick-up date.
5.10 Contractor’s Representatives or Supervisors: Contractor shall have a company representative on call to respond to maintenance requests with full telephone coverage and authority to make decisions on behalf of the company on a 24 hour basis. The time for a required maintenance call starts when the Government calls the company representative. The Contractor shall have functioning voicemail. Lack of receiving capabilities by the Contractor does not relieve the Contractor of liability for the required service call timeframe to repair or replace equipment.
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
PART 7
ATTACHMENT/TECHNICAL EXHIBIT LISTING
7. Attachment/Technical Exhibit List:
7.1. Technical Exhibit 1 – Performance Requirements Summary
7.2. Technical Exhibit 2 – Deliverables Schedule
7.3 Technical Exhibit 3 – Estimated Workload Data
TECHNICAL EXHIBIT 1
Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective (The Service required— usually a shall statement)
Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)
Method of Surveillance
PRS # 1.
The Contractor shall ensure Oshkosh OEM Training is conducted to all enrolled students.
4-day CAT Engine Maintenance and Troubleshooting, 3-day Allison Transmission Maintenance and Troubleshooting 3-day Air Conditioning with Fed Certification 3-day CTIS system Maintenance and Troubleshooting 2-day Wheel end rebuild (any truck)
Oshkosh OEM Training will be taught IAW Oshkosh Training Support Package (TSP’s) All Training support materials will be supplied by the contractor.
0% deviation First failure will result in the issuance of a Contractor Deficiency Report (CDR) Continuance of not meeting performance standard (2 or more) a corrective action plan will be developed at the discretion of the KO
PRS # 2.
The Contractor shall ensure Oshkosh OEM (HEMTT SORTS) training is conducted to all enrolled students.
5-day HEMTTA4 (any variant) Operation, 5-day HEMTTA4 (any variant) Maintenance and Troubleshooting, 5-day PLSA1 Maintenance and Troubleshooting, 5-day Complete HEMTT Annual Service – would require parts
Oshkosh Training Support Package (TSP’s) All Training support materials will be supplied by the contractor.
0% deviation
First failure will result in the issuance of a Contractor Deficiency Report (CDR) Continuance of not meeting performance standard (2 or more) a corrective action plan will be developed at the discretion of the KO
PRS # 3.
Oshkosh OEM (JLTV SORTS) training is conducted to all enrolled students.
10-day JLTV Maintenance and Troubleshooting, 5-day JLTV Advanced Troubleshooting, 5-day JLTV Operation
Oshkosh Training Support Package (TSP’s) All Training support materials will be supplied by the
Contractor Deficiency Report (CDR) Continuance of not meeting performance standard (2 or more) a corrective action plan will be
PRS # 4
Oshkosh OEM (FMTV SORTS) training is conducted to all enrolled students.
5-day FMTVA1P2 (all variant) Maintenance and Troubleshooting
Oshkosh Training Support Package (TSP’s) All Training support materials will be supplied by the
Contractor Deficiency Report (CDR) Continuance of not meeting performance standard (2 or more) a corrective action plan will be
PRS # 5
Oshkosh OEM (HETA1) training is conducted to all enrolled students. 5-day HETA1 Maintenance and Troubleshooting
Oshkosh Training Support Package (TSP’s) All Training support materials will be supplied by the
Contractor Deficiency Report (CDR) Continuance of not meeting performance standard (2 or more) a corrective action plan will be
File details come from the government source that posted it. Updated .