This is a federal delivery order and statement of work for extending an existing 48-inch diameter fiberglass reinforced plastic (FRP) air scrubber stack at Watervliet Arsenal in Building 35, Watervliet, New York.
The contractor must extend the existing stack by 10 feet in elevation (from 167'-3" to 177'-3") to achieve acceptable air quality at all locations of concern. Work includes fabrication and installation of the FRP ductwork extension, supplemental structural steel framing, work platform with sampling ports, roofing repairs to the existing 60-mil EPDM membrane system, and lightning protection bonding. The contract is firm fixed price at $235,431.74 with a 60-calendar-day performance period commencing within 7 days of notice to proceed, with completion required by July 17, 2026. One hundred percent payment and performance bonds are required. The contract is a small business 8(a) direct award to DMYLES, Inc. (CAGE Code 723U0), issued by Watervliet Arsenal's contracting office. Key submittals include shop drawings (structural steel, ductwork, platform, roofing, and lightning protection) stamped by New York State Professional Engineers, safety plans, welding certifications, material certifications, and as-built drawings. The work must comply with applicable AISC, AWS, ASTM, NFPA, and OSHA standards. All work is performed on-site at Watervliet Arsenal during normal business hours (Monday-Thursday 7:00 AM-4:00 PM EST; Friday 7:00 AM-3:00 PM EST) with inspection and acceptance at the Arsenal location. A one-year warranty on all materials and workmanship is required.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
14. SHIP TO
ORDER FOR SUPPLIES OR SERVICES PAGE 1 OF
1. CONTRACT/PURCH ORDER/AGREEMENT NO. 2. DELIVERY ORDER/ALL NO. 3. DATE OF ORDER/CALL
(YYYYMMMDD)
4. REQUISITION/PURCH REQUEST NO. 5. PRIORITY
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than 6) CODE 8. DELIVERY FOB
DESTINATION
OTHER
(See Schedule if other)
10. DELIVER TO FOB POINT BY (Date)
(YYYYMMMDD)
12. DISCOUNT TERMS
13. MAIL INVOICES TO THE ADDRESS IN BLOCK
11. X IF BUSINESS IS
SMALL
SMALL DISAD-
VANTAGED
WOMEN-OWNED
CODE 15. PAYMENT WILL BE MADE BY CODE MARK ALL
PACKAGES AND
PAPERS WITH
IDENTIFICATION
NUMBERS IN
BLOCKS 1 AND 2.
16.
TYPE
OF
ORDER
DELIVERY/
CALL
PURCHASE
This delivery order/call is issued on another Government agency or in accordance with and subject to terms and conditions of above numbered contract.
Reference your furnish the following on terms specified herein.
ACCEPTANCE. THE CONTRACTOR HEREBY ACCEPTS THE OFFER REPRESENTED BY THE NUMBERED PURCHASE ORDER AS IT MAY PREVIOUSLY HAVE BEEN OR IS NOW MODIFIED, SUBJECT TO ALL OF THE TERMS AND CONDITIONS SET FORTH, AND AGREES TO PERFORM THE SAME.
NAME OF CONTRACTOR SIGNATURE
If this box is marked, supplier must sign Acceptance and return the following number of copies:
TYPED NAME AND TITLE DATE SIGNED
(YYYYMMMDD)
17. ACCOUNTING AND APPROPRIATION DATA/LOCAL USE
18. ITEM NO. 19. SCHEDULE OF SUPPLIES/SERVICES
20. QUANTITY
ORDERED/
ACCEPTED*
21.
UNIT
22. UNIT PRICE 23. AMOUNT
*If quantity accepted by the Government is same as quantity ordered, indicate by X.
If different, enter actual quantity accepted below quantity ordered and encircle.
24. UNITED STATES OF AMERICA 25. TOTAL
26.
DIFFERENCES
30. INITIALS
27a. QUANTITY IN COLUMN 20 HAS BEEN
INSPECTED RECEIVED
ACCEPTED, AND CONFORMS
TO THE CONTRACT EXCEPT
AS NOTED:
c. DATE
(YYYYMMMDD)
b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
28. SHIP. NO.
PARTIAL
FINAL
31. PAYMENT
COMPLETE
PARTIAL
FINAL
29. D.O. VOUCHER NO.
32. PAID BY 33. AMOUNT VERIFIED CORRECT FOR
34. CHECK NUMBER
35. BILL OF LADING NO.
42. S/R VOUCHER NO.
36. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT.
a. DATE
(YYYYMMMDD)
b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
37. RECEIVED
AT
38. RECEIVED BY (Print) 39. DATE RECEIVED
(YYYYMMMDD)
40. TOTAL CON-
TAINERS
41. S/R ACCOUNT NUMBER
DD FORM 1155, DEC 2001 PREVIOUS EDITION IS OBSOLETE.
CONTRACTING/ORDERING OFFICER
9. CONTRACTOR CODE FACILITY
NAME
AND
ADDRESS
BY:
d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
f. TELEPHONE NUMBER g. E-MAIL ADDRESS
Section A - Solicitation/Contract Form
Extension of the existing 48-inch diameter fiberglass reinforced plastic (FRP) Instrument Name:
air scrubber stack
A. NOTICE OF WATERVLIET ARSENAL INFORMATION/REQUIREMENTS
(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:
(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN THE
REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID, PLEASE
ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.
(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO THE
DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD. FAILURE TO
COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY RESULT IN
TERMINATION OF THE ORDER OR REQUIRE CONSIDERATION IF THE GOVERNMENT
ELECTS TO EXTEND DELIVERY. (NOTE: Non-availability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid.
They are not acceptable excuses for failing to meet the delivery after award).
(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE JUST
AS IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NON-
CONFORMING PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED COSTS
TO THE ARSENAL.
(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR
CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT AWARDS.
NOTICE: Throughout this document we may use the terms "we" and "you", the term "we" means the government of the United States of America, and the term "you" means the contractor.
(b) WATERVLIET ARSENAL INFORMATION FOR CONTRACTORS:
"Watervliet Arsenal Information for Contractors" document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address: http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available."
POC - CONTRACT SPECIALIST/BUYER: Christopher Battiste
TELEPHONE NUMBER: 518-266-4607
E-MAIL ADDRESS: christopher.k.battiste.civ@army.mil
Please provide the following information for your company.
VENDOR NAME: DMYLES, Inc.
W911PT26FA203
VENDOR POC: Darius Myles
POC PHONE: 716-909-0718
E-MAIL ADDRESS: dariusmyles@dmylesinc.com
UNIQUE ENITITY ID: HS24M3JAGVU5
CAGE CODE:723U0
TAX ID NUMBER: On FIle
(c) POSTERS:
(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards. Orders subject to these Acts require contractors to post WH Publication 1313, "Employee Rights on Government Contracts".
(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, "Employee Rights under the Davis Bacon" and the Office of Federal Contract Compliance poster on "Equal Employment Opportunity is the Law."
(3) These posters can be accessed electronically at http://www.dol.gov .
(4) Hard copies of the posters will be made available upon request to the contracting officer.
(d) PAYMENTS:
Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://piee.eb.mil/ using the "my invoice" system.
You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.
(e) RELEASE OF INFORMATION:
The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor's responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.usapa.army.mil/pdffiles/r360_1.pdf
C._1_ Submission of Recordable Injuries and Illness Cases (Dec 2012) Watervliet Arsenal is pursuing OSHA Voluntary Protection Program (VPP) recognition. The VPP impacts all contractors whose employees cumulatively work more than 1000 hours per quarter within a calendar year at Watervliet Arsenal (herein referred to as "applicable contractors"). It is the contractor's responsibility to ensure its employees and managers are in full compliance with OSHA requirements and have a general understanding of VPP. Detailed information on VPP is available on the OSHA website at http://www.osha.gov/dcsp/vpp/index.html . All contractors, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, must follow the safety and health rules of Watervliet Arsenal.
Applicable contractors are required to annually submit to Watervliet Arsenal, ATTN: TAWV-XO- S/Safety Office, Bldg. 10, 1 Buffington Street, Watervliet, NY 12189-4050 or email: usarmy.
watervliet.tacom.list.watesafety@army.mil the following documents (covering the previous calendar year quarters) by 15 January:
- Total Case Incidence Rate (TCIR)
- the number of recordable injuries and illness cases per 100 full-time employees that a site has experienced in a given time frame.
- Days Away, Restricted, and/or Transfer Case Incident Rate (DART)
- Number of recordable injuries and illness cases per 100 full-time employees resulting in days away from work, restricted work activity, and/or job transfer that a site has experienced in a given time frame.
- OSHA Form 300A
Applicable contractors may submit the above immediately following the completion of a quarter, if desired.
H._1_ SERVICES/CONSTRUCTION REQUIREMENTS
(a) SCHEDULE UNIT OF MEASURE NOTE: When "LOT" is stated as a unit of measure it is the equivalent to "JOB".
(b) WORK PERFORMED ON-SITE AT WATERVLIET ARSENAL:
The contractor agrees that each employee working at Watervliet Arsenal will sign the "Contractor Personnel Agreement on Non-Disclosure of Watervliet Arsenal Technology below.
Signatures must be received by the Contract Administrator before work may begin and any resultant delay won't be considered an excusable delay to contract performance as defined in the contract clause "Default". Additional copies of this Non-Disclosure Statement can be found on the Internet at http://www.wva.army.mil/Documents/Contracting/nondis.pdf
(d) CONTRACTOR PERSONNEL AGREEMENT ON NON-DISCLOSURE OF WATERVLIET
ARSENAL TECHNOLOGY
(1) The Undersigned, as an employee of (Name of Firm) agrees to the following terms and conditions.
(2) Any knowledge gained, as a result of my being permitted on Watervliet Arsenal's premises, concerning cannon production technology (as defined below) or other technology on any defense item being manufactured or developed at Watervliet Arsenal, will not be released outside of (Name of firm) and/or the United States of America (this prohibition includes, but is not limited to, the company's domestic and foreign subsidiaries, affiliates, etc.), nor will such technology be used to manufacture or assist another in the manufacture of cannon (as described below) or other defense items being manufactured or developed at Watervliet Arsenal, without the written prior approval of Watervliet Arsenal.
(3) Definitions:
(a) CANNON: is defined as any and all components/parts of a complete assembly consisting of a tube, breech mechanism, tube attachments, muzzle appendages, firing mechanisms, and all integral components. It may also be a component of a weapons system of 40mm Bore or over such as tank guns, towed and self propelled howitzers, naval guns, mortars and recoilless guns.
(b) CANNON PRODUCTION TECHNOLOGY: is defined as the technical data package and manufacturing technology.
(1) TECHNICAL DATA PACKAGE: cannon engineering drawings, specifications and standards.
(2) MANUFACTURING TECHNOLOGY: technical knowledge, documentation, assistance and equipment and machines used and/or useful in the manufacturing of cannon.
(c) TECHNICAL KNOWLEDGE: the know how collected, trade secrets, production experience and special skills necessary for the production of cannon and the technical information and inventions necessary for the manufacture of cannon and relating to the manufacture of cannon.
(d) TECHNICAL DOCUMENTATION: manufacturing technical data comprised of drawings, specifications, schemes, composition, descriptions, methods of calculations, instructions and other information necessary for the manufacture of cannon.
(e) TECHNICAL ASSISTANCE: all assistance required to make practical and economical use of the technology required to manufacture cannon, such as delivery of documentation, training of personnel, instructions, consultations and acquainting of specialists with the most economical method of using this technology in the manufacture of cannon.
(f) EQUIPMENT AND MACHINES: production machines, machine accessories, apparatuses, spare parts and tooling used for cannon manufacture.
TYPED OR PRINTED NAME SIGNATURE DATE
TYPED OR PRINTED NAME SIGNATURE DATE
TYPED OR PRINTED NAME SIGNATURE DATE
(e) JOB SITE AVAILABILITY:
The work site will be available for performance during normal business hours:
Monday through Thursday Business Hours: 7:00 a.m. EST to 3:00 p.m. EST
Friday Business Hours: Every other Friday from 7:00a.m. EST to 2:00 p.m. EST
Fridays will be staggered with every other Friday being a closed business day. The first Friday of 2026 to be closed is January 09, 2026.
Based on the above, service contractors should call contract/purchase order administrator in advance if service is scheduled for a Friday to determine if the Arsenal will be open for business. When a federal holiday is normally observed on Friday, the Arsenal may be closed on the preceding Thursday. In this case, contact the contract/purchase order administrator in advance if scheduling service to determine if the Arsenal will be open for business. Work at other than the above hours won't be allowed unless the contractor makes an application at least 48 hours in advance and gets written contracting officer approval. No guarantee is made that the job site will be made available other than as stated above.
(f) CONTROL OF FOREIGN VISITORS TO WATERVLIET ARSENAL:
Offerors are advised that any employee or representative of their company who is not a U.S.
citizen, (or is representing a foreign company) and is a U.S. citizen), planning on visiting the Watervliet Arsenal for the purpose of attending: bid conferences, bid openings, site visits, engineering services, or any other visit related to this solicitation will be escorted at all times by an arsenal representative while on the installation grounds. Therefore, offerors must notify the Contracting Officer in advance (a minimum of two [2] weeks) of any proposed visit by a non-U.
S. citizen or U.S. citizen representing a foreign firm, to assure proper clearance for entry into the arsenal. Failure to comply, or disclose a foreign national visitor, may subject the Contractor to the penalties set forth in 18 U.S.C.A. Section 1001, Chapter 14. Due to manpower constraints, Watervliet Arsenal is often unable to provide escort services during contract performance. Therefore, if the resulting contract requires performance on Watervliet Arsenal property, employees, individuals or subcontractors representing the successful offeror who are not U.S. citizens may not, depending on staffing levels and the availability of escorts, be allowed access to the Arsenal for purpose of contract performance. Be further advised that the inability of the Arsenal to provide escorts resulting in denial of access to Watervliet Arsenal of the aforementioned personnel will not be considered an excusable delay to contract performance as defined in the contract clause "Default" contained in the contract. Therefore, offerors should consider the above contingencies during offer preparation.
(h) CONTRACTOR IDENTIFICATION:
Contractor employees shall identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. In addition, contractor personnel shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence, and when working in situations where their actions could be construed as official government acts.
*** END OF NARRATIVE ***
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
0001 Contractor Required to provide extension of the existing 48-inch diameter fiberglass reinforced plastic (FRP) air scrubber stack , in Building 35 at the Watervliet Arsenal, Watervliet, NY. All work will be performed in accordance with Statement of Work under Project #26OD001, which is attached and incorporated. Wage Determination General Decision Number NY20260002 Rev 1 dated 01/30 /2026 applies and is incorporated.
Magnitude of this entire project is between $100,000 - $350,000.
Period of Performance is 60 days after notice to proceed. 100% Payment and Performance Bonds are required. Technical Point of Contact is Sean Lyons CLIN only - Requisition Document Number (MILSTRIP, DLMS, FEDSTRIP): 12412034
Pricing Arrangement: Firm Fixed Price
ACRN: AA
PR Number:
W56DRX0012412034PR Line Item Number: 0001
1 Lot USD 235,431.74
Firm Price
USD
235,431.74 Funded Amount
USD
235,431.74
Section C - Description/Specifications/Statement of Work
STATEMENT OF WORK (SOW)
FOR
Extension of Air Scrubber Stack
AT
Watervliet Arsenal
Building 35
Project #: 26OD001 Installation Management, Public Works Division
Facilities Engineering (TAWV-IMP-F)
Revised: 25 November 2025
PART 1 GENERAL
1.1 SUMMARY OF WORK
1.1.1 Project Description
a. This Statement of Work (SOW) defines the effort required to provide extension of the existing 48-inch diameter fiberglass reinforced plastic (FRP) air scrubber stack as required to achieve another 10-foot in elevation (167'-3" to 177'-3"). The goal of the new stack design is to ensure acceptable air quality at all locations of concern.
1.1.2 Location of Work
a. The work will be conducted in between Building 35. The exact location will be shown by the Contracting Officer Representative (COR) at the Site Visit.
1.1.3 Period of Performance
a. The Contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than 60 calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.
1.1.4 Hours of Operation
a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on Fridays. Federal holidays are non-workdays. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
1.2 SUBMITTALS
1.2.1 General Submittal Requirements
a. The Contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval.
All submittals require government approval unless otherwise explicitly stated.
b. The Contractor shall reference APPENDIX A "Consolidated List of Submittals" for the complete list of required submittals.
1.2.2 Contractor Safety Plan
a. The Contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.
1.2.3 Lockout / Tagout (LOTO) Acknowledgement
a. The Contractor shall sign and submit a "Lockout/Tagout (LOTO) Notification Acknowledgement Record" prior to working on or de-energizing any electrical equipment.
1.2.4 Asbestos Notification Acknowledgement Record
a. The Contractor shall sign the "Asbestos Notification Acknowledgement Record" and submit this form to the Project COR prior to starting project work.
1.2.5 Project Schedule
a. The Contractor shall create a project schedule and submit for Government review and approval.
b. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The Contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.
1.3 GENERAL REQUIREMENTS
1.3.1 Watervliet Arsenal Information for Contractors (WAIC)
a. The Contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publicly available at:
1.3.2 Utility Outage Requests and Utility Connection Requests
a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
b. The Contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the Project COR a minimum of seven (7) business days before the shut-down of a utility or building service.
1.3.3 Safety Requirements
a. The Contractor is required to provide the proper control of hazardous energy (lockout/tagout) per OSHA 29 CFR 1910.147.
b. The Contractor shall inspect the project work site prior to starting work and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials.
1.4 ON-SITE PERMITS
1.4.1 Excavation (Dig Permit)
a. The clearance of buried utilities will be performed by the Government in advance of the Contractor performing subsurface work, unless otherwise explicitly stated.
b. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420- 2-E) from the COR prior to performing subsurface work. Verify existing utility locations indicated on contract drawings, within area of work.
1.4.2 Hot Work and Confined Space
a. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.
1.5 APPLICABLE DOCUMENTS
1.5.1 Drawings
a. The following drawings accompany this Statement of Work and are a part thereof.
i. M-1308
ii. S-0001
iii. S-0002
iv. S-0404
v. S-0405 vi.
Modernization_of_Industrial_Facilities_Bldg_1002_Roof_Power_and_Lightning_Protection_Plan_Part_1_ (EL-209_7557-6847_July_1979_247).TIF vii.
Modernization_of_Industrial_Facilities_Bldg_1002_Roof_Power_and_Lightning_Protection_Plan_Part_2_ (EL-210_7557-6848_July_1979_248).TIF viii.
Modernization_of_Industrial_Facilities_Bldg_1002_Roof_Power_and_Lightning_Protection_Plan_Part_3_ (EL-211_7557-6848_July_1979_249).TIF ix.
Modernization_of_Industrial_Facilities_Bldg_1002_First_Floor_120_Volt_Power_and_Grounding_Plan- Part_1_(EL-206_7557-6844_July_1979_244).TIF
x. Modernization_of_Industrial_Facilities_Bldg_1002_Roof_Framing_Plan_1_(S-206_7557- 6806_July_1979_206).TIF
1.5.2 Specifications
a. The following specifications accompany this Statement of Work and are a part thereof.
i. 01 45 35 - Special Inspections
ii. 01 50 00 - Temporary Construction Facilities and Controls
iii. 01 57 19 - Temporary Environmental Controls
iv. 05 12 00 - Structural Steel
v. 09 96 00 - High Performance Coatings
vi. 23 08 01.00 - Testing Industrial Ventilation Systems
vii. 23 35 19.00 - Industrial Ventilation and Exhaust
1.5.3 References
a. The following references accompany this Statement of Work and are a part thereof.
i. Watervliet Arsenal Instructions for Contractors (WAIC).
ii. Internation Building Code (ICC)
iii. American Industrial Hygiene Association (AIHA)
iv. American Institute of Steel Construction (AISC)
i. AISC 303-22 - Code of Standard Practice for Steel Buildings and Bridges
ii. AISC 325 - Steel Construction Manual
iii. AISC 326 - Detailing for Steel Construction
iv. AISC 341 - Seismic Provisions for Structural Steel Buildings
v. AISC 348 - Structural Joints High-Strength Bolts Specification
vi. AISC 360-22 - Specification for the Design, Fabrication, and Erection of Structural Steel Buildings
v. American Society for Testing and Materials (ASTM)
i. ASTM A123/A123M - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ii. ASTM A143/A143M - Standard Practice for Safeguarding Against Embrittlement of Hot-Dip Galvanized Structural Steel Products and Procedure for Detecting Embrittlement
iii. ASTM A153/A153M - Structural Connections for Hot-Dip Galvanizing
iv. ASTM A276/A276M - Standard Specification for Stainless Steel Bars and Shapes
v. ASTM A29/A29M - Standard Specification for General Requirements for Steel Bars, Carbon and Alloy, Hot-Wrought
vi. ASTM A307 - Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Strength
vii. ASTM A325 - Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
viii. ASTM A36/A36M - Standard Specification for Carbon Structural Steel
ix. ASTM A490 - Standard Specification for Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength
x. ASTM A500/A500M - Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
xi. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc- Coated, Welded and Seamless
xii. ASTM A563 - Standard Specification for Carbon and Alloy Steel Nuts
xiii. ASTM A6/A6M - Standard Specification for General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling
xiv. ASTM A668/A668M - Standard Specification for Steel Forgings, Carbon and Alloy, for General Industrial Use
xv. ASTM A780/A780M - Standard Practice for Repair of Damaged and Uncoated Areas of Hot- Dip Galvanized Coatings
xvi. ASTM A992/A992M - Standard Specification for Structural Steel Shapes
xvii. ASTM B695 - Standard Specification for Coatings of Zinc Mechanically Deposited on Iron and Steel
xviii. ASTM F2280 - Standard Specification for "Twist Off" Type Tension Control Structural Bolt /Nut/Washer Assemblies, Steel, Heat Treated, 150 ksi Minimum Tensile Strength
xix. ASTM F2329 - Zinc Coating, Hot-Dip, Requirements for Application to Carbon and Alloy Steel Bolts, Screws, Washers, Nuts, and Special Threaded Fasteners
xx. ASTM F436 - Hardened Steel Washers
xxi. ASTM F844 - Washers, Steel, Plain (Flat), Unhardened for General Use
xxii. ASTM F959/F959M - Standard Specification for Compressible-Washer-Type Direct Tension Indicators for Use with Structural Fasteners, Inch and Metric Series
vi. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)
vii. American Welding Society (AWS)
i. AWS 2.4 - Standard Symbols for Welding, Brazing, and Nondestructive Examination
ii. AWS D1.1 - Structural Welding Code for Steel
viii. ASME International
i. ASME B46.1 - Surface Texture, Surface Roughness, Waviness and Lay
ix. National Fire Protection Association (NFPA)
i. NFPA 70 - National Electric Code (NEC).
x. AMC Environmental Requirements Supplement.
xi. Unified Facilities Criteria (UFC)
i. UFC 3-301-01 - Structural Engineering
ii. UFC 3-310-04 - Seismic Design for Buildings
xii. Society for Protective Coatings (SSPC)
i. SSPC PA 1 - Shop, Field, and Maintenance Coating of Metals
ii. SSPC Paint 20 - Zinc-Rich Primers (Type I, Inorganic, and Type II, Organic)
iii. SSPC Paint 29 - Zinc Dust Sacrificial Primer, Performance-Based
iv. SSPC SP 3 - Power Tool Cleaning
v. SSPC SP 6/NACE No.3 - Commercial Blast Cleaning
1.6 CONTRACTOR EQUIPMENT
1.6.1 Equipment Identification
a. The Contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor's:
i. Company Name, POC Name (first, last), POC phone number, Project Number.
1.6.2 Waste Dumpster
a. The Contractor shall place any waste dumpsters in a manner that does not interfere with thru traffic.
b. Place waste dumpsters with a minimum of 33' clearance from any building. The final location shall be coordinated with and approved by the COR before any dumpsters are mobilized.
c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.
d. The Contractor shall submit all Bills of Lading and Weight Slips associated with the disposal of all construction and demolition (C&D) debris to the Contracting Officer monthly. The contractor shall provide this information within ten (10) days of disposal of the waste.
PART 2 PRODUCTS
2.1 GENERAL
All work shall be in strict accordance with product manufacturer's instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.
2.1.1 Hazardous Materials
a. The Contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.
2.1.2 Asbestos, Mercury, Lead, PCB
a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, or Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer's original packaging.
2.1.3 DoD Green Procurement Program
a. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at .
2.1.4 Paint
a. To meet the Affirmative Procurement Program (Federal Government's Buy Recycled Requirements) all paint used in the project shall adhere to the below listed requirements of the Comprehensive Procurement Guideline for recovered materials. This applies only to interior latex paint, only if available at the time of the project.
i. Reprocessed Latex Paint (White, Off-White, Pastel Colors) shall contain 20% Post consumer content.
ii. Reprocessed Latex Paint (Grey, Brown Earth tones, and Other Dark Colors) shall contain 50- 99% Post consumer content.
iii. Consolidated Latex Paint shall contain 100% Post consumer content.
2.2 PRODUCTS
2.2.1 Structural Steel
a. Wide flange and WT shapes, ASTM A992/A992M.
b. Angles, Channels and Plates, ASTM A36/A36M.
2.2.2 Structural Steel Tubing
a. ASTM A500/A500M, Grade C.
2.2.3 Steel Pipe
a. ASTM A53/A53M, Type E or S, Grade B, weight class STD (Standard).
2.2.4 Common Grade Bolts
a. Bolts. ASTM A307, Grade A. The bolt heads and the nuts of the supplied fasteners must be marked with the manufacturer's identification mark, the strength grade and type specified by ASTM specifications.
b. Nuts. ASTM A563M, Grade A, heavy hex style.
c. Self-Locking Nuts. Provide nuts with a locking pin set in the nut. The locking pin must slide along the bolt threads, and by reversing the direction of the locking pin, the nut must be removed without damaging the nut or bolt. Provide stainless steel locking pins.
d. Washers. ASTM F844.
2.2.5 High-Strength Bolts
a. Bolts. ASTM A325M ASTM A325, Type 1 ASTM A490M, ASTM A490, Type 1 or 2.
b. Nuts. ASTM A563M ASTM A563, Grade and Style as specified in the applicable ASTM bolt standard.
c. Washers. ASTM F436, plain carbon steel.
2.2.6 Welding Electrodes and Rods
a. AWS D1.1/D1.1M
PART 3 EXECUTION
3.1 ITEMS OF WORK
3.1.1 General.
a. The Contractor is required to review the project site, obtain and/or verify all measurements and project data required to perform the project work. Information shown on the project plans is of a graphical nature. Precise locations and actual sizes must be verified.
i. Before submitting a proposal, each bidder shall carefully examine the scope, drawings, and specifications. They shall also visit the site and fully inform themselves as to all existing conditions and limitations applying to the work. If, after such examination and study, it appears that any change from the drawings and specifications should be allowed, the bidder shall state in writing together with any change in cost involved.
ii. By the act of submitting a proposal, each bidder shall be deemed to have made such examinations of the scope, drawings, and specifications and premises, and it will be assumed that they are therefore familiar with the entire scope of the project and have based their proposal upon the work described in the Scope, Drawings, and Specifications and upon all existing conditions and limitations applying to their work.
iii. All details, sections, and notes shown on the drawings are intended to be typical and shall apply to similar situations elsewhere.
iv. All the expenses needed to erect the steel structure into its final position as per drawings, technical specifications and the approved methodology of erection including the rate for provision of scaffolding, temporary platforms, cranes and other efforts such as handling, transportation, loading, offloading, etc. shall be included in the bid.
v. No work under this scope will be provided for by any agency other than the Contractor, unless specifically mentioned otherwise elsewhere in the contract.
b. The Contractor shall fully review all contract documents and provide written notice to the Project Engineer and Contracting Officer (KO) of any discrepancies that are found prior to bid submission.
c. The Contractor shall provide all materials, tools and equipment, qualified labor, transportation, and supervision as needed to complete the services that meet the technical requirements in this scope, and ensure work is completed safely and properly.
d. The Contractor acknowledges that they have read the Watervliet Arsenal Information for Contractors (WAIC) and agrees with the content and the intent of the manual. The Government is not responsible for fire, theft, loss and/or vandalism of any of the Contractor's tools, equipment, materials, supplies and/or work in progress.
e. The Contractor shall have been deemed to have visited the site, prior to submission of his tender, to acquaint himself/herself with the availability of land and the development necessary by way of filling, drainage, access roads, fences, sheds etc., all of which shall be carried out by the Contractor at his own cost and as directed by the Project COR/Engineer. f. The Contractor shall identify a Project Site Manager who shall be responsible for the overall management of the project and shall represent the Contractor onsite during construction.
i. The Project Site Manager shall be approved by the Project COR/Engineer.
ii. The Project Site Manager shall attend all project meetings, prepare Status Reports on the project, and submit them to the Project COR/Engineer.
iii. The Project Site Manage shall ensure that adequate, qualified manpower will be provided to carry out this scope of work, and work will be commenced and completed as per the Project Schedule, as revised from time to time.
g. The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this Contract. Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.
h. If any of the Contractor's services do not conform to the contract requirements, the Project COR/Engineer may require the Contractor to perform the services again in conformity with the contract requirements at no cost to the government.
i. The Contractor shall be responsible for identifying any possible service interruptions.
Coordination with Project COR shall be required to develop a plan.
j. The Contractor shall maintain continuity of existing service in the construction area and for building occupants not otherwise affected by the project throughout the demolition and construction phases unless prior arrangements have been negotiated.
k. The Contractor shall notify the Project COR in writing of all items, which are serving occupied spaces, that must be relocated. The Contractor shall be responsible for relocating existing cables, wire, conduits, etc. that are to remain in service after consultation with the Project COR and building occupants.
l. The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters.
m. The fall protection threshold height requirement is 6 feet for ALL work covered by this manual, unless specified differently below, whether performed by government or Contractor work forces, to include steel erection activities, systems engineered activities (prefabricated) metal buildings, residential (wood) construction and scaffolding work.
n. The Contractor shall comply with EM 385-1-1, NFPA 70, NFPA 70E, NFPA 241, the APP, the AHA, Federal and State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails. PPE is governed in all areas by the nature of the work the employee is performing. Always use personal hearing protection in designated noise hazardous areas or when performing noise hazardous tasks. Mandatory PPE includes:
i. Safety Glasses (always)
ii. Hard Hat (always)
iii. Long Pants (always)
iv. Appropriate Safety Shoes (always)
v. Appropriate Class Reflective Vests or High Visibility Safety Apparel (always)
o. The Contractor shall provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials weekly to minimize potential hazards.
p. The Contractor shall always keep the work area free from accumulation of waste materials.
Upon completing construction, the Contractor shall remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to the Project COR.
q. All materials shall be stored to prevent deterioration, and to ensure the preservation of their quality and fitness for the work. If required by the Project COR/Engineer, the materials shall be stored under cover and suitably painted for protection against weather. Any material which has deteriorated or has been damaged shall be removed from site and replaced by new members, as directed by the Project COR/Engineer at no extra cost and time.
r. All steel materials required for the work shall be free from imperfections, mill scales, slag intrusions, laminations, pitting, rust etc. that may impair strength, durability and appearance. All materials shall be of tested quality only. If desired by the Project COR/Engineer, test Certificates in respect of each consignment shall be submitted in triplicate.
s. Project work will require outages to overhead cranes due to aerial/man lifts and proximity to power sources. This will directly impact manufacturing operations; therefore, the Project COR /Engineer will coordinate such outages with Production Managers. Advanced notice from the
Contractor shall be provided (minimum of 14 calendar days); however, there will be no guarantees. The Contractor shall prepare/plan to work nights and weekends as required to maintain the installation schedule.
t. The Contractor shall be and remain liable in accordance with applicable law for all damages caused by the Contractor's negligent performance of any of the services furnished under this Contract.
u. The Contractor shall always keep the work area free from accumulation of waste materials.
Upon completing construction, the Contractor shall remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to the Project COR.
v. The Contractor shall not permit storing, walking, wheeling, and trucking directly on applied roofing materials. Provide temporary walkways, runways, and platforms of smooth clean boards, mats, or planks as necessary to avoid damage to applied roofing materials, and to distribute weight to conform to live load limits of existing roof construction.
w. The Contractor will have the best means of access/egress to/from the roof and interior workspace through the overhead door in C-Bay, Section 1 (South). Approximate dimensions of the door are as follows: 10-feet wide by 12-feet high. Access will be tight, but the Project COR will do their best to provide additional space as needed. Items that can be moved with the permission from our Operations Directorate (OD) include pallets, tool platforms/stands, oil containers and cabinets. Items that cannot or will not be moved include manufacturing machines /tools, chrome vats, grating, storage racks, any items bolted to the floor.
i. The Contractor shall take note of these items and protect them from damage during this project. Any damage because of negligence will be grounds for immediate dismissal. All damage shall be fixed (or the part replaced) by the Contractor at no additional cost to the government.
ii. The Contractor shall cover stationary items with a minimum of 6-mil poly to prevent contamination (place two layers over the Chrome vats). In the event of overhead sparks/flame from cutting, grinding, or welding operations, the Contractor shall place fire blankets over the poly and protect openings in the bar grating.
x. Where any form of deficiency is found, take additional measures as deemed necessary by the Project COR to determine the extent of the deficiency and perform corrective actions as directed by the Project COR.
3.1.2 Ductwork.
a. The Contractor shall provide extension of the existing 48-inch diameter FRP exhaust stack as required to achieve the top of stack elevation indicated on the drawings.
b. The Contractor shall furnish all labor, equipment, materials, supervision, tools, supplies, certifications, and transportation as necessary to completely inspect, design, fabricate, install, and test the exhaust stack.
c. The Contractor shall perform final design of stack extension and visit the site to verify existing conditions and dimensions prior to fabrication. The Contractor shall confirm the material type, wall thickness, and stack diameter and perform material tests as required to verify ability of stack to support the extension.
i. The duct manufacturer shall design the stack extension for 25 pounds per square foot of wind load (ASCE 7-16).
ii. The duct manufacturer shall design the stack extension for tributary weight of HSS6.875x0.
250 braces as shown.
iii. The duct manufacturer shall design the stack extension such that the existing stack supports its weight vertically.
iv. The duct manufacturer shall provide shop drawings bearing the stamp and seal of a Registered Professional Engineer in the state of which the work is to be performed (New York).
d. The Contractor shall construct ductwork, fittings, accessories, and material of construction in accordance with NFPA 91, SMACNA 1546, and ASTM C582. Fabricate supplementary steel in accordance with the AISC 360.
e. The Contractor shall remove the existing flange and stack section as needed for installation of a new stable stack extension. Do NOT remove existing test ports.
f. The Contractor shall laminate new load ledge and flange on existing stack for extension connection per the extension fabricator's detailed design.
g. The Contractor shall provide temporary shoring and bracing until final connections are made.
Provide temporary guy lines for proper alignment of stack.
h. The Contractor shall isolate duct support contact surfaces from supporting steel by 1/4-inch-thick closed cell foamed cellular elastomer insulation material of a width greater than support.
Design duct supporting system to include additional weight due to collection of condensate and washing water in non-drainable, deflected surface and other areas.
i. The Contractor shall securely attach supporting elements to building structural steel as shown on the approved drawings. Clamp attachment to building structural steel in accordance with AWS D1.1/D1.1M. Welding test agenda must be done in accordance with the applicable provisions of AWS D1.1/D1.1M and AWS D1.3/D1.3M.
j. The Contractor shall protect duct openings from construction debris using temporary caps, flanges, or other approved means. Clean ductwork in accordance with manufacturer's recommendations. Test watertight duct work for proper support, leakage, and unacceptable drainage provisions by intermittently spraying interior with garden hose nozzle, at a rate of 3 gallons per minute, exercising care to prevent excessive water accumulation. k. After construction is complete but accessible and prior to acceptance, the Contractor shall remove all construction debris from exterior surfaces. Do NOT close duct inspection ports until inspected by the Project COR/Engineer.
l. The Contractor shall inspect, and test systems pressure rated higher than 2 inches water gauge for structural integrity and leakage as systems or sections during construction but after erection, as work progresses, in system or section lengths not exceeding 100 feet. Test for structural integrity at fifty percent in excess of system fan negative total pressure. Test for leakage at fifty percent in excess of system fan negative total pressure.
m. The Contractor shall conduct an operational test on the entire exhaust duct system, components, and equipment for a period of not less than 6 hours after power transmission components are adjusted. Replace filters, if any, after preliminary tests and prior to conducting final acceptance tests.
n. After systems and equipment testing, adjusting, and balancing has been completed and accepted, the Contractor shall demonstrate the complete and correct functioning of systems equipment and controls by operation through normal ranges and sequences, and by simulation of abnormal conditions.
i. Manually and automatically cause every device to function as intended.
ii. Readjust, as necessary, any settings and after sufficient operating time, but not less than 6 hours, verify ability of equipment and controls to establish and maintain stable and accurate operation and required system performance.
iii. Note any abnormal deviations, such as excessive vibration, noise, and heat, binding damper mechanisms, and incorrect fan rotation.
iv. Make any necessary repairs, replacements, or adjustments.
3.1.3 Supplemental Framing.
a. The Contractor shall provide all construction, transportation, equipment, tools, tackle, and consumables, materials, labor and supervision required for the fabrication and erection of the structural steelwork as shown. Supply of all necessary bolts, nuts, washers, tie rods and welding electrodes for field connections. Supply all raw steel materials for fabrication, considering wastage margin, including storage and upkeep of the materials.
b. The Contractor shall prepare and submit detailed shop drawings prepared under the supervision of, and bear the seal of, a New York State Licensed Professional Engineer, including completing details and schedules for fabrication and assembly of the structural steel to the Project COR/Engineer for review prior to installation.
i. Prepare shop drawings in accordance with AISC 326 and AISC 325. Fabrication drawings must not be reproductions of contract drawings. Include complete information for the fabrication and erection of the structure's components, including the location, type, and size of bolts, welds, member sizes and lengths, connection details, blocks, copes, and cuts.
ii. Submit erection drawings for record purposes. The erection drawings must conform to AISC
303. Erection drawings must also be reviewed, stamped and sealed by a registered professional engineer in New York State.
c. The Contractor shall design all connections, supply and fabricate all steelwork and furnish all connections materials in accordance with the drawings and/or as approved by the Registered Engineer. The methods of painting, marking, packing, and delivery of all fabricated materials shall be in accordance with the specifications or as approved by the Project COR/Engineer.
d. The Contractor shall provide the structural steel system, including shop primer, complete and ready for installation of the added ductwork. The structural steel system shall include the design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing. All these items must be provided in accordance with AISC 360, AISC 341, UFC 3-301-01 and UFC 3-310-04 except as modified herein.
e. The Contractor shall be responsible for the fabrication of the steelwork in accordance with the approved fabrication drawing, including all shop assembling, matching and marking.
Design, manufacture/fabrication and provision of all jigs, fixings, manipulators etc. required for the fabrication.
f. The Contractor shall load, transport and unload all fabricated structural steel materials from site storage to erection site, handling, assembling, bolting, welding and satisfactory installation of all fabricated structural steel materials in proper location, according to approved erection drawings and/or as directed by the Project COR/Engineer.
g. The storage area should be kept clean and properly drained. Structural steel shall be so stored and handled in such a manner that members are not subjected to excessive stress and damage. Long members shall be supported on closely spaced skids to avoid unacceptable deflection.
h. All workmanship shall be in accordance with the best practice in modern structural shops.
Greatest accuracy shall be maintained in the manufacture of every part of the work, and all similar parts shall be strictly interchangeable.
i. All parts assembled for welding shall be in as close contact as practicable over the whole surface.
j. The component parts shall be so assembled that they are neither twisted nor otherwise damaged, and if necessary, before being worked, shall be straightened and/or flattened by pressure, unless required to be of curvilinear form.
k. All parts of bolted and welded members shall be held firmly in position by means of jigs or clamps while bolting or welding. No drifting of holes shall be permitted, except to draw the parts together and no drift used shall be larger than the nominal diameter of the bolt. Drifting done during assembling shall NOT distort the metal or enlarge the holes.
l. No fabrication work shall commence by the Contractor without having obtained written approval from the Project COR/Engineer on the relevant drawings. Approval by the Project COR /Engineer of any of the drawings shall NOT relieve the Contractor of his/her responsibility to provide correct workmanship, fit of parts, details, materials and errors or omissions of all work shown thereon.
m. The Contractor shall provide supplemental steel and supports in accordance with the approved…