OR FLAP POLK MITCHELL(1)_Project Description.pdf

PDF 178 KB Posted

Attached to
OR FLAP POLK MITCHELL(1), Mitchell Street and Black Rock Road Reconstruction
Solicitation number
69056723B000022
Issued by

About this file

This project description outlines specifications for the OR FLAP POLK MITCHELL(1) construction project located one mile west of Falls City, Oregon. The work includes grading, drainage, base and asphalt paving, construction of a 113-foot single span precast concrete bridge, retaining walls, and demolition of an existing steel truss bridge. The project length is 0.95 miles with an estimated price range between $7-10 million. The tentative completion date is fall/winter 2024. Related pre-solicitation number 69056723B000022 is for the Mitchell Street and Black Rock Road Reconstruction project and is issued by the Department of Transportation Federal Highway Administration. The project description provides specifications for various earthwork, drainage, paving, concrete, and incidental construction items required to complete the project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OR FLAP POLK MITCHELL(1), Mitchell Street and Black Rock Road

Reconstruction, Polk County, Oregon

This project consists of grading, drainage, base, paving, walls, and construction of a 1-span, 113-foot long precast, prestressed concrete deck bulb-tee girder bridge.

Abutments are founded on spread footings. The work also includes construction of a temporary detour bridge and demolition of the existing steel truss bridge.

Project length: 0.95 miles

Tentative Fixed Completion Date: Fall/Winter 2024

(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: Between $7,000,000 and $ 10,000,000

Location: 1 mile W of Falls City, Oregon

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

S ch ed u le

A

S ch ed

B

DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) Yes Yes

153 Contractor Quality Control and Assurance (yes/no) Yes Yes

154 Contractor Sampling & Testing (yes/no) Yes Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes

157 Soil Erosion & Sediment Control Silt Fence Fiber Roll Temporary Diversion Berm Check Dam

250 LNFT

1,720 LNFT

1,010 LNFT

30 EACH

250 LNFT

3,890 LNFT

1,010 LNFT

60 EACH

DIVISION 200 – Earthwork

201 Clearing & Grubbing 3.8 ACRE 6.0 ACRE

203 Removal of Structures & Obstructions Removal of Mailbox Removal of Pipe Culvert Removal of Sign Removal of Fence Removal of Bridge

1 EACH

2 EACH

6 EACH

160 LNFT

ALL

3 EACH

2 EACH

8 EACH

960 LNFT

ALL

204 Excavation & Embankment Roadway Excavation Rock Excavation

3,567 CUYD

32 CUYD

11,067 CUYD

32 CUYD

ed ed

205 Blasting Consultant (Consultant/Engineering Services) (yes/no) No No

207 Earthwork Geosynthetics 1,183 SQYD 1,198 SQYD

208 Structure Excavation 570 CUYD 570 CUYD

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Riprap Placed Riprap, Method A, Class 1 Placed Riprap, Method A, Class 2 Placed Riprap, Method A, Class 4 Placed Riprap, Method A, Class 5 (bank stone) Remove and Reset Boulder

15 CUYD

185 CUYD

580 CUYD

766 CUYD

2 EACH

15 CUYD

190 CUYD

580 CUYD

766 CUYD

2 EACH

252 Rockery, Special Rock Embankment, and Rock Buttress Rockery, In-stream 10,176 SQFT 10,176 SQFT

254 Precast Concrete Block Retaining Wall 0 SQFT 2,250 SQFT

257 Contactor-Designed Retaining Walls (contractor completed designs) 0 ALL

DIVISION 300 – Aggregate and Base Courses

302 Minor Crushed Aggregate Roadway Aggregate, Method 2 3,537 CUYD 5,564 CUYD

DIVISION 400 – Asphalt Pavements & Surface Treatments

403 Asphalt Concrete Asphalt Concrete Pavement, Type 1 2,287 TON 3,667 TON

412 Asphalt Tack Coat 15 TON 30 TON

DIVISION 550 – Bridge Construction

552 Structural Concrete Structural Concrete Class A(AE) 231 CUYD 231 CUYD

553 Prestressed Concrete Precast, Prestressed Concrete Decked Bulb Tee Girder (60-inch) 558 LNFT 558 LNFT

554 Reinforcing Steel Reinforcing steel Reinforcing steel, epoxy coated

13,700 LB

13.200 LB

13,700 LB

13.200 LB

556 Bridge Railing 286 LNFT 286 LNFT

562 Temporary Works Temporary Support Structure (Temporary Bridge) ALL ALL

564 Bearing Devices 10 EACH 10 EACH

585 Ultra High Performance Concrete 7 CUYD 7 CUYD

DIVISION 600 – Incidental Construction

601 Minor Concrete Structures 45 CUYD 45 CUYD ed ed

602 Culverts & Drains 18-Inch Pipe Culvert 24-Inch Pipe Culvert 36-Inch Pipe Culvert

88 LNFT

190 LNFT

90 LNFT

88 LNFT

390 LNFT

90 LNFT

609 Curb & Gutter Curb, Asphalt, 6-Inch Depth 985 LNFT 985 LNFT

617 Guardrail Guardrail System MGS, Type 2, Class A, Steel Posts Terminal Section, Type MSG Tangent Structure Transition Railing

1,175 LNFT

6 EACH

74 LNFT

1,575 LNFT

8 EACH

74 LNFT

619 Fences, Gates, Cattle Guards & Bollard Posts Fence, Barbed Wire, 4 Strand Remove and Reset Gate

140 LNFT

940 LNFT

2 EACH

621 Monuments & Markers (construction survey & staking) (yes/no) No No

622 Rental Equipment (yes/no) Yes Yes

623 General Labor (yes/no) Yes Yes

624 Topsoil Furnishing and placing topsoil, 3-inch depth 1.6 ACRE 4.5 ACRE

625 Turf Establishment Turf Establishment Turf Establishment (Swale and Ditch)

1.4 ACRE

0.3 ACRE

2.4 ACRE

0.6 ACRE

626 Plants, Trees, Shrubs, Vines & Groundcovers Cuttings, Willow Pole (Single Group Method) 960 EACH 960 EACH

633 Permanent Traffic Control (traffic control devices) Sign System Object Marker, Type 3 Delineator, Type Flexible

20 SQFT

6 EACH

70 EACH

40 SQFT

8 EACH

75 EACH

634 Permanent Pavement Markings (traffic pavement markings) Type B, Solid (4-Inch, White) Type B, Solid (4-Inch, Yellow)

14,020 LNFT

13,950 LNFT

21,050 LNFT

20,950 LNFT

635 Temporary Traffic Control – Flagger 440 HOUR 440 HOUR

635 Temporary Traffic Control – Pilot Car 0 0

635 Temporary Traffic Control Cone, Type 36-Inch Drum Traffic Signal System Construction Sign

56 EACH

30 EACH

4 EACH

255 SQFT

88 EACH

30 EACH

4 EACH

255 SQFT

646 Roadside Development Fixture, Mailbox Roadside Development (Treatment Ditch)

1 EACH

580 LNFT

3 EACH

790 LNFT

650 Temporary Diversions ALL ALL