This document is an Opinion of Probable Construction Cost (OPC) for the CR 183S Cross Drain Replacement project in Florida, dated October 2024. The project involves replacing an existing cross-drain on CR 183 South at Spears Branch, with a contract duration of 120 days for substantial completion and an additional 30 days for punch list completion. The detailed cost estimate includes 28 line items covering roadway construction activities such as mobilization, maintenance of traffic, sediment barriers, excavation, embankment, stabilization, asphalt work, concrete culverts and retaining walls, reinforcing steel, curbing, riprap, guardrail installation, performance turf, and pavement markings.
The total estimated project cost is $685,167.83, which includes a 10% contingency of $62,287.98 on top of the base construction costs of $622,879.84. Unit prices were developed using Florida Department of Transportation (FDOT) 12-month and 6-month moving statewide and area averages for cost information published between May 2023 and July 2024. The opinion of probable construction cost explicitly does not include utility improvements, relocations, or right-of-way acquisition costs. The engineer notes that the cost estimate represents their professional judgment based on current information and cannot guarantee that actual construction costs will precisely match the estimated figures.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Re_BID_CR_183_S_CROSS_DRAIN_REPLACEMENT_(Spears_Branch)_(Addendum_#1_Revision).pdf | ||
| Construction_Plans.pdf | ||
| CR_183_S_Bridge_Hydraulics_Report.pdf | ||
| Public_Construction_Bond.doc | DOC document | |
| Contract_No._24-46.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CR 183S Cross Drain Replacement
Based on 100% Plans Submitted October 2024 Opinion of Probable Construction Cost October 2024
ROADWAY
PAY ITEM DESCRIPTION TOTAL QUANTITY UNIT WEIGHTED AVG. UNIT PRICE TOTAL AMOUNT
101-1 MOBILIZATION 1 LS LUMP $56,625.44
102-1 MAINTENANCE OF TRAFFIC 1 LS LUMP $26,964.50
104-10-3 SEDIMENT BARRIER (SILT FENCE) 515 LF $5.07 $2,613.37
104-11 FLOATING TURBIDITY BARRIER 35 LF $87.57 $3,099.10
110-1-1 CLEARING AND GRUBBING 0.35 AC $79,723.00 $28,142.22
120-1 REGULAR EXCAVATION 242.60 CY $16.78 $4,070.83
120-6 EMBANKMENT 301.20 CY $27.22 $8,198.66
160-4 TYPE B STABILIZATION 735 SY $8.44 $6,201.52
285-701 OPTIONAL BASE, BASE GROUP 01 415 SY $26.62 $11,056.17
285-706 OPTIONAL BASE, BASE GROUP 06 183 SY $34.42 $6,310.33
327-70-5 MILLING EXIST ASPH PAVT, 2" AVG DEPTH 444 SY $15.00 $6,656.53
334-1-12 SUPERPAVE ASPHALTIC CONC, TRAFFIC B 37 TN $250.00 $9,225.64
337-7-80 ASPHALT CONCRETE FRICTION COURSE,TRAFFIC B, FC-9.5, (PG 76-22)(1.0") 63 TN $180.08 $11,407.49
400-4-1 CONCRETE CLASS IV, CULVERTS 106 CY $1,193.87 $126,550.22
400-4-11 CONCRETE CLASS IV, RETAINING WALLS 155 CY $1,148.02 $177,943.10
415-1-1 REINFORCING STEEL-ROADWAY 20076 LB $1.80 $36,136.80
415-1-3 REINFORCING STEEL-RETAINING WALL 17076 LB $1.13 $19,295.88
520-2-4 CONCRETE CURB, TYPE D 30 LF $38.59 $1,153.84
524-1-4 CONCRETE DITCH PAVEMENT, NON REINFORCED, 6" 4 SY $110.55 $464.31
530-3-3 RIPRAP - RUBBLE, BANK, AND SHORE 78.80 TN $402.83 $31,743.00
530-74 BEDDING STONE 48.90 TN $169.34 $8,280.73
536-1-1 GUARDRAIL - ROADWAY, GENERAL TL-3 382 LF $27.28 $10,420.96
536-85-24 GUARDRAIL - END TREATMENT - PARALLEL APPROACH TERMINAL 4 EA $3,816.75 $15,267.00
570-1-2 PERFORMANCE TURF, SOD 3192 SY $4.39 $14,012.88
706-1-3 RAISED PAVMT MARK, TYPE B 6 EA $5.54 $35.50
711-15-101 THERMOPLASTIC, STANDARD-OPEN GRADED ASPHALT SURFACES WHITE, SOLID, 6" 0.10 GM $6,801.65 $660.33 0711-15-201 THERMOPLASTIC, STANDARD-OPEN GRADED ASPHALT SURFACES, YELLOW, SOLID, 6" 0.05 GM $7,075.80 $343.47
SUB-TOTAL $622,879.84
CONTINGENCY (10%) $62,287.98
TOTAL $685,167.83
NOTES:
MOBILIZATION AND MAINTENANCE OF TRAFFIC WERE DETERMINED BASED UPON THE FOLLOWING ASSUMPTIONS:
(1) MOBILIZATION - 10% OF CONSTRUCTION COSTS
(2) MAINTENANCE OF TRAFFIC - 5% OF CONSTRUCTION COSTS
THE UNIT PRICES WERE DEVELOPED BY REFERENCING THE FOLLOWING:
(1) FDOT 12-MONTH MOVING 'STATEWIDE' AVERAGES (COST INFORMATION PUBLISHED BETWEEN (2023/05/01 - 2024/04/30))
(2) FDOT 6-MONTH MOVING 'STATEWIDE' AVERAGES (COST INFORMATION PUBLISHED BETWEEN (20234/02/01 - 2024/07/31))
(3) FDOT 12-MONTH MOVING 'AREA 1' AVERAGES (COST INFORMATION PUBLISHED BETWEEN (2023/08/01 - 2024/07/31)) OPINION OF PROBABLE CONSTRUCTION COST DOES NOT INCLUDE UTILITY IMPROVEMENTS AND/OR RELOCATIONS (WATER, SEWER, GAS, FRANCHISE, ETC.)
OPINION OF PROBABLE CONSTRUCTION COST DOES NOT INCLUDE THE ACQUISITION COST OF RIGHT OF WAY OR EASEMENT
THE ENGINEER HAS NO CONTROL OVER THE COST OF LABOR, MATERIALS, EQUIPMENT, OR OVER THE CONTRACTOR'S METHODS OF DETERMINING PRICES OR OVER COMPETITIVE BIDDING OR MARKET CONDITIONS. OPINIONS OF PROBABLE COSTS PROVIDED HEREIN ARE BASED ON THE INFORMATION KNOWN TO ENGINEER AT THIS TIME AND REPRESENT ONLY THE ENGINEER'S JUDGMENT AS A DESIGN PROFESSIONAL FAMILIAR WITH THE