Summary of Old Post Village General Renovations Rebid Specifications
This is a comprehensive bid specification document for a general renovations project at Old Post Village Senior Housing in Tolland, Connecticut, issued by the Tolland Housing Authority with Capital Studio Architects serving as the project architect. The project encompasses exterior and interior renovations across five residential buildings totaling 32 apartments, plus common spaces, including comprehensive work such as roof and gutter replacement, siding removal and replacement, window and door replacements, apartment bathroom and kitchen renovations, electrical and mechanical system upgrades, plumbing fixture replacements, asbestos and radon abatement, community room expansion and renovation, parking lot improvements, and landscaping modifications. The mandatory pre-bid meeting is scheduled for Thursday, February 12, 2026 at 2:00 p.m. at Old Post Village Community Room, with bid opening on Tuesday, March 3, 2026 at 2:00 p.m. at the same location. The bid documents were issued February 2, 2026, and the contract period is 180 consecutive calendar days from the Notice to Proceed. The project includes hazardous materials abatement with unit prices for asbestos removal, PCB waste disposal, and radon mitigation systems, as well as alternates for community room renovation, asphalt and concrete repair work, gazebo and shed removal, and septic system work.
The project is funded by Community Development Block Grant (CDBG) funds through the Connecticut Department of Housing (DOH) and Connecticut Housing Finance Authority (CHFA), requiring compliance with federal Davis-Bacon prevailing wage rates and state prevailing wage determinations, with both Connecticut Department of Labor and federal wage rates applying where conflicts exist, resulting in the higher rate being mandated. A 5% bid bond is required, and the successful bidder must provide 100% performance and payment bonds, along with comprehensive insurance including $1,000,000 minimum coverage for comprehensive general liability, commercial auto liability, and contractor's protective liability, plus worker's compensation with higher limits ($2,000,000) for lead and asbestos abatement work. The contractor must maintain a 5% retainage with lien waiver requirements beginning with payment application #2, and liquidated damages are set at $250 per calendar day for failure to meet contract deadlines. The specifications include detailed requirements for shop drawing submittals, certified weekly payroll reports, OSHA 10-hour safety training documentation, and compliance with Section 3 worker requirements and equal employment opportunity provisions, with final payment withheld until all documentation, permits, and hazardous materials shipment records are submitted.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P ro ject Manua l
REBID
GENERAL RENOVATIONS
OLD POST VILLAGE SENIOR HOUSING
764 Tolland Stage Road Tolland, Connecticut
Owner
TOLLAND HOUSING AUTHORITY
763 Tolland Stage Road Tolland, Connecticut 06084
Kelly McDermott, President & CEO
Elderly Housing Management Property Manager
Bid Opening:
Tuesday, March 3, 2026 @ 2:00 p.m.
Mandatory Pre-Bid Meeting:
Thursday, February 12, 2026 @ 2:00 p.m.
BID & CONSTRUCTION SET
Bid Documents Issue Date:
February 2, 2026 CSA Project 24-10
THIS PAGE IS INTENTIONALLY LEFT BLANK
(FOR DUPLEX PRINTING PURPOSES)
CAPITAL STUDIO ARCHITECTS GENERAL RENOVATIONS
1379 Main Street OLD POST VILLAGE SENIOR HOUSING East Hartford, Connecticut 06108 764 Tolland Stage Road 860-289-3262 Tolland, Connecticut capitalstudio.net CSA PROJECT 24-10
TABLE OF CONTENTS
T.O.C. / 1 of 8
T A B L E O F C O N T E N T S
GENERAL RENOVATIONS
OLD POST VILLAGE SENIOR HOUSING
734 TOLLAND STAGE ROAD
TOLLAND, CONNECTICUT
CSA Project 24-10
T I T L E
1.) Title Page 2.) Table of Contents
A. BID SOLICITATION: _______________________________________________________________ 1.) Invitation to Bid
B. BIDDING DOCUMENTS:
1.) List of Required Documents NOTE: Each bid package must include one (1) set of the following forms and documents
(INCOMPLETE BID PACKAGES WILL NOT BE ACCEPTED)
2.) Bonding and Insurance Requirements
3.) BID SUBMITTAL:
REQUIRED SUPPLEMENTS TO BE SUBMTTED WITH BID FORM:
• Supplements to Bid Form Statement
• Supplements to Bid Form Signature(s)
• Appendix A - List of Subcontractors
• Appendix B - List of Allowances
• Appendix C - List of Alternates
• Appendix D - List of Unit Prices
• Appendix E - Schedule of Values
• Appendix F - BABA Notification and Certification
• Appendix G - BABA Materials Certification Form
• Permitting Requirements
• Bid Bond (Refer to Bonding and Insurance Requirements for details)
• Non-Collusion Affidavit of Prime Bidder
• Certificate as to Corporate Principal
• Statement of Contractor’s Qualifications (AIA Document A305-1986)
• CDBG Contractor’s Certification Concerning Labor Standards and Prevailing Wage Rates
• CDBG Subcontractor’s Certification Concerning Labor Standards and Prevailing Wage Rates
• Commission on Human Rights Bidder Notification to Bidders and Compliance Reports:
PART I - Bidder Information PART II - Bidder Nondiscrimination Policies and Procedures PART III - Bidder Subcontracting Practices PART IV - Workforce Analysis PART V - Bidder Hiring and Recruitment Practices
• Non-discrimination Laws/Executive Orders
• Equal Employment Opportunity (Executive Order 11246, as amended)
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 2 of 8
• General Contractor’s Certification of Bidding Regarding Equal Employment Opportunity
• Sub-Contractor’s Certification of Bidding Regarding Equal Employment Opportunity
• Section 3 Contractor Requirements
• General Contractor’s Section 3 Plan Certification
ADDITIONAL REQUIRED DOCUMENTS TO BE PROVIDED BY CONTRACTOR AT BID SUBMISSION:
• Contractor’s Current Trade License, i.e. Major Contractor, Plumber, Electrician, etc. as well as Asbestos Abatement Supervisor/Worker(s) if applicable in addition to all Apprentice Certificate(s) and Current Insurance Certificate(s).
• Contractor’s Insurance Certificate (contractor to supply) - Refer to Bonding and Insurance Requirements for details.
4.) SUPPLEMENTARY CONDITIONS AND WAGE REQUIREMENTS:
• D.O.H. Program Requirements (includes project sign)
• Federal Labor Standards Provisions
• Section 31-53b: Construction Safety and Health Course
• Information Bulletin: The 10-Hour OSHA Construction Safety and Health Course
• Notice For All Mason Contractors Regarding Statute 31-53
• CT General Statute 31-55a
• CT General Statute 31-53 Wage Certification Documents
• Information Bulletin: Occupational Classification
• Wage & Workplace Footnotes
• Federal Labor Wage Decision
• State of Connecticut Prevailing Wage Rates
C. CONTRACT CONDITIONS AND FORMS REQUIRED AT CONTRACT SIGNING: __________________ 1.) CHFA Contractor Addenda REV Dec 2025 2.) Standard Form of Agreement between Owner and Contractor (AIA Document A101) 3.) General Conditions of the Contract for Construction (AIA Document A201) 4.) Instructions to Bidders (AIA Document A701) 5.) Performance Bond (AIA Document A312) 6.) Payment Bond (AIA Document A312)
D. DOCUMENTS TO BE SUBMITTED FOR ALL EMPLOYEES AND SUBCONTRACTORS PRIOR TO WORK:
• Permits as required by the Town of Tolland, CT. Tolland will not waive any permit fees.
• Information Bulletin: The 10-Hour OSHA Construction Safety and Health Course
• CDBG Subcontractor’s Certification Regarding Equal Employment Opportunity
• CDBG Subcontractor’s Certification Concerning Labor Standards and Prevailing Wage Rates
• Current Trade License, i.e. Major Contractor, Plumber, Electrician, etc. as well as Asbestos
Abatement Supervisor/Worker(s) if applicable in addition to all Apprentice Certificate(s) and Current Insurance Certificate(s).
• All Social Security Numbers on company letterhead (last four digits are acceptable) .
E. CERTIFIED PAYROLL REQUIREMENTS: ________________________________________________ 1.) Items to be submitted with each Payment Application:
• Original Weekly Certified Payroll Forms
• State and Federal Statements of Compliance from General Contractor and all Subcontractors.
• Final Certified Payrolls must be clearly marked as “Final.”
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 3 of 8
F. LIEN WAIVERS AND RETAINAGE PAYMENT: ___________________________________________ 1.) Waiver of Lien Form
• Original Partial or Final Lien Waivers required from General Contractor; All Subcontractors and Major Suppliers are required beginning with submission of Payment Application #2.
• Original Final Lien Waivers from General Contractor, All Subcontractors and Major Suppliers with submission of retainage payment application.
• It is recommended that the form “Waiver of Lien” attached be used. If a substitution is used, please be sure it contains all the same information.
2.) List of Documents Required Prior to Submission of Retainage Payment Application:
• PAYMENTS INCLUDING THE STANDARD 5% RETAINAGE WILL NOT BE PROCESSED UNTIL ALL
REQUIRED DOCUMENTS ARE SUBMITTED. IF ANY EMPLOYEE OR SUBCONTRACTOR STARTS
WORK ON THE PROJECT PRIOR TO REQUIRED PAPERWORK BEING SUBMITTED, A PORTION OF
THE CONTRACT AMOUNT MAY BE DEDUCTED THROUGH A CHANGE ORDER.
ADDITIONAL REQUIRED DOCUMENTS TO BE PROVIDED BY CONTRACTOR:
• Certificate of Completion as required by the Town of Tolland, CT.
• Certificate of Substantial Completion.
G. TECHNICAL SPECIFICATIONS - GENERAL REQUIREMENTS: ________________________________
T E C H N I C A L S P E C I F I C A T I O N S :
DIVISION 1 - GENERAL REQUIREMENTS
Section 00900 - Special Conditions Section 01200 - Summary of the Work Section 01100 - Hazardous Materials General Conditions Section 01160 - Scheduling and Phasing Section 01210 - Allowances Section 01220 - Hazardous Materials - Unit Prices (include on Bid Form) Section 01230 - Alternates Section 01270 - Unit Prices Section 01290 - Payment Procedures Section 01400 - Submittals Section 01500 - Cutting and Patching Section 01600 - Product Requirements Section 01700 - Hazardous Material Contract Close-out Section 01732 - Selective Demolition Section 01770 - Closeout Procedures Section 01780 - Project Record Documents
DIVISION 2 - SITEWORK
Section 02070 - Site Demolition Section 02080 - Asbestos Abatement Section 02082 - Universal Waste Reclamation Section 02094 - Radon Mitigation Section 02100 - Site Preparation
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 4 of 8
Section 02110 - PCB Remediation Section 02200 - Earthwork Section 02505 - Asphalt Pavement Reclamation Section 02510 - Bituminous Concrete Pavement Section 02580 - Pavement Markings Section 02605 - Drainage Structures Section 02610 - Buried Pipe Installation Section 02750 - Concrete Paving Section 02930 - Seeding
DIVISION 3 - CONCRETE
Section 03300 - Cast-In-Place Concrete
DIVISION 4 - MASONRY (not used)
DIVISION 5 - METALS
Section 05521 – Pipe and Tube Railings
DIVISION 6 - WOODS AND PLASTICS
Section 06100 - Rough Carpentry Section 06200 - Finish Carpentry
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
Section 07200 - General Building Insulation Section 07220 - Blown-in Cellulose Insulation Section 07300 - Asphalt Shingle Roofing Systems Section 07464 - Vinyl Siding, Trim and Accessories Section 07600 - Sheet Metal Flashing and Trim Section 07630 - Gutters and Downspouts Section 07900 - Sealants
DIVISION 8 - DOORS AND WINDOWS
Section 08100 - Fiberglass Doors Section 08110 - Hollow Metal Doors and Frames Section 08150 - Storm Doors Section 08160 - Molded Composite Doors Section 08211 - Flush Wood Doors Section 08310 - Attic Doors and Frames Section 08311 - Access Doors and Frames Section 08560 - Vinyl Windows Section 08710 - Finish Hardware
DIVISION 9 - FINISHES
Section 09250 - Gypsum Board Section 09627 - Luxury Vinyl Tile and Plank Section 09652 - Resilient Sheet Flooring Section 09653 - Vinyl Wall Base Section 09900 - Painting
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 5 of 8
DIVISION 10 - SPECIALTIES
Section 10400 - Signage Systems Section 10550 - Postal Specialties Section 10800 - Toilet and Bath Accessories
DIVISION 11 - EQUIPMENT
Section 11450 - Residential Appliances
DIVISION 12 - FURNISHINGS
Section 12300 - Residential Casework Section 12366 - Solid Surface Countertops Section 12491 – Horizontal Louver Blinds
DIVISION 13 - SPECIAL CONSTRUCTION (not used) DIVISION 14 - CONVEYING SYSTEMS (not used)
DIVISION 15 - MECHANICAL
Section 15010 - General Conditions for Mechanical Trades Section 15050 - Basic Mechanical Materials and Methods Section 15071 - Mechanical Vibration & Seismic Controls Section 15075 - Mechanical Identification Section 15081 - Duct Insulation Section 15083 - Pipe Insulation Section 15110 - Valves Section 15121 - Pipe Expansion Fittings and Loops Section 15122 - Meters and Gages Section 15140 - Domestic Water Piping Section 15150 - Sanitary Waste and Vent Piping Section 15160 - Storm Drainage Piping Section 15183 - Refrigerant Piping Section 15430 - Plumbing Specialties Section 15815 - Metal Ducts Section 15820 - Duct Accessories Section 15900 - HVAC Instrumentation and Controls Section 15990 - Testing, Adjusting and Balancing
DIVISION 16 - ELECTRICAL
Section 16010 - General Conditions for Electrical Trades Section 16050 - Basic Electrical Materials and Methods Section 16060 - Grounding and Bonding Section 16111 - Fire Alarm Section 16120 - Conductors and Cables Section 16130 - Raceways and Boxes Section 16140 - Wiring Devices Section 16145 - Lighting Control Devices Section 16231 - Engine Generator Section 16410 - Enclosed Switches and Circuit Breakers Section 16415 - Transfer Switches Section 16442 - Panel Boards Section 16491 - Fuses
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 6 of 8
Section 16511 - Interior Lighting
LIST OF DRAWINGS
TITLE SHEE T
HAZARDOUS M ATERIALS:
HM-1.0 Building #1 – Hazardous Building Material Abatement Plan HM-1.1 Building # 2 and #5 – Hazardous Building Material Abatement Plans HM-1.2 Building #3 – Hazardous Building Material Abatement Plan HM-1.3 Building #4 – Hazardous Building Material Abatement Plan
SITE/CIVIL:
C-0 CIVIL COVER SHEET
C-1A Boundary Survey / Existing Conditions Plan C-1B Existing Conditions and Demolition Plan C-2 Layout Plan C-3 Grading Plan C-4 Utility Plan C-5 Septic Notes & Details C-6 Details C-7 Septic Profiles
ARCHITECTURAL
G-1 General Project Data and Wall Types
SP-1 Site Architectural Plan SP-2 Site Details
A-1.0 Building #1 – Demolition Floor Plan A-1.1 Building #1 – New Construction Floor Plan A-1.2 Building #2 and #5 – Floor Plans A-1.3 Building #3 – Floor Plan A-1.4 Building #4 – Floor Plan
A-2.1 Building #1 – Front and Left Elevations A-2.1a Building #1 – Rear and Right Elevations A-2.2 Buildings #2 and #5 – Elevations A-2.3 Building #3 – Elevations A-2.4 Building #4 – Elevations
A-3.1 Building #1 – Roof & Structural Framing A-3.1a Building #1 – Roof Plan A-3.2 Buildings #2 and #5 – Roof Plans A-3.3 Building #3 – Roof Plan A-3.4 Building #4 – Roof Plan A-3.5 Roof Details
A-4.1 Building #1 - Sections and Details A-4.2 Building #1 – Details A-4.3 Window & Door Sections
A-5.0 Bathroom Accessory Schedule and Plans A-5.1 Bathroom Elevations
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 7 of 8
A-5.2 Bathroom Elevations A-5.3 Kitchen Elevations A-5.4 Kitchen Elevations A-5.5 Interior Details
A-6.1 Door, Window and Frame Types A-6.2 Door, Finish and Hardware Schedules
PLUMB ING
P-101 Plumbing – Plumbing Drainage & Vent Piping Floor Plans – Building #1 P-102 Plumbing – Supply Piping Floor Plans – Building #1 P-103 Plumbing – Floor Plans – Buildings #2 thru #5 P-501 Plumbing – Details and Schedules
MECHANCIAL
M-101 HVAC – Floor Plans - Building #1 M-102 HVAC – Floor Plans - Buildings #2 thru #5 M-501 HVAC – Details and Schedules
ELECTRICAL
E-101 Electrical – Floor Plans - Building #1 E-102 Electrical – Floor Plans - Buildings #2 thru #5 E-501 Electrical – Details and Schedules
END OF TABLE OF CONTENTS
East Hartford, Connecticut 06108 764 Tolland Stage Road
T.O.C. / 8 of 8
Section A
BID SOLICITATION
INVITATION TO BID
Sealed bids for furnishing all labor, materials, tools, services, and equipment necessary to complete the “General Renovations for Old Post Village, Tolland CT” will be received at the Tolland Town Manager’s Office located at 21 Tolland Green, Level 5, Tolland, CT 06084 until 2:00 p.m. on March 3, 2026. Bids received after 2:00 p.m. will not be opened. Bid Opening will be shortly thereafter at the Old Post Village Community Room 763 Tolland Stage Road, Tolland, CT 06084.
The successful bidder will be required to furnish and pay for 100% Performance and Payment Bonds. The successful bidder must have the minimum insurance coverage required by the CT Department of Housing.
Bidders are required to furnish all labor, materials, tools, and equipment necessary to complete the project in accordance with the Contract documents, including plans and specifications dated September 18, 2025 as prepared by Capital Studio Architects, LLC; 1379 Main Street, East Hartford, CT 06108.
Contract documents, including plans, specifications and addendums can also be reviewed and/or purchased online starting February 2, 2026 at the Public Jobs Plan Room of Advanced Reprographics, 50 Corporate Drive. Plainville, CT 06062; www.advancedplanroom.com or by calling them at 860-410-1020.
A mandatory pre-bid walk through will be held on site in the Community Room at Old Post Village, 763 Tolland Stage Road, Tolland, CT at 2:00 p.m. on February 12, 2026.
A satisfactory Bid Bond or Certified Check, in an amount equal to five percent (5%) of the base bid, shall be submitted with each bid. The Bid Bond shall be made payable to Tolland Housing Authority and shall be properly executed by the Bidder and acceptable sureties. All bonds must be from sureties registered in the State of Connecticut.
This project is funded by the CT Department of Housing and requires compliance with the Equal Employment Opportunity provisions of Executive Order 11246; Non Discrimination Provisions of Title VI of the Civil Rights Act of 1964; labor Standards Provision of the Davis- Bacon Act and related acts and Contract Work Hours Standards Act;
Section 3 Contractor Requirements; DOH Program Requirements; Prevailing Wage determinations as issued by the Connecticut Department of Labor; and Prevailing Wage determinations as issued by the United States Department of Labor, and other provisions outlined in the bid documents.
Bids, to receive consideration, must be in the hands of the authorized representative no later than the day and hour mentioned above. No bids shall be withdrawn for a period of sixty (60) days after the opening of bids, without the consent of the above Authority.
The Tolland Authority and their designated agents reserve the right to accept or reject any or all options, bids, or proposals; to waive any technicality in any bid or part thereof, and to accept any bid deemed to be in the best interest of the Tolland Housing Authority.
The Tolland Housing Authority is an Affirmative Action/Equal Opportunity Employers, and encourage bid submissions from Section 3 firms, MBE’s, WBE’s and SBE’s.
Dated this ___________________________ Kelly McDermott, President & CEO, Elderly Housing Management, for the Tolland Housing Authority http://www.advancedplanroom.com/
Section B
BIDDING DOCUMENTS
LIST OF REQUIRED DOCUMENTS
Please use the following as a guide to be sure all required paperwork is submitted
EACH BID PACKAGE SHALL INCLUDE ONE SET OF THE FOLLOWING FORMS AND DOCUMENTS
(INCOMPLETE BID PACKAGES WILL NOT BE ACCEPTED)
• Bid Bond (Refer to Bonding and Insurance Requirements for details)
• Bid Form
• Supplements to Bid Form:
o Appendix A – List of Subcontractors o Appendix B – List of Allowances (not used) o Appendix C – List of Alternates o Appendix D – List of Unit Prices o Appendix E – Schedule of Values o Appendix F – BABA: “Build America, Buy America Act” (BABA) - Notification and
Certification.
o Appendix G – BABA: “Build America, Buy America Act (BABA) - Materials Certification
Form.
• Non-collusion Affidavit of Prime Bidder
• Certificate as to Corporate Principal
• Statement of Contractor’s Qualifications
• Contractor’s Certification Concerning Labor Standards and Prevailing Wage Rates
• Bidder Contract Compliance Reports:
Part I – Bidder Information Part II – Bidder Nondiscrimination Policies and Procedures Part III – Bidder Subcontracting Practices Part IV – Workforce Analysis Part V – Bidder Hiring and Recruitment Practices
• Contractor’s Certification Regarding Equal Employment Opportunity
• General Contractor’s Section 3 Plan Certification
• CT Dept. of Labor Contractor’s Wage Certification Form
• Current Trade License, i.e. Major Contractor, Plumber, Electrician, etc. as well as Asbestos Abatement
Supervisor/Worker(s) if applicable in addition to all Apprentice Certificate(s) and Current Insurance Certificate(s). Refer to Bonding and Insurance Requirements.
• Contractor’s Insurance Certificate (Refer to Bonding and Insurance Requirements for details)
LIST OF REQUIRED DOCUMENTS AT CONTRACT SIGNING
• Performance, Labor, and Materials Bonds
REQUIRED DOCUMENTS TO BE SUBMITTED FOR ALL EMPLOYEES AND SUBCONTRACTORS PRIOR
TO WORK COMMENCING
• Permits as required by the Town of Tolland, CT. Tolland will not waive any permit fees.
• The OSHA 10-hour Construction Safety and Health Course
• Subcontractor’s Certification Regarding Equal Employment Opportunity
• Subcontractor’s Certification Concerning Labor Standards and Prevailing Wage Rates
• Current Trade License, i.e. Major Contractor, Plumber, Electrician, etc. as well as Asbestos Abatement
Supervisor/Worker(s) if applicable in addition to all Apprentice Certificate(s) and Current Insurance Certificate(s).
• All Social Security Numbers on company letterhead (last four digits is acceptable)
CERTIFIED PAYROLL REQUIRMENTS
• Original Weekly Certified Payrolls
• State and Federal Statements of Compliance forms from General Contractor and all Subcontractors
• Final Certified Payrolls must be clearly marked as Final
LIEN WAIVERS
• Original Partial or Final Lien Waivers required from General Contractor, All Subcontractors and Major
Suppliers are required beginning with submission of payment application #2
• Original Final Lien Waivers from General Contractor, All Subcontractors and Major Suppliers with submission of retainage payment application.
• It is recommended that the form located within the spec manual be used. If a substitution is used please be sure it contains all of the same information.
LIST OF REQUIRED DOCUMENTS PRIOR SUBMISSION OF RETAINAGE PAYMENT APPLICATION
• Certificate of Completion as required by the Town
• Certificate of Substantial Completion
PAYMENTS INCLUDING THE STANDARD 5% RETAINAGE WILL NOT BE PROCESSED UNTIL
ALL REQUIRED DOCUMENTS ARE SUBMITTED. IF ANY EMPLOYEE OR SUBCONTRACTOR
STARTS WORK ON THE PROJECT PRIOR TO REQUIRED PAPERWORK BEING SUBMITTED, A
PORTION OF THE CONTRACT AMOUNT MAY BE DEDUCTED THROUGH A CHANGE ORDER.
BONDING AND INSURANCE REQUIREMENTS
A state or local unit of government receiving a grant from the Federal Government which requires contracting for construction of facility improvement shall follow its own requirements relating to bid guarantees, performance bonds, and payment bonds, except for contracts or subcontracts exceeding $100,000.00. For contracts or subcontracts exceeding $100,000.00 the Federal agency may accept the bonding policy and requirements of the grantee provided the Federal agency has made a determination that the Government’s interest is adequately protected. If such a determination has not been made, the minimum requirements shall be as follows:
a. A bid guarantee from each bidder equivalent to five percent (5%) of the bid price. The “bid guarantee” shall consist of a firm commitment such as a bid bond, certified check, or other negotiable instrument accompanying a bid as assurance that the bidder will, upon acceptance of his/her bid, execute such contractual documents as may be required within the time specified.
b. A performance bond on the part of the contractor for one hundred percent (100%) of the contract price. A “performance bond” is one executed in connection with a contract to secure fulfillment of all the contractor’s obligations under such contract.
c. A payment bond on the part of the contractor for one hundred percent (100%) of the contract price.
A “payment bond” is one executed in connection with a contract to assure payment as required by law of all persons supplying labor and material in the execution of the work provided for in the contract.
d. Comprehensive General Liability. The contractor shall be covered under Comprehensive General
Liability insurance with a minimum coverage amount of $1,000,000.
e. Commercial Auto Liability. The contractor shall be covered under Commercial Auto Liability insurance with a minimum coverage amount of $1,000,000.
f. Contractor’s Protective Liability. The contractor shall be covered under Contractor’s Protective
Liability insurance with a minimum coverage amount of $1,000,000.
g. Worker’s Compensation & Employer’s Liability. (Note: when lead based and/or asbestos abatement work is undertaken, direct & indirect damages arising from these activities must be covered.) The contractor shall be covered under Worker’s Compensation & Employer’s Liability insurance with the following minimum coverage amounts: Bodily injury by accident, $1,000,000/accident; Bodily injury by disease, $1,000,000/employee; Bodily injury by disease, $1,000,000 policy limit or $100,000/$500,000/$100,000 when not involving hazardous material abatement.
h. Certificates of Insurance for all subcontractors’ Workers Compensation & Employer’s Liability.
(Note: when lead based and/or asbestos abatement work is undertaken, direct & indirect damages arising from these activities must be covered.) The contractor shall provide certificates of insurance for Worker’s Compensation & Employer’s Liability insurance with the following minimum coverage amounts: Bodily injury by accident, $1,000,000/accident; Bodily injury by disease, $1,000,000/employee; Bodily injury by disease, $1,000,000 policy limit or $100,000/$500,000/$100,000 when not involving hazardous material abatement.
BID SUBMITTAL
page / 1 of 10
BID FORM
DATE: ________________________
DELIVER TO:
Tolland Town Manager’s Office 21 Tolland Green, Level 5 Tolland, CT 06084
ATTN: Kelly McDermott, President & CEO / Elderly Housing Managment
FROM:
To Whom It May Concern:
The Contract award will be made to the lowest responsible bidder. The Authority reserves the right to reject all bids, and to waive any informality in the bids when such action is deemed to be in the best interest of the Authority. The Authority further reserves the right to increase or decrease the award, in accordance with the availability of funds. The Authority reserves the right to negotiate all Allowance, Alternate Price, and Unit Price bid amounts when, in the opinion of the Authority, those prices do not accurately reflect either quantity of work, current fair market value or competitive pricing. The Contract Award shall be made on available funds; the housing authority reserves the right to add/deduct work based on the availability of funds.
BID OPENING:
Bid delivery is to Tolland Town Hall. Bid opening will be at the Old Post Village Community Room.
Bids will be delivered from the Town Hall to the Community Room immediately after the bid deadline, and opened upon arrival for benefit of any resident wanting to attend.
page / 2 of 10
BID FORM (cont’d)
The undersigned bidder, having examined the Contract Documents, the site, and being familiar with all of the conditions, hereby proposes to furnish and install, complete and in place, “General Renovations for Old Post Village, Tolland, CT”, including all design services, plant, materials, supplies, machinery, equipment, tools, superintendence, labor, insurance, bonds, permits, construction stakeout, overhead, profit, and other accessories and services, in accordance in accordance with these Contract Documents, including all addenda, no exceptions taken, for the bid prices below. The final project price will be adjusted to reflect actual work performed and will be paid for at the unit prices identified in the bid.
Were hereby certify and affirm that the attached list includes all defects, errors, inconsistencies, and omissions in the bidding and proposed Contract Documents, of which we are aware, either directly or indirectly or by notification from any sub-bidder or material supplier. (If none, enter “NONE” below)
We hereby certify that we have received all Addenda (Addendum) inclusive, as follows
#_______________ Date ______________________
#_______________ Date ______________________
#_______________ Date ______________________
#_______________ Date ______________________
#_______________ Date ______________________
BASE BID
_______________________________________________________________________ DOLLARS
(Base Bid Price in Words)
$ _________________________________________________ DOLLARS
(Base Bid Price in Figures) page / 3 of 10
SUPPLEMENTS TO BID FORM
Respectfully Proposed by: On: ______________________________
Date Company Name Signature
Company Address Typed Name
Title
If a Corporation: (Corporate Seal)
Incorporated in the State of: _______________________Or Commonwealth of: ____________________
Date:
Submitted by: (full name)
(full address)
The Supplements to Bid Form Appendices listed below shall be provided and considered an integral part of the Bid Form. These Appendices are as follows:
Appendix A – List of Subcontractors: Include the names of all Subcontractors and the portions of the Work they will perform.
Appendix B – Allowances: Include the costs on form provided.
Appendix C – Alternates: Include the costs on form provided.
Appendix D – Unit Prices: Include the costs on form provided.
Appendix E – Schedule of Values: Include an itemized list of the Bid Price applicable to the Work.
Appendix F – BABA: “Build America, Buy America Act” (BABA) - Notification and Certification.
Appendix G – BABA: “Build America, Buy America Act (BABA) - Materials Certification Form.
page / 4 of 10
SUPPLEMENTS TO BID FORM SIGNATURE(S)
The Corporate Seal of
(Bidder – please print the full name of your Proprietorship, Partnership, or Corporation) was hereunto affixed in the presence of:
(Authorized signing officer Title)
(Seal)
(Authorized signing officer Title)
(Seal) page / 5 of 10
APPENDIX “A” – LIST OF SUBCONTRACTORS
Herewith is the list of Subcontractors referenced in the bid submitted by:
(Bidder)
Dated and which is an integral part of the Bid Form.
In accordance with the bid documents, we hereby submit a completed List of Subcontractors. The Owner reserves the right to reject a proposed Subcontractor for reasonable cause. Refer to AIA Article 5 of General Conditions.
The following work will be performed (or provided) by Subcontractors and coordinated by us. This list comprises all the subcontractors to be employed on this project:
WORK SUBJECT SUBCONTRACTOR CONTRACT VALUE
page / 6 of 10
APPENDIX “B” – LIST OF ALLOWANCES
The following is a list of Allowances referenced in the bid submitted by:
Dated and which is an integral part of the Bid Form.
I certify that the following Allowance amount(s) listed below are included within the Base Bid Price total.
A. Provide an Allowance of $50,000 for new finishes in the existing Community Center page / 7 of 10
APPENDIX “C” – LIST OF ALTERNATES
The following is a list of Alternates referenced in the bid submitted by:
The following amounts shall be added to or deducted from the Bid Price. This form requests a “difference” in bid price by adding to or deducting from the base bid price using the Alternates listed below.
ALTERNATE No. 1 (DEDUCT) – COMMUNITY ROOM RENOVATION.
ALTERNATE No. 2 (DEDUCT)– ASPHALT AND CONCRETE REPAIR WORK.
ALTERNATE No. 3 (DEDUCT) – GAZEBO & SHED.
ALTERNATE No. 4 (ADD) – SEPTIC WORK.
page / 8 of 10
APPENDIX “D” – LIST OF UNIT PRICES
The following is the list of Unit Prices referenced in the bid submitted by:
Dated and which is an integral part of the Bid Form.
We propose and agree that, should the amount of work required be increased or decreased, by a request of the Owner, the following Unit Prices will be the basic price for computing extra cost or credit. It is understood that the right is reserved by the Owner to reject or negotiate any or all the Unit Prices.
Each Unit Price includes all equipment, tools, labor, permits, fees, overhead and profit, etc. incidental to completion of the work involved and the disposal of surplus or unsuitable material in accordance with the Plans and Specifications or as directed by the Architect. Unit Prices will be decreased ten percent (10%) if change requested is a reduction in work.
UNIT PRICES:
UNIT PRICE No. 1 – REMOVAL AND DISPOSAL OF FLOOR TILE AND MASTIC. DISPOSE OF AS REGULATED ASBESTOS
WASTE AND PRESUMED PCB WASTE >50PPM.
$__________________________ per square foot.
UNIT PRICE No. 2 – REMOVAL AND DISPOSAL OF SINK WITH ASBESTOS UNDERCOATING. DISPOSE OF AS
REGULATED ASBESTOS WASTE AND PRESUMED PCB WASTE >50 PPM.
$__________________________ per sink.
UNIT PRICE No. 3 – REMOVAL AND DISPOSAL OF GYPSUM WALL BOARD WITH ASBESTOS JOINT COMPOUND.
DISPOSE OF AS REGULATED ASBESTOS WASTE AND PRESUMED PCB WASTE >50 PPM.
UNIT PRICE No. 4 – REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING TEXTURED CEILING PAINT. DISPOSE OF
AS REGULATED ASBESTOS WASTE AND PRESUMED PCB WASTE >50 PPM.
UNIT PRICE No. 5 – INSTALLATION OF RADON SUCTION PIT AND MITIGATION SYSTEM WITH PIPING, ELECTRICAL, FAN UNIT, ALARM, AND ALL ASSOCIATED CONSTRUCTION WORK.
$__________________________ per system.
page / 9 of 10
UNIT PRICE No. 6 – Plywood Roof Sheathing Replacement (FULL SHEET):
$__________________________ per 4’x 8’ SHEET.
UNIT PRICE No. 7 – Plywood Roof Sheathing Replacement (HALF SHEET):
$__________________________ per 4’x 4’ SHEET.
UNIT PRICE No. 8 – Wood Fascia Replacement:
$__________________________ per 4’ PIECE.
UNIT PRICE No. 9 – Wood Rake Replacement:
$__________________________ per 4’ PIECE.
page / 10 of 10
APPENDIX “E” – SCHEDULE OF VALUES
The following is the Schedule of Values Itemization of the base bid submitted by:
Schedule of Values Itemization shall be based on individual specification sections. Provide breakdown for each building and provide total.
General Renovations for Old Post Village, Tolland CT
SPEC SECTION WORK SUBJECT CONTRACT VALUE
BID TOTAL $_________________
Appendix F – BABA: “Build America, Buy America Act” (BABA) - Notification and Certification.
Attachment 4-16
PURPOSE: The “Buy America Certification Form” is used to certify that, as required by federal law, all of the iron, steel (for FY23 funded projects and forward) , specific construction materials – non-ferrous metals, lumber, composite building materials, plastic and polymer based pipe and tube, (for FY24 funded projects and forward), all construction materials, including manufactured products (for FY25 funded projects and forward) utilized in federally funded projects with an aggregate of $250,000 or more funds, including HUD CDBG funds, are produced in the United States in a manner that complies with the Build America, Buy America Act, unless an applicable waiver applies or is granted by the Made in America Office of Management and Budget (MIAO).
GENERAL INFORMATION: BABA guidance requires the following Buy America preference: 1) All iron and steel used in the project are produced in the United States. This means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States; 2) All listed manufactured products used in the project are produced in the United States. This means the manufactured product was manufactured in the United States, and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation; and, for FY 2025 funded projects forward; 3) All (listed and non-listed) construction materials are manufactured in the United States. This means that all manufacturing processes for the construction material occurred in the United States. The Build America, Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.
CERTIFICATION: I hereby certify the materials to be installed pursuant to the attached Bid Submittal conform to the Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. 177-58. Signing this document does not relieve the signee of providing evidence of compliance upon request by DOH or HUD.
Prime Contractor:
Phone Number:
Email:
The Prime Contractor is responsible for all subcontractors and for ensuring that all manufacturers and suppliers certify materials with the understanding that those certifying the material assume full legal responsibility of the material and are subject to providing documentation verifying the material meets all requirements upon demand. Any additional materials needed for the project should be itemized, specify if BABA applies, and then certified by the engineer and submittal to DOH with an official Change Order.
* Attach the itemized cost estimate that identifies all materials subject to BABA.
Appendix G – BABA: “Build America, Buy America Act (BABA) - Materials Certification Form.
Attachment 4-17
Build America Buy America Materials Certification
Grantee: Contract Number:
Contractor: Invoice Period:
Material Type (Steel, Iron, Manufactured
Goods, Construction Materials)
Description
Name of Manufacturer
Location of Product
By signing, I certify that the statements made above are true to the best of my ability and knowledge and that the listed materials for use in this project funded by federal dollars were produced in the United States of America.
Contractor Signature:
Print Contractor Name:
Contractor Company:
Permitting Requirements
● The awarding contractor and all subcontractors will be responsible for securing all necessary local permits from the Town of Tolland Building Department and Eastern Highlands Health District, as applicable, prior to any work commencing.
● Town Permit fees will be waived with the exception of the State required education fee, as well as any necessary permit fees from Eastern Highland Health District.
● Permits are to be properly displayed at the job location.
● A final inspection from the Tolland Building Official and Eastern Highlands Health District, as applicable, is required upon completion of all work.
● Copies of all permits and final inspections must be submitted to the Tolland Housing Authority immediately upon receipt.
PAYMENTS INCLUDING THE STANDARD 5% RETAINAGE WILL NOT BE
PROCESSED UNTIL ALL OF THE ABOVE DOCUMENTS ARE IN PLACE AND
SUBMITTED TO THE APPROPRIATE PARTIES. IF ANY EMPLOYEE OR
SUBCONTRACTOR STARTS WORK ON THE PROJECT PRIOR TO THE REQUIRED
PAPERWORK BEING FILED AND SUBMITTED, ALL WORK MUST CEASE AND A
PORTION OF THE CONTRACT AMOUNT MAY BE DEDUCTED THROUGH A
CHANGE ORDER.
BID BOND
KNOW ALL MEN BY THESE PRESENTS, that we the undersigned as Principal, and _______________________________________________________________ as Surety are held and firmly bound unto_____________________________________________
"Owner", in the penal sum of _______________________________________________Dollars, ($__________________________), lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has submitted the Accompanying Bid, dated ____________________ 20_____, for ______________
NOW THEREFORE, if the Principal shall not withdraw said Bid within the period specified therein after the opening of the same, or within any extended time period agreed to by the Principal, Surety and Owner, or, if no period be specified, within thirty (30) days after the said opening, and shall within the period specified therefore, or if no period be specified, within ten (10} days after the prescribed forms are presented to him for signature, enter into a written Contract with the Owner in accordance with the Bid as accepted, and give bond with good and sufficient surety or sureties, as may be required, for the faithful performance and proper fulfillment of such Contract; then the above obligation shall be null and void and of no effect, otherwise to remain in full force or virtue.
Failure to comply with the aforementioned condition shall result in the forfeiture of this Bid Bond as liquidated damages.
IN WITNESS WHEREOF, the above-bounded parties have executed this instrument under their several seals this _______ day of ___________________, 20___, the name and corporate seal of each corporate party being hereto affixed and these presents signed by its undersigned representative, pursuant to authority of its governing body.
No extension of time or other modification of this Bid Bond shall be valid unless agreed to in writing by the parties of this Bond.
In presence of:
______________________________________________________________________ (SEAL)
(Individual Principal)
(Business Address)
_______________________________ _______________________________ (SEAL)
Attest: By:____________________________
(Corporate Principal)
By: ____________________________ (Affix Corporate Seal)
Attest:
(Corporate Surety)
By: ____________________________ (Affix Corporate Seal)
Countersigned By: ________________________________________________________
*Attorney-in-Fact, State of __________________________________________________
*Power-of-Attorney for person signing for Surety Company must be attached to Bond.
NON-COLLUSION AFFIDAVIT OF PRIME BIDDER
State of _____________________________ ) County of ___________________________ )
___________________________________________, being first duly sworn, deposes and says that:
1. He is ___________________________________ of ________________________________, the bidder who has submitted the attached bid;
2. He is fully informed respecting the preparation and contents of the attached bid and of all pertinent circumstances respecting such Bid;
3. Such Bid is genuine and is not a collusive or sham Bid;
4. Neither the said Bidder, nor any of its officers, partners, owners, representatives, employees, or parties in interest, including this affiant has in any way colluded, conspired, connived or agreed, directly or indirectly with any other bidder, firm or person to submit a collusive or sham bid in connection with the contract for which the attached bid has been submitted or refrain from bidding in connection with such contract, or has in any manner, directly or indirectly, sought agreement or collusion or communication or conference with any other bidder, firm or person to fix the price or prices in the attached bid or of any other bidder, or to fix any overhead, profit, or cost element of the bid price or the bid price of any bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage against the _____________________________ (Owner), or any other person interested in the contract; and
5. The price or prices quoted in the attached bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant.
(Signature)
(Title)
Subscribed and sworn to before me, this ______ day of ___________________, 20____.
Notary Public Signature
My Commission Expires: __________________
CERTIFICATE AS TO CORPORATE PRINCIPAL
I, __________________________________________________________, certify that I am the ________________________________________________________________
Secretary of the Corporation named as Principal in the within bond; that
__________________________________ of said corporation; that I know his signature, and his signature thereto is genuine; and that said bond was duly signed, sealed, and attested to for and on behalf of said corporation by authority of this governing body.
Signature
(Corporate Seal) Title
COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM
CONTRACTOR’S CERTIFICATION
CONCERNING LABOR STANDARDS AND PREVAILING WAGE REQUIREMENTS
To (Department, Agency, or Bureau) Date
C/O Project Number
Project Name
1. The undersigned, having executed a contract with ______________________________________ for the construction of the above identified project acknowledges that:
a. The Labor Standards Provisions of the Contract For Construction are included in the aforesaid
b. Correction of any infractions of the aforesaid conditions, including infractions by any of his subcontractors and any lower tier subcontractors, is his responsibility;
2. He Certifies that:
a. Neither he nor any firm, corporation, partnership, or association in which he has a substantial interest is designated as an ineligible contractor by the Comptroller General of the United States pursuant to section 5.6 (b) of the regulations of the Secretary of Labor, Part 5 (29CFR, Part 5), or pursuant to section 3 (a) of the Davis-Bacon Act, as amended (40 USC 276e-2 (a)).
b. No part of any aforementioned contract has been or will be subcontracted to any subcontractor if such subcontractor or any firm, corporation, partnership, or association in which any subcontractor has a substantial interest is designated as an ineligible contractor pursuant to the aforesaid regulatory or statutory provisions.
3. He agrees to obtain and forward to the contractor, for transmittal to the recipient, within ten days after the execution of any lower subcontract, a Subcontractor’s Certification Concerning Labor Standards and Prevailing Wage Requirements, executed by the lower tier subcontractor, in duplicate.
4. He certifies that:
a. The legal name and the business address of the undersigned are:
b. The Undersigned is:
1. ______ A Single Proprietorship
2. ______ A Partnership
3. ______ A Corporation Organized in the State of ________________________________________
4. ______ Other Organization (describe) ________________________________________________
c. The name, title, and address of the owner, partners, or officers of the undersigned are:
NAME TITLE ADDRESS
d. The names and addresses of all other persons, both natural and corporate, having a substantial interest in the undersigned, and the nature of the interests (if none, so state):
e. the names, addresses, and trade classifications of all other building construction contractors in which the undersigned has a substantial interest are (if none, so state):
Social Security No. Or Federal Employer I.D. No.__________________ ___________________________________ (Contractor)
Date:_____________________________________ BY:________________________________
WARNING
U.S. Criminal Code, Section 1010, Title 18, U.S.C., provides in part: “Whoever…makes, passes, utters, publishes any statement, knowing the same to be false…shall be fined not more than $5,000.00 or imprisoned not more than two years, or both”
COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM
SUBCONTRACTOR’S CERTIFICATION
CONCERNING LABOR STANDARDS AND PREVAILING WAGE REQUIREMENTS
To (Department, Agency, or Bureau) Date
C/O Project Number
Project Name
1. The undersigned, having executed a contract with ______________________________________ for _____________________________________________________________________________________ in the amount of $___________________in the construction of the above identified project
a. The Labor Standards Provisions of the Contract For Construction are included in the aforesaid
b. Neither he nor any firm, corporation, partnership, or association in which he has a substantial interest is designated as an ineligible contractor by the Comptroller General of the United States pursuant to section 5.6 (b) of the regulations of the Secretary of Labor, Part 5 (29CFR, Part 5), or pursuant to section 3 (a) of the Davis-Bacon Act, as amended (40 USC 276e-2 (a)).
c. No part of any aforementioned contract has been or will be subcontracted to any subcontractor if such subcontractor or any firm, corporation, partnership, or association in which any subcontractor has a substantial interest is designated as an ineligible contractor pursuant to the aforesaid regulatory or statutory provisions.
2. He agrees to obtain and forward to the contractor, for transmittal to the recipient, within ten days after the execution of any lower subcontract, a Subcontractor’s Certification Concerning Labor Standards and Prevailing Wage Requirements, executed by the lower tier subcontractor, in duplicate.
The workmen will report for duty on or about: __________________
3. He certifies that:
a. The legal name and the business address of the undersigned are:
b. The Undersigned is:
5. ______ A Single Proprietorship
6. ______ A Partnership
7. ______ A Corporation Organized in the State of ________________________________________
8. ______ Other Organization (describe) ________________________________________________
c. The name, title, and address of the owner, partners, or officers of the undersigned are:
d. The names and addresses of all other persons, both natural and corporate, having a substantial interest in the undersigned, and the nature of the interests (if none, so state):
e. the names, addresses, and trade classifications of all other building construction contractors in which the undersigned has a substantial interest are (if none, so state):
Social Security No. Or Federal Employer I.D. No.__________________ __________________________________ (Contractor)
Date:_____________________________________ BY:_______________________________
WARNING
U.S. Criminal Code, Section 1010, Title 18, U.S.C., provides in part: “Whoever…makes, passes, utters, publishes any statement, knowing the same to be false…shall be fined not more than $5,000.00 or imprisoned not more than two years, or both”
COMMISSION ON HUMAN RIGHTS AND OPPORTUNITIES
CONTRACT COMPLIANCE REGULATIONS
NOTIFICATION TO BIDDERS
(Revised 09/17/07)
The contract to be awarded is subject to contract compliance requirements mandated by Sections 4a-60 and 4a-60a of the Connecticut General Statutes; and, when the awarding agency is the State, Sections 46a-71(d) and 46a-81i(d) of the Connecticut General Statutes. There are Contract Compliance Regulations codified at Section 46a-68j-21 through 43 of the Regulations of Connecticut State Agencies, which establish a procedure for awarding all contracts covered by Sections 4a-60 and 46a-71(d) of the Connecticut General Statutes.
According to Section 46a-68j-30(9) of the Contract Compliance Regulations, every agency awarding a contract subject to the contract compliance requirements has an obligation to “aggressively solicit the participation of legitimate minority business enterprises as bidders, contractors, subcontractors and suppliers of materials”. “Minority business enterprise” is defined in Section 4a-60 of the Connecticut General Statutes as a business wherein fifty-one percent or more of the capital stock, or assets belong to a person or persons: “(1) Who are active in daily affairs of the enterprise; (2) who have the power to direct the management and policies of the enterprise; and (3) who are members of a minority, as such term is defined in subsection (1) of Section 32-9n.” “Minority” groups are defined in Section 32-9n of the Connecticut General Statutes as “(1) Black Americans…(2) Hispanic Americans…(3) persons who have origins in the Iberian Peninsula…(4) Women…(5) Asian Pacific Americans and Pacific Islanders; (6) American Indians…” An individual with disability is also a minority business enterprise as provided by Section 4a-60g of the Connecticut General Statutes. The above definitions apply to the contract compliance requirements by virtue of Section 46a-68j-21(11) of the Contract Compliance Regulations.
The awarding agency will consider the following factors when reviewing the bidder’s qualifications under the contract compliance requirements:
(a) the bidder’s success in implementing an affirmative action plan;
(b) the bidder’s success in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .