This document is a Question and Answer (Q&A) report from an Industry Day webinar held by the Federal Emergency Management Agency's (FEMA) Office of Emerging Threats (OET). The webinar covered an upcoming opportunity for OET subject matter expert (SME) and technical staff support services to develop and enhance CBRN and non-CBRN emerging threat program initiatives.

The key details include: The solicitation will be a total small business set-aside on the GSA Multiple Award Schedule (MAS) under NAICS codes 541611 and 541690. The final solicitation is expected to be released next month. Capability statements are due by April 1st and should be submitted to FEMA-Industry-Registration@fema.dhs.gov. The current incumbent is Gryphon Scientific LLC. The Q&A covers topics such as security clearance requirements, staffing, pricing, and the relationship between OET and other FEMA offices. No Statement of Work or other procurement documents were provided in this file.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Industry Day Q and A

Question Report
Report Generated:3/26/24 8:17
TopicWebinar IDActual Start TimeActual Duration (minutes)# Question
Office of Emerging Threats (OET) Industry Day161 858 58963/25/24 11:2219776
Question Details
#QuestionAsker NameAsker EmailAnswerQuestion TimeAnswered TimeAnswer NameAnswer Email
1Please enable chat.Anonymous Attendee3/25/24 13:05
2Will these slides be posted on SAM.gov? as well as Q&A?Anonymous AttendeeThe slides will be posted. The Q&A may be posted at the discretion of the Contracting Officer.3/25/24 13:073/25/24 13:16Jesse HatcherJesse.Hatcher@fema.dhs.gov
3Chat is disabledAnonymous AttendeeYes. Kindly use the Q&A box for questions to panelists.3/25/24 13:073/25/24 13:11Jesse HatcherJesse.Hatcher@fema.dhs.gov
4the slides are behind the speakerAnonymous Attendee3/25/24 13:09
5Slides are behind the briefer. Please advance to the Branch being discussed.Anonymous Attendee3/25/24 13:11
6Are the slides for Kerrisha Francis one behind her presentation?Anonymous Attendee3/25/24 13:12
7The RFI requests 2 page capes sheets be submitted by April 1st. Are you seeking only sheets from small business who are seeking to prime, or from all interested parties, large and small? Thank you.Neil CohenNeil.cohen@hexagonusfederal.comThis solicitation will be to small businesses only3/25/24 13:233/25/24 13:24Tara ShirleyTara.Shirley@fema.dhs.gov
8Are the Support SME needs for specified functions in the different branches or varrying requirements based on current needs?Anonymous AttendeeFor the Emerging Threats Identification and Risk Analysis Branch, the SOW specifies support to perform risk analysis and are not necessarily requiring specific specialty in CBRN or non-CBRN threats. For the Risk Management Branch, because of the specific products tailored to a CBRN or non-CBRN threat, appropriate specialized staff personnel may be needed during the development or update timeframe.3/25/24 13:253/25/24 13:34Joselito Ignaciojoselito.ignacio@fema.dhs.gov
9Will this procurement be on GSA MAS or sam.gov?Joe Cabelljcabell@shieldanalysis.comGSA MAS3/25/24 13:273/25/24 13:29Tara ShirleyTara.Shirley@fema.dhs.gov
10What is the estimated timeframe for a final solicitation for this opportunity?

Is it expected to be a total small business set aside?

What NAICS code is associated with this effort?Anonymous AttendeeFinal solicitation will go out next month. This will be a total small business set aside and the anticipated GSA MASs are 541611 and 541690 but this is subject to change3/25/24 13:273/25/24 13:30Tara ShirleyTara.Shirley@fema.dhs.gov
11Overall risk scores have three variables and appear to range from 1 to something greater than 45. Does each variable range from 1 to 5?Mark Thallermthaller@Securifense.comWe recognize that there are overlaps in the Risk Scores (e.g., 30 and above) to drive towards one of the three risk analysis branch products. This is where OET leadership consultation is needed, and also, there may be threats/hazards requiring two or all three of the products to be developed. There is definitely a semi-qualitative approach in this process.3/25/24 13:283/25/24 13:31Joselito Ignaciojoselito.ignacio@fema.dhs.gov
12Can a small business submit a stand alone proposal for just one specific element of the SOW? For example, a new emerging threat assessment/analysis project?Anonymous AttendeeNo. The awardee for this requirement must be able to satisfy all requirements however a prime may engage a subcontractor3/25/24 13:303/25/24 13:32Tara ShirleyTara.Shirley@fema.dhs.gov
13We'd appreciate clarification of the following language within the SOW: "All personnel require access to information up to the Top Secret/SCI levels." As it reads curently, with the language "specified at the task order level" that follows, it sounds as though all contract support members should have a TS/SCI.Lauren Plainelplaine@gryphonscientific.comThe SOW states something differently. I defer to the CO to ensure that the updated SOW is available to you all.3/25/24 13:353/25/24 13:44Joselito Ignaciojoselito.ignacio@fema.dhs.gov
13We'd appreciate clarification of the following language within the SOW: "All personnel require access to information up to the Top Secret/SCI levels." As it reads curently, with the language "specified at the task order level" that follows, it sounds as though all contract support members should have a TS/SCI.Lauren Plainelplaine@gryphonscientific.comThe current SOW does state that so I will discuss with the program to see how this paragraph should be updated3/25/24 13:353/25/24 13:47Tara ShirleyTara.Shirley@fema.dhs.gov
14Have you ever considered utilizing the Hubzone program to include small, tactically driven organizations that can support your efforts? This program can effectively drive small and innovative businesses that contribute significantly to your success.Anonymous AttendeeThank you for the suggestion.3/25/24 13:383/25/24 13:44Joselito Ignaciojoselito.ignacio@fema.dhs.gov
15Would you please publish this Q&A as well?Adam Montellaadammontella@summitet.comQ&A may be published, but this will be at the discretion of the Contracting Officer.3/25/24 13:483/25/24 13:59Jesse HatcherJesse.Hatcher@fema.dhs.gov
16What procurement are you referring to? Staffing specifically?Anonymous Attendee3/25/24 13:50
17The CRSS Program was just briefed but isn't listed in the posted SOW. Will it be in an updated SOW?Lauren Plainelplaine@gryphonscientific.com3/25/24 13:50
18How many FTEs are on the current Gryphon contract?Anonymous AttendeeWe will confer and respond at a later date.3/25/24 13:503/25/24 13:57Jesse HatcherJesse.Hatcher@fema.dhs.gov
19How is the current contractor performing? Meets, does not meets, exceedsJerry Partneyjerry.partney@emkeysolutions.comDetails will be provided in CPARS as per FAR.3/25/24 13:513/25/24 13:58Jesse HatcherJesse.Hatcher@fema.dhs.gov
20Expected RFP date?Charles Stevens-MarroneChuckstevens-marrone@summitet.com3/25/24 13:51
21Do you have an estimated final RFP releaseChuck Hchuck@kinetic.win3/25/24 13:51
22For clarity, what will the phase 1 down selection be based on?Anonymous Attendee3/25/24 13:51
23Will there be any health related response requirements?Geane Chatmangchatman@Axisconsultantgroup.com3/25/24 13:52
24How and where do we submit our capability statements?Eric Williamsewilliams@obscidion.comCapability Statements can be sent to FEMA-Industry-Registration@fema.dhs.gov, subject line, "FEMA OET Industry Day, Capability Statement"3/25/24 13:523/25/24 13:55Jesse HatcherJesse.Hatcher@fema.dhs.gov
25`Has there been any changes in the ESF structure within the past ten years?Joseph E Fordjoseph.ford@jef-at.comSee ESF's here: https://www.fema.gov/emergency-managers/national-preparedness/frameworks/response#esf3/25/24 13:523/25/24 14:01Jesse HatcherJesse.Hatcher@fema.dhs.gov
26Can you say the name of where to send questions again?Anonymous AttendeeQuestions can be sent to FEMA-Industry-Registration, subject line, "FEMA OET Industry Day"3/25/24 13:533/25/24 13:56Jesse HatcherJesse.Hatcher@fema.dhs.gov
27It was pretty clear… but some topics were merged together on a single slideAnonymous Attendee3/25/24 13:53
28?Anonymous Attendee3/25/24 13:53
29Sorry, I meant to provide company information with my question. RELI Group Inc. Will Smith. Thank you for your response.Will Smithwill.smith@religroupinc.com3/25/24 13:54
30Why has FEMA decided to use GSA MAS vs OASIS SB Pool 1?Anonymous AttendeeAs per CO verbal response, Market Research showed that a GSA BPA offered greater flexibility.3/25/24 13:543/25/24 14:03Jesse HatcherJesse.Hatcher@fema.dhs.gov
31Is this currently listed under 541611 on GSA ebuy?Nakia Youngnyoung@software-tec.com3/25/24 13:54
32Is it just for acquiring personnel to support the office?Anonymous Attendee3/25/24 13:54
33There is a big difference in capabilities that we "can" do, versus what we "have" done, which falls under the KSA's normally used by DHS-FEMA. Will our "have done" capabilities be considered over what is stated as "can do"?Joseph E Fordjoseph.ford@jef-at.com3/25/24 13:55
34Are there any Id’d Key Postions?Ryan Schelskeryan.schelske@aag-llc.com3/25/24 13:55
35Have the CMCU and DEST program efforts been moved outside of OET, or have they been incorporated into existing elements of OET?Michael Podguskimichael.podguski@onevaliant.com3/25/24 13:55
36There was a recent solicitation related to CMCU and DEST support. How is that work related to this solicitation and how does FEMA intend to manage the relationships between that work and the OET work outlined today?Anonymous Attendee3/25/24 13:56
37What is the solicitation number?Anonymous Attendee3/25/24 13:56
38CBRN is such an entrenched set of tools, products, and risk responses. Hence, a case could be made that CBRN could/should be excluded from all of the “new” emerging threats that may be identified. Has this been considered and will this contract accommodate this bifurcation?Anonymous Attendee3/25/24 13:56
39Is the Office of Emerging Threats most interested in continuing support to the current CBRN threats or the “New & Emerging” threats ? For example, would the support effort be 80/20 for CBRN / New & Emerging ?Anonymous AttendeeTo summarize: Program will seek to sustain current capabilities, however risk analysis will be new.3/25/24 13:573/25/24 14:14Jesse HatcherJesse.Hatcher@fema.dhs.gov
40Unless the Grypon Contract question is answered, then this entire acquisition is targetted towards Grpyon… and small businesses would be wasting their time bidding.Anonymous Attendee3/25/24 13:57
41Does the execution of this contract involve interagency corodination by FEMA and is FEMA and isChandrashekar Tamirisachandrashekar.tamirisa@digitrantech.com3/25/24 14:01
42expecting contractor support for it?Chandrashekar Tamirisachandrashekar.tamirisa@digitrantech.com3/25/24 14:01
43Thank you.Nakia Youngnyoung@software-tec.com3/25/24 14:03
44Can a Small Business without MAS partner with a large business with MAS to bid on this?Mikel Anwarmikela@consultingwhiz.comThe prime has to be a small business3/25/24 14:043/25/24 14:05Tara ShirleyTara.Shirley@fema.dhs.gov
45Is the RFI still available on eBuy?Eric Williamsewilliams@obscidion.comNo. But we are accepting capability statements through April 1st3/25/24 14:043/25/24 14:06Tara ShirleyTara.Shirley@fema.dhs.gov
46Is there any requirement to provide staff in the FEMA regions ?David Smithdsmith@jgmsinc.com3/25/24 14:04
47How long does FEMA generally need the support services for personnel through this BPA?Christian Wrightcpwright@arslimited.comContract is for Base plus four option years.3/25/24 14:053/25/24 14:18Jesse HatcherJesse.Hatcher@fema.dhs.gov
48Not even the PM?Adam Montellaadammontella@summitet.comno Key Personnel at this time3/25/24 14:063/25/24 14:07Tara ShirleyTara.Shirley@fema.dhs.gov
49Will there be any pricing sheets supplied byBrian EconomyBrian@pace-contracting.comyes3/25/24 14:063/25/24 14:07Tara ShirleyTara.Shirley@fema.dhs.gov
50Can you send out the SOW since it is no longer available on eBuy?Eric Williamsewilliams@obscidion.com3/25/24 14:07
51Definitely! With SB (without MAS) as prime, can we bring in a large business having MAS as subcontractor?Mikel Anwarmikela@consultingwhiz.comThe prime will need to be a GSA MAS contract holder. I hope that answers your questions.3/25/24 14:073/25/24 14:08Tara ShirleyTara.Shirley@fema.dhs.gov
52When we submit our Capability Statement, may we submit suppport documentation such as Professional Bio's and agency information, or do we need to wait until asked to provide additional information?Joseph E Fordjoseph.ford@jef-at.com3/25/24 14:09
53What is the relationship between OET / Office of CWMD and FEMA S&T as related to FEMA CONOPS and the objectives of this solicitation?JB Burtonburtonjb@leidos.com3/25/24 14:10
54Can you say whether the existing contract holder is using one or more sub companies to meet requirements?Anonymous Attendee3/25/24 14:10
55Why aren't all these questions appearing in the Q&A box? Currently, there are only 22 questions showing on my screen.Anonymous Attendee3/25/24 14:13
56Will mission sets or programs from the Tech Hazards Division be incorporated into OET's portfolio?Anonymous Attendee3/25/24 14:14
57What is the budget for the contract?Anonymous AttendeeAPFS provides a range.3/25/24 14:143/25/24 14:25Jesse HatcherJesse.Hatcher@fema.dhs.gov
58Will there be any remote support on a regular basis, or all HQ support?Anonymous AttendeeSecurity Clearance employees will need to work onsite. Others may have remote work opportunities.3/25/24 14:173/25/24 14:27Jesse HatcherJesse.Hatcher@fema.dhs.gov
59how many call orders or task orders
currently exist on the current contract?Anonymous AttendeeI don't know the exact answer but I think roughly 4-53/25/24 14:183/25/24 14:23Tara ShirleyTara.Shirley@fema.dhs.gov
60It's on Sam.govNakia Youngnyoung@software-tec.com3/25/24 14:19
61I asked ten minutes ago why aren't the questions you are answering showing up in my Q&A section?Daniel Mackneydaniel.mackney@bluemonttechnology.comIt appears only questions answered in writing appear to the attendees.3/25/24 14:193/25/24 14:28Jesse HatcherJesse.Hatcher@fema.dhs.gov
62Gotcha. A better way to phase the question - when FEMA OET does a BPA call for support on an emerging threat, how long on average will staff provide support to OET for a BPA call?Christian Wrightcpwright@arslimited.com3/25/24 14:20
63Are these Q&As going to be published?Anonymous AttendeeWe plan to publish to SAM.gov.3/25/24 14:203/25/24 14:29Jesse HatcherJesse.Hatcher@fema.dhs.gov
64Can you consider making two awards? Rationale is based upon your office appearing to protect any and all information about the imcumbent.Anonymous AttendeeNo.3/25/24 14:233/25/24 14:29Jesse HatcherJesse.Hatcher@fema.dhs.gov
65Can you share the current ceiling and obligation values for the current IDIQ and task orders?Anonymous Attendee3/25/24 14:25
66Great presentation, gratitude FEMA OET team, and Happy Women's History Month -- thank you!Adekunle Omoyosiadekunle@omoyosi.com3/25/24 14:25
67Can you confirm that the current Incumbent is Gryphon Group Security Solutions or another "Gryphon"?Anonymous AttendeeGryphon Scientific LLC3/25/24 14:263/25/24 14:30Jesse HatcherJesse.Hatcher@fema.dhs.gov
68To review all questions, close the Q&A tab and reopen it, then click on all questions and all will be shown.Joseph E Fordjoseph.ford@jef-at.com3/25/24 14:26
69Will the requirement for access to a SCIF be a FEMA on-site SCIF or will the contractor require a SCIF for its employees to work in?Anonymous AttendeeIntent is to work with FEMA on-site SCIF. Contractors need a facility clearance.3/25/24 14:293/25/24 14:32Jesse HatcherJesse.Hatcher@fema.dhs.gov
70Capability Statement due COB on 1 April?Stacey Myersstacey.myers@spaark-inc.com5PM EST3/25/24 14:293/25/24 14:33Tara ShirleyTara.Shirley@fema.dhs.gov
71Thanks FEMA Team, definitely one of the best Industry day briefing for me.Charles Walkercwalker@randkes.com3/25/24 14:31
72Can you identify how many SCI billets will be issued under this contract?Anonymous Attendee3/25/24 14:32
73This webinar has been real helpful in providing great answers through other participent's questions. We appreciate the opportunity to participate....no response required.Joseph E Fordjoseph.ford@jef-at.com3/25/24 14:34
74Understand the requirement for a Facility Clearance, thank you. Will the FEMA SSO handle contractor SCI Indoc and mangement?Anonymous Attendee3/25/24 14:35
75Thank youNeil CohenNeil.cohen@hexagonusfederal.com3/25/24 14:38
76ThanksAnonymous Attendee3/25/24 14:38