This is a Statement of Work (SOW) for an Open-End Roofing contract covering roof repair and replacement services at various Army installations on the island of Oahu, Hawaii. The contract scope includes reroofing and repairs for miscellaneous buildings at locations such as Fort Shafter, Aliamanu Military Reservation, Fort DeRussy, Schofield Barracks, Wheeler Army Airfield, and Helemano Military Reservation, excluding Tripler Medical Facilities. Specific work involves removing existing roofing and installing new fiberglass composition shingles, sheet-metal roofing, gutters, downspouts, flashing, and replacing deteriorated or termite-damaged roof lumber and sheathing.
The contract is a firm fixed-price requirements type construction contract that will require the contractor to provide all labor, materials, equipment, management, supervision, tools, and transportation. Work will be performed during standard hours from 7:30am to 4:00pm, Monday through Friday, excluding federal holidays. Measurement and payment for materials will be based on actual quantities replaced, with contract modifications required for variances of 10% or more. The contract will be administered by the Department of the Army Materiel Command Army Contracting Command, with the solicitation number W912CN25R0015.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PART 1 GENERAL
1.1 GENERAL
Contractor shall furnish all labor, equipment, materials, and other services required to perform Reroofing, Roof Repairs, guarantee workmanship for all work described below and provide a warranty in strict accordance with these technical provisions. Equipment including telescoping boom lifts, articulating boom lifts, stairway scaffolding etc., shall be considered incidental to roofing. Costs for these items shall be included in bid items for shingles, roofing panels, BUR, flashing, gutters, lumber, etc. Tiedowns shall be installed in accordance with EM 385-1-1 and remain in place after roofing is complete. The scope of work covered by this Contract does not cover Reroofing and Roof Repair work which might arise as part of a Contract to repair or renovate a Building or group of Buildings. The work covered by this Contract does not include projects awarded by The U.S. Army Engineering District, Honolulu, excluding the Medical Facilities under Tripler (TAMC), to be designated by the Government during the contract period.
1.2 LOCATION OF WORK
The sites of work will be at Miscellaneous Buildings at Various Army Installations, on the Island of Oahu, excluding the Medical Facilities under Tripler (TAMC), to be designated by the Government during the contract period.
1.3 DESCRIPTION OF WORK:
Description of work are as follows: Repair Roofs of Miscellaneous Buildings which includes removal of existing and installation of new Fiberglass composition Shingles, Preformed Sheet-metal Roofing, Sheet-metal Gutters, Downspouts, Flashing, and replacement of deteriorated and Termite damaged Roof Lumber & Sheathing as required. Including incidental Painting of all bare exposed repaired wood surfaces, and all incidental items necessary to complete the work as required.
1.4 ITEMS OF WORK
Reroofing and Roof Repairs of Miscellaneous Buildings at Fort Shafter, Aliamanu Military Reservation, Fort DeRussy, Schofield Barracks, East Range, Leilehua Golf Course, Wheeler Army Airfield, Helemano Military Reservation and Tripler, (excluding the Medical Facilities, (TAMC).
1.5 ESTIMATED QUANTITIES OF WORK:
The quantities for the items of work are estimated only.
1.6 METHOD OF MEASUREMENT FOR LUMBER AND STEEL REPLACEMENT:
Lumber and Plywood replaced shall be tabulated in the actual quantity of board feet of lumber and square feet of plywood replaced. Wastage due to sawing, other field operations, and correction of deficiencies as a result of the Contractor's negligence or fault shall not be included in the allowances. The Contractor shall maintain a record of quantities of lumber and plywood replaced and shall submit it to the Contracting Officer for verification. The contract shall be modified for variances of 10% or greater. Purlins and steel members replaced shall be tabulated in the actual quantity replaced. Wastage, other field operations, and correction of deficiencies as a result of the Contractor's negligence or fault shall not be included in the allowances. The Contractor shall maintain a record of quantities of steel replaced and shall submit it to the Contracting Officer for verification. The contract shall be modified for variances of 10% or greater.
1.7 METHOD OF MEASUREMENT FOR SHINGLE, METAL, TILE AND BUILT UP ROOFING:
Roofing shall be tabulated in the actual area of roofing replaced (plan view). Factor for roof pitch will be allowed. Excess waste and overlap shall not be included in the allowances.
1.8 OBSTRUCTION AND INTERFERENCES:
In the prosecution of this work, the Contractor shall move, return, or relocate all obstructions or interferences such as signs, furniture, rugs, appliances, office furnishings, draperies, desks, cabinets, office equipment, and (1/2" diameter, bright yellow "Ethernet", 1 EEE 82.3 which is not to be painted wherever encountered), with the exception of valuables and personal effects. Prior to the commencement, the Contractor should report to the occupants and the Technical Representative of the Contracting Officer any noticeable damage to all items.
1.9 DAILY CLEAN-UP:
During the course of the work, the Contractor shall keep the entire premises free from any accumulation of empty cans, rags, or rubbish that constitutes a fire hazard. At the end of each days work, the Contractor shall remove all paint smears and stains. The entire area shall be cleaned and left in a condition acceptable to the Technical Representative of the Contracting Officer.