West_Africa_-_Housing_Development_response_templates_-_EXHIBIT_D.xlsx
XLSX spreadsheet 689 KB Posted
- Solicitation number
- OBO-BTL-BKO-001
- Issued by
-
Department of State US Embassy Bamako
About this file
Templates for Submission
View the file
Other files
| File | Type | Posted |
|---|---|---|
| West_Africa_-_Housing_Development_Opportunities.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule
| Build-To-Lease (BTL) Schedule | |||||||
| Task Name | Start | Days | End | Status | Notes | ||
| Land Acquisition & | |||||||
| Land Use Approval | Phase 1 - Registering Property - Land Without Title Disputes | ||||||
| Business License | |||||||
| Register Property | |||||||
| Phase 2 - Permitting Activities Related to Design | |||||||
| Geotechnical Study/Soil Test Results | |||||||
| Transfer Property Ttile to the Developer | |||||||
| Obtain a Plat/Map - Confirming Boundaries | |||||||
| Rezoning Complete - Finish Milestone | |||||||
| Design | Prepare & Submit Concept & Mock-up Model | ||||||
| OBO Review and Comment on Concept Design | |||||||
| Prepare & Submit 65% Design Stage | |||||||
| USG Review and Comment on 65% | |||||||
| Prepare & Submit 100% Design Stage | |||||||
| USG Review and Comment on 100% | |||||||
| Prepare & Issue Package for Issued for Construction (IFC) | |||||||
| Bidder Site Visit, Questions & Answers, Receive Proposals | |||||||
| Provision of Utilities & Permitting | Obtain Building Permit (Local) | ||||||
| Submit & Obtain Work Plan Approvals (Local) | |||||||
| Obtain Certificate of Conformity | |||||||
| Apply for & Obtain Utility Connections | |||||||
| Procurement | |||||||
| Long Lead Items | Reinforcing Bars | ||||||
| Films | |||||||
| FE/BR Doors and Windows | |||||||
| ENS | |||||||
| Mechanical Systems | |||||||
| Generators | |||||||
| Construction Phase | Mobilization to Site | ||||||
| Site Preparation | |||||||
| Groundbreaking Milestone | |||||||
| Construct Anti-Climb 3m Perimeter Wall | |||||||
| Construct Controlled Site Access | |||||||
| Construct Vehicle Screening Area | |||||||
| Construct Interior Roadways | |||||||
| Construct Parking Spaces | |||||||
| Construct Utility Building & Fuel Systems | |||||||
| Install Site Irregation System & Garden | |||||||
| Construct Staff Housing Units | |||||||
| Construct Recreational Building | |||||||
| Construct DCMR Housing & Garden | |||||||
| Erect Site Lighting Systems | |||||||
| Construction Outdoor Pool | |||||||
| Erect Covered Outdoor Parking Spaces Covers (1 per SHU) | |||||||
| Install Children's Play Areas | |||||||
| Site Restoration/Landscaping | |||||||
| Final Inspections and completion | Partial Site Demobilization | ||||||
| USG Inspection - TSS | |||||||
| USG Inspection - Fire Protection | |||||||
| USG Inspection - MEP | |||||||
| Generate Punchlist | |||||||
| Final Inspection Milestone | |||||||
| Training on Equipment | |||||||
| Substantial Completion | |||||||
| Final Acceptance | |||||||
| Full Demobilization | |||||||
| Project Completion - Finish Milestone |
&"Arial Narrow,Bold"EXHIBIT D - PROJECT SCHEDULE
Balance Sheet
| BALANCE SHEET | Insert Offeror Name |
| Return this sheet in Excel. | |
| Currency used to prepare bid: |
ASSETS
| CURRENT ASSETS | |
| Cash and cash equivalents | $0 |
| Short-term investments | $0 |
| Accounts receivable | $0 |
| Inventories | $0 |
| Deferred income taxes | $0 |
| Prepaid expenses and other current assets | $0 |
| Total current assets | $0 |
| OTHER ASSETS | |
| Property, plant, and equipment at cost | $0 |
| Less accumulated depreciation | $0 |
| Property, plant, and equipment (net) | $0 |
| Long-term cash investments | $0 |
| Equity investments | $0 |
| Deferred income taxes | $0 |
| Other assets | $0 |
| Total other assets | $0 |
TOTAL ASSETS $0
LIABILITIES
| CURRENT LIABILITIES | |
| Loans payable and current portion long-term debt | $0 |
| Accounts payable and accrued expenses | $0 |
| Income taxes payable | $0 |
| Accrued retirement and profit-sharing contributions | $0 |
| Total Current Liabilities | $0 |
| OTHER LIABILITIES | |
| Long-term debt | $0 |
| Accrued retirement costs | $0 |
| Deferred income taxes | $0 |
| Deferred credits and other liabilities | $0 |
| Total Other Liabilities | $0 |
TOTAL LIABILITIES $0
NET WORTH $0
| If Net Worth (US$) is less than $10 million, is a related entity or bonding company prepared to guarantee performance? |
| If Yes, please provide name of the entity, relationship, net worth, etc.: |