This is a Bid Clarification document issued by Rockford Construction, the project manager for the Northview High School Athletic Stadium Addition & Renovation project in Grand Rapids, Michigan. The clarification, dated October 14, 2026, addresses scope changes and questions raised during the bidding process for various bid packages (BP) associated with the athletic stadium construction project. All Bid RFIs (Requests for Information) were required to be submitted by October 15, 2026, to allow time for responses and incorporation into an addendum. Key scope clarifications include: Soccer and Lacrosse goals previously listed for BP 6 will be furnished and installed by the owner rather than the contractor; the Bleacher Contractor (BP 13) is responsible for providing concrete slabs under proposed bleachers; BP 32D is responsible for Turf Drain Tile work; and specific alternates were revised or disregarded for various bid packages related to concrete work, netting replacement, turf installation, and demolition activities.
The clarification establishes multiple alternate pricing options for contractors to submit, including alternates for curb turf anchors at two bullpens (BP 3), netting replacement at the Quad (BP 32C), turf specifications at higher ounce weight (BP 32D), and comprehensive demolition and removal services for existing turf and related materials (BP 31). Specific work scope delineation was clarified for demolition zones, with BP 31 responsible for sawcutting track edges and demolishing surfaces in the South D Zone, while BP 31 also handles storm drainage work in the North D Zone. No pricing amounts were specified in this clarification document, with blank lines provided for contractors to submit their alternate bid prices. The document does not identify any set-asides, funding sources, or incumbent contractors.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
601 First Street NW Grand Rapids, Michigan 49504
(616) 285-6933 www.rockford.com
BID CLARIFICATION NO. 1
TO: All Subcontractors / Suppliers
FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager
DATE: October 14, 2026
RE: NVPS Athletics Addition and Renovation
This Bid Clarification No.1 is being sent to all bidders to address questions raised at bid time.
1. Bid RFIs have been generated; no responses have been received from design team as of this clarification. Responses will be provided in future bid clarifications. AS A REMINDER ALL BID
RFIS ARE DUE BY 10/15/2026 TO ALLOW TIME FOR RESPONSE AND INCORPORATION INTO
ADDENDUM.
2. Scope Clarifications
a. BP 6; Soccer and Lacrosse goals previously listed to be included shall not be included in this bid package. Soccer and Lacrosse Goals will be furnished and installed by owner.
b. BP 13 Bleacher Contractor is responsible for providing concrete slabs under proposed bleachers. Reference sheets LD1.09, L5.01, L5.02, LD5.01, LD5.02, LD5.03, LD5.04, LD 5.05.
c. BP 32D shall be responsible for Specification section 33 4615 Turf Drain Tile under their turf system.
d. Revised Alternate 3 for BP 3 Concrete to provide alternate to furnish and install curb turf anchors at 2 Bullpens. Reference LD1.07
e. BP 32C Alternate 1 provide Alternate for Netting replacement at Quad which is not currently specified to be replaced. $__________
f. BP 32D Alternate 4 Provide Alternate to provide 52 oz turf in lieu of 46 oz turf. This will also be issued in the addendum.
g. BP 31 Provide revised Alternate 5 Demo, Removal and Off Site Disposal of Existing Turf and Shock pad. $___________
h. BP 31 ALTERNATE 6 Include Complete removal of Existing Turf base, drain tiles, flat drains at band field. Dispose of offsite A $_____________ B. This material can be used as access roads $________
i. South D Zone Demo. BP 31 shall sawcut edge of track as required to prevent damage to track and allow for Demo all weather surface in D zone, asphalt surface, aggregate, trench train etc. to allow for new Aggregate Base and drainage system to be installed by
BP 32D.
j. North D Zone Demo. BP 31 shall sawcut edge of track as required to demo items as specified in D zone to allow for new storm drainage aggregate base by BP 31.
k. BP 3 Alternate 3 Disregard Alternate 3 as this is provided by BP 13.
End of Clarification https://protect.checkpoint.com/v2/r01/___http:/www.rockford.com___.YzJ1OnJvY2tmb3JkMTpjOm9mZmljZTM2NV9lbWFpbHNfYXR0YWNobWVudDo5M2QwMjI2MWQxMmRhNzdlYmEzMzkzODgzYTMyNTAwMDo3OmE1OGI6NWEyYTg3YTcwZmI4OWM3M2VlNmEzNjAzOGZhZGM4YzE5NDE3ODNlY2Q3Y2YwOWZiNGUzYWY2Y2NiZmQ2YjRmOTpwOlQ6Rg