Frequently Asked Questions

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Nationally Significant Federal Lands and Tribal Projects Program Questions and Answers

Section 1123 of the Fixing America’s Surface Transportation Act (FAST Act) (Pub. L. 114-94) established the Nationally Significant Federal Lands and Tribal Projects Program (Program) to provide funding for major projects accessing Federal and Tribal lands. The FHWA has issued a notice of funding opportunity (NOFO) with application instructions and deadlines.

Links to NOFO – https://www.federalregister.gov/d/2018-21826 https://apply07.grants.gov/apply/opportunities/instructions/opp693JJ319NF-NSFLTP-cfda20.205-cid693JJ319NF-NSFLTP-instructions.pdf

These Questions and Answers provide supplementary guidance for preparing applications under the Program.

Eligible Applicants

1. Are non-profit organizations or other non-governmental entities eligible to apply?

No. Non-governmental entities, including non-profit organizations, are not eligible to apply for Program funds.

2. Are FLMAs or Tribes required to sponsor an application on behalf of a State, county, or unit of local government if the proposed project does not align with their goals?

No.

Eligible Projects and Facilities

3. What types of activities qualify as “construction” costs?

The FHWA interprets the intent of the term “construction” in section 1123 to mean the supervising, inspecting, actual building, and incurrence of all costs incidental to the construction, reconstruction or rehabilitation of an eligible transportation facility, including bond costs, but excluding costs related to project design.

4. Are operations and maintenance of transit facilities eligible activities under this program?

No. This Program provides funding to “construct, reconstruct, or rehabilitate nationally significant Federal lands and Tribal transportation projects.”

5. Does a transportation facility need to be included in the national Federal lands transportation or Tribal transportation facility inventory to be eligible under this program?

No. Section 1123 of the FAST Act specifically exempted nationally significant Federal lands and Tribal projects from this requirement.

6. Are corridor projects eligible?

Only a single continuous project is eligible. A series of unconnected projects along a corridor likely would not be eligible for Program funds unless the applicant is able to make a convincing case that the project is somehow continuous.

7. Are visitor centers eligible?

No. Facilities such as visitor centers, contact stations, campgrounds, and other visitor amenities are not listed under the definitions for Federal lands transportation facility, a Federal lands access transportation facility, or a tribal transportation facility, and, therefore, are not eligible.

8. Are rail projects eligible?

A rail project is eligible only if it fits the definition of a transit system.

Eligible Project Expenses

9. Are easements and other land acquisition eligible?

Yes. The Program funds construction and acquisition of rights-of-way are part of the definition of construction found under 23 U.S.C. 101(a)(4). Therefore, land acquisition would be an eligible activity.

10. Are activities to meet environmental commitments eligible?

Environmental commitments, including mitigation activities, are often part of project construction or they coincide with the timing of project construction. Activities to meet environmental commitments and accelerate project delivery are eligible. Environmental studies are not eligible unless they relate to fulfilling environmental commitments that the lead Federal agency made during the NEPA process.

11. Are contract management costs eligible?

Contract management costs are eligible for contracts related to construction, reconstruction, and rehabilitation.

Selection Criteria

12. Does a project need to meet all of the selection criteria listed in section 1123(f)?

No. A project could be eligible if it does not meet all nine selection criteria listed in section 1123(f). However, applicants should try to address each of the criteria to the greatest extent possible in their applications. If a project does not meet one or more of the criteria, the application should clearly state this.

The following questions and answers (numbers 13 to 20) are intended to assist applicants in the development of their applications. The descriptions and considerations offered for each selection criteria are provided as examples.

13. How could an applicant demonstrate that a project “furthers the goals of the U.S.

DOT, including state of good repair, economic competitiveness, quality of life, and safety”?

An applicant could address this by:

Documenting that the project would further the goal of state of good repair for transportation facilities. Documentation may include technical data about existing facilities in poor repair or, where the project is new construction, the extent to which the existing conditions demonstrate a need for new transportation facilities.

Showing existing economic indicators in the project vicinity to demonstrate the extent to which the project would further economic competitiveness. Economic indicators may include economic impact analysis or other data demonstrating existing economic conditions and projected future economic conditions with and without the project.

Demonstrating that the project may improve the quality of life for a local community and/or the traveling public. Measures of quality of life may include, but are not limited to, the extent to which the project would improve reliability and reduce delay, the extent to which it would facilitate access to goods and services, education, employment, and recreational opportunities.

Demonstrate how the project can improve safety by providing baseline data of any safety problems that the project will correct.

14. How could an applicant demonstrate that a project “improves the condition of critical transportation facilities, including multimodal facilities”?

Applicants could describe and justify the basis for determining the facilities are critical transportation facilities, including critical multimodal facilities. For example, an applicant can demonstrate facilities are primary visitation routes to public lands and/or recreation resources, that socioeconomic data demonstrate a need to improve access opportunities for underserved populations, or other baseline data that make a strong case for critical transportation facilities. After establishing and defining critical transportation facilities, the applicant should demonstrate the extent to which the project will improve the condition of these facilities.

15. How could an applicant demonstrate that a project meets “the need for construction, reconstruction, or rehabilitation”?

Many factors may demonstrate the need for a project. Some examples include condition assessments that show substantial deterioration or safety problems, socioeconomic data that demonstrate a need to improve access opportunities for underserved populations, or other baseline data that make a strong case that the need for the project is significant.

16. How does an applicant identify and document that transportation facilities are included in or eligible for inclusion in the National Register of Historic Places? Does this criterion apply to all facilities subject to project activities?

The National Historic Preservation Act (54 U.S.C. 300101 et seq.) established the National Register of Historic Places (National Register), and the Act defines a ‘‘historic property’’ as “any prehistoric or historic district, site, building, structure, or object included on, or eligible for inclusion on, the National Register, including artifacts, records, and material remains relating to the district, site, building, structure, or object.”

When a property is not already listed in the National Register, the Federal agency or the Keeper of the National Register may make a determination of a property’s National Register eligibility. An applicant will need to determine if project facilities are National Register eligible historic properties based on the professional judgement of an employee or consultant meeting the Secretary of the Interior’s Professional Qualification Standards in one or more disciplines appropriate to identifying all or part of the project facilities.

An applicant should document that the transportation facility is a historic property, is a contributing element to a historic property, and/or that the transportation facility provides an opportunity for enjoyment of or access to a historic property. Linear historic properties often have sections that contribute to the overall National Register eligibility of the property as well as sections that no longer retain sufficient integrity to contribute to National Register eligibility. Therefore, an applicant can demonstrate that they have met criterion 5 when any part of a project is a historic property or provides enjoyment of or access to a historic property.

17. How could an applicant show a project uses new technologies and innovations that enhance the efficiency of the project?

The applicant could describe what makes the particular technology new. Then the applicant could describe how the technology makes construction of the project either shorter, less costly, or both relative to a more conventional construction method. And finally, an applicant can demonstrate how the technology improves safety, visitor experience, or offers long-term efficiencies in the operations, maintenance, or other aspects of the useful life of the newly constructed, reconstructed, or rehabilitated facility.

18. What information could an applicant provide regarding the extent to which a project is supported by funds, other than funds received under the Program, to construct, maintain, and operate the facility?

Besides the required 10% match, an applicant could demonstrate and describe the availability of other funding sources for construction. If the available funds exceed the requisite 10% match, these applications will be viewed favorably. Additionally, an applicant could demonstrate that non-Program funds are available to maintain and operate a facility built with Program dollars and that the applicant has a reasonable expectation that those funds will be available throughout the useful life of all project facilities.

19. Is a project required to span two or more States to be eligible? If a project does not span two States, what other documentation can an applicant provide to address that criterion?

A project does not have to span more than one State to be eligible under the Program.

However, FHWA will consider the extent to which a project spans two or more States when applying the selection criteria. If a project does not span two or more States, but serves communities or recreational interests in two or more States, an applicant can strengthen its application by demonstrating the benefits to two or more States. Many Federal and Tribal lands span more than one State. Additionally, many State and Tribal lands near State borders serve communities and/or recreational interests in multiple States. If an applicant can demonstrate that a project is part of a larger infrastructure system or is a necessary access point that benefits Federal or Tribal lands in two or more States, FHWA may consider this information to review the extent to which a project meets the intent of selection criterion 8.

20. Is a project required to serve land owned by multiple Federal agencies or Indian tribes to be eligible for funding? How should an applicant demonstrate that a project serves multiple Federal or Tribal lands?

A project does not have to serve multiple Federal or Tribal lands to be eligible under the Program.

To demonstrate that the project serves land owned by multiple Federal agencies and/or Indian tribes, applicants should include a description of the project and how it supports multiple stakeholders. Applicants may also include letters of support from officials at each of the agencies and/or Tribes that would benefit from the project.

Funding Authorization

21. Is there a maximum project cost?

No.

22. Can a single project receive funds from the Program from more than one application cycle?

Yes. A single project may apply for funds during multiple application cycles. Each application must clearly identify the phase and deliverables of the project for which it is seeking annual funding. For example, the resubmission of an identical application (that received funds) will not be considered unless the application clearly identifies how the use of prospective funding will advance additional stages of the project.

23. What other FHWA funding sources may supplement Program funds for a project?

Subject to the eligibility requirements of each FHWA funding program, a project eligible under this Program may also be eligible for supplemental funding under one of the following:

One or more State transportation agency’s allotments under the FHWA Federal-aid program;

Surface Transportation Block Grants https://www.fhwa.dot.gov/fastact/factsheets/stbgfs.pdf;

BUILD discretionary grants http://ops.fhwa.dot.gov/freight/infrastructure/tiger/;

INFRA discretionary grants https://www.transportation.gov/FASTLANEgrants; and Any of FHWA’s other discretionary grants https://www.fhwa.dot.gov/discretionary/.

Non-Federal Share Requirement

24. What are the Federal and non-Federal share requirements?

Program funds may cover up to 90 percent of eligible project costs. Federal funds other than those made available under Title 23 or Title 49 of the U.S. Code may be used to satisfy the non-Federal share requirement.

25. Can Tribal Transportation Program funds be used for the non-Federal match?

No. Because TTP funds are made available under Title 23 of the US Code, they cannot be used as match.

26. Can previously incurred expenses count toward meeting the non-Federal share of a project?

Some related costs incurred before a project application is submitted may count toward meeting the non-Federal share requirement if the project costs were covered by non-23 and non-49 U.S.C. funding sources. The applicant is responsible for providing documentation reflecting the actual expenses incurred that may apply toward match. The FHWA will decide if the documentation and project costs are satisfactory to apply toward the match requirement.

Project Administration

27. How will Stewardship an Oversight of the funds be handled?

For projects awarded to an FLMA, FHWA will provide Stewardship and Oversight (S&O) following the process provided in FLH’s S&O Guidance document, located at http://flh.fhwa.dot.gov/programs/stewardship-oversight/.

For projects awarded to a Tribal government, FHWA will provide S&O following the process provided in format provided in the Tribal Transportation Program Delivery Guide, located at https://flh.fhwa.dot.gov/programs/ttp/guide/.

For projects awarded to a State or local government, FHWA will provide S&O following the process developed under the Federal Lands Access Program, in conjunction with a State’s Programming Decisions Committee.

28. Will a project level agreement be executed and, if so, what will be its scope?

After project selection, FLH will work to execute an agreement between the pertinent agencies to describe how a specific project will be delivered.

Agreements for projects that will be delivered by an FLMA or a Tribal government should generally include:

Scope of the project;

Schedule for delivery;

Budget, including funding sources other than USDOT sources;

Roles and responsibilities of all agreement signatories;

other project issues worth noting, such as the performance goal(s) supported by the project;

match requirements and strategy for administering and tracking;

reporting requirements, such as:

o Progress Reports to the FLH headquarters office on the status of the project, as well as a closeout report documenting completion of all project elements; and o Financial Reports, such as an SF 133;

maintenance commitment; and other recommended information included in the Office of Federal Lands Highway’s

Stewardship and Oversight (S&O) Guidance and Instructions, if applicable.

Agreements for projects that a State or local government will carry out under the sponsorship of an FLMA or tribe should contain all of the information described above, plus the following:

Maintenance commitment of the State or Local Government carrying out the project;

budget, including funding sources other than FHWA program funding;

process for coordinating with pertinent FLMAs and/or Tribal governments, including the sponsor; and any other necessary information, including items required under 2 CFR part 200.

File details come from the government source that posted it.