Northwest Campus Partial Roof Replacement Project Specifications
This is a comprehensive project specification document prepared by Wolf Trail Engineering PLLC for Forsyth Technical Community College, a public educational institution in North Carolina. The project involves the partial replacement of approximately 2,800 square feet of PVC roofing membrane at the Northwest Campus located at 3111 Big Oaks Drive, King, NC 27021. The work includes demolition of existing fully adhered PVC membrane with two layers of 2-inch isocyanurate insulation on a metal deck, installation of new 1.5-inch mechanically attached isocyanurate insulation with crickets and saddles, application of 0.25-inch silicone-impregnated fiberglass reinforced gypsum cover board, and full adherence of new PVC membrane with all flashings and accessories. A pre-bid conference is scheduled for 1:00 PM on Thursday, April 16, 2026, at the Northwest Campus, with sealed bids due by 2:00 PM on Monday, April 27, 2026. The contract will be awarded to a single prime contractor, and the project timeline includes a preliminary schedule with specific milestones for substantial completion and final completion.
Bid security of 5 percent of the bid amount is required with submission, and successful bidders must provide performance and payment bonds each equal to 100 percent of the contract sum. The specifications require contractors to have been in business for a minimum of five years, be approved by manufacturers for premium roof systems with twenty-year non-delegable (NDL) warranties, maintain a drug and alcohol-free workplace program, and provide qualified project management, foreman, and roofing mechanic personnel with specific experience requirements. A $5,000 contingency allowance is included in the base bid, with unit prices required for fire-treated wood blocking and installation. The project requires compliance with the 2018 North Carolina Building Code and all applicable ASTM, NRCA, and SMACNA standards. The contractor must provide a two-year warranty on all work and secure a manufacturer's twenty-year NDL warranty at no additional cost to the owner. Construction must occur during normal business hours (Monday through Saturday, 8:00 AM to 5:00 PM) with the building remaining occupied, and the contractor is responsible for all debris removal, site protection, and restoration of damaged areas to pre-construction condition.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FORSYTH TECHNICAL COMMUNITY COLLEGE NORTHWEST ROOF REPLACEMENT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NORTHWEST CAMPUS PARTIAL
ROOF REPLACEMENT
PROJECT SPECIFICATIONS
February 2026
Prepared by:
Wolf Trail Engineering PLLC 1001 Lancaster Avenue, Monroe, NC 28112
NC P-1817 | SC 5872
Forsyth Technical Community College Section 000110 -Table of Contents Northwest Campus Partial Roof Replacement Page 1 of 2
SECTION 00 01 10
TABLE OF CONTENTS
DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
Introductory Information 00 01 01 Cover 00 01 10 Table of Contents 00 01 15 List of Drawings
Procurement Requirements 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 26 00 Procurement Substitution Procedures 00 31 13 Preliminary Schedule
Procurement Forms and Supplements 00 41 13 Bid Form 00 43 13 Bid Bond 00 43 38 MBE Program Guild lines 00 43 39 MBE Program 00 43 40 Sample Contract
Project Forms 00 60 00 Project Forms 00 61 13.13 Performance Bond 00 61 13.16 Payment Bond 00 62 33 Roofing Manufacturer’s Acknowledgement 00 62 76.13 Sales Tax Statement 00 63 63 AIA G701 Change Order Form (Sample) 00 65 14 Asbestos Free Statement 00 65 36 Contractor’s Warranty Form 00 65 37 Roofing Warranty Form
Conditions of the Contract 00 72 13 AIA General Conditions 00 73 00 Supplementary Conditions
DIVISION 01 GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 00 Work Restrictions 01 21 00 Contingency and Allowance 01 22 00 Unit Prices 01 25 00 Substitution Procedures 01 26 00 Contract Modification Procedures 01 29 00 Payment Procedures 01 31 19 Project Meetings
Forsyth Technical Community College Section 000110 -Table of Contents Northwest Campus Partial Roof Replacement Page 2 of 2
01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 73 29 Cutting and Patching 01 74 13 Progress and Final Cleaning 01 74 19 Construction Waste Management 01 77 00 Closeout Procedures 01 78 36 Warranties
DIVISION 06 ROUGH CARPENTRY
06 10 00 Rough Carpentry
DIVISION 07 THERMAL AND MOISTURE PROTECTION
07 54 19 Polyvinyl-Chloride Roofing 07 62 00 Sheet Metal Flashing and Trim
Forsyth Technical Community College Section 000115 -List of Drawings Northwest Campus Partial Roof Replacement Page 1 of 1
SECTION 00 01 15
LIST OF DRAWINGS
PART 1 - GENERAL
The following drawings and details are included as part of the Contract Documents:
Drawing Description Date
C01 Cover/Vicinity Map 02/2026
AP-1
Swisher Appendix B
02/2026 DP01 Detail Plan
R-1 Roof Details 02/2026 R-2 Roof Details 02/2026
UP-1
Wind Uplift
END OF SECTION 00 01 15
Forsyth Technical Community College Section 001113 -Advertisement for Bids
SECTION 00 11 13
ADVERTISEMENT FOR BIDS
Sealed bids for Forsyth Technical Community College Technology & Northwest Campus Partial Roof Replacement Project, will be received by the Owner at 2100 Silas Creek Parkway Winston Salem, NC 27103 by 2:00 PM on Monday April 27th, 2026, at which time bids will be publicly opened and
The Owner is: Address: Forsyth Technical Community College 2100 Silas Creek Parkway
Winston Salem, NC 27103
Project Manager: Heather Brazell Email: hbrazell@forsythtech.edu Phone: 336-971-1242
The Engineer is: Wolf Trail Engineering, LLC Attention: Lynne Hall
Phone # 704-282-0826 Email: Lynne@wolftrailengineering.com
Prime Bidders & major subcontractors may receive a complete PDF set of plans and specifications upon request from the office of the Engineer.
Potential bidders are advised to familiarize themselves with the Bidder Qualifications contained in the specifications prior to submitting bid documents.
All questions should be directed to the Engineer at the phone number indicated above.
A Pre-Bid conference is scheduled for 1:00 PM on Thursday April 16th,2026, at the Northwest Campus, 3111 Big Oaks Dr., King, NC 27021.
This is not a mandatory pre-bid. Attendance is Recommended.
Bid security in the amount of 5% of the bid amount shall be submitted with each bid.
The Owner reserves the right to reject any and all bids, to waive informalities, and to award contract to other than the low bidder should it be deemed in their best interest.
END OF SECTION 00 11 13
hbrazell Highlight hbrazell Highlight hbrazell Highlight
Forsyth Technical Community College Section 002113 -Instructions to Bidders Northwest Campus Partial Roof Replacement Page 1 of 5
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
1.1 SECURING DOCUMENTS
A. Obtain procurement documents for bidding purposes under conditions as set forth in the Advertisement for Bid.
1.2 BID FORM
A. Submit Bids on the forms provided, properly executed and with all items filled out. Modification of the Bid Form, attachment of conditions or limitation of provisions may be cause for rejection of the Bid. Alterations, erasure or interlineations must be noted with explanation on the Bid Form over the signature of the Bidder.
1.3 FAMILIARITY WITH WORK AND CONDITIONS:
A. Before preparing Bids, Bidders are urged to visit the site to inform and familiarize themselves with all conditions involved and under which the project is to be constructed or apparatus erected or installed. The Owner will not be responsible to the Contractor for payments other than as set out in the Construction Contract should construction conditions be different from those assumed or contemplated by the Contractor. The Contractor is required to satisfy himself, before bidding, as to the correctness of the site as indicated by the Contract Documents.
1.4 SUBMISSION OF BIDS
A. Deliver Bid to the location indicated in the Advertisement for Bid before time set for receipt of bids. Submit Bid in an opaque, sealed envelope and marked in the lower left-hand corner with the following information:
1. Bidder's Name
2. Bidder's Address
3. Bidder's Phone
4. Contractor's License No.
5. Title of Project
6. Date and Time of the Bid Opening
B. If not delivered in person, envelope shall be enclosed in a second envelope for posting to the location indicated for receipt of bids. Address outside envelope as follows:
Heather Brazell Project Manager, Facilities Forsyth Technical Community College
Northwest Campus Partial Roof Replacement Page 2 of 5
2100 Silas Creek Parkway Winston Salem, NC 27103 Label Packages “URGENT– TIME SENSITIVE BID ENCLOSED”
C. It is the sole responsibility of the Bidder to submit Bid prior to time fixed for receipt.
D. Electronic submission of Bids or Bid modifications will not be accepted. Bids received after the time fixed for receipt will be considered late and will be returned to the Bidder unopened.
1.5 BID SECURITY
A. A Bid Security in the amount of 5 percent of the Bid Sum shall be furnished with the submission of the Bid for each project. Acceptable Bid Securities include a bid bond, certified check, or other type of security, as stipulated by the North Carolina General Statutes. Submit Bid Security should be on the Owner’s form, attached in the Project Manual.
1.6 PERFORMANCE AND PAYMENT BONDS
A. Performance Bond and Labor and Material Payment Bonds, each in the amount of 100 percent of the Contract Sum, shall be furnished at the time of Contract execution. Submit Bonds on the Owner’s forms attached in the Project Manual.
1.7 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF WORK
A. Prior to submitting Bid, each Bidder shall carefully examine the proposed Contract Documents and visit the project site. Bidders shall fully inform themselves, prior to Bidding, as to all existing conditions and limitations under which the Work is to be performed and shall include in the Bid Sum an amount to cover the cost of all items necessary to perform the Work as set forth in the proposed Contract Documents. No allowance will be made due to lack of such examination or knowledge. The submission of a Bid shall be construed as conclusive evidence that the Bidder has made such an examination.
1.8 SUBSTITUTIONS
A. Each Bidder represents that their Bid is based upon the materials and equipment described in the proposed Contract Documents. Substitutions will be considered during the Bidding process in accordance with Document 00 26 00 - Procurement Substitution Procedures. Substitutions after the execution of the Agreement will only be considered in strict accordance with Section 01 25 00 - Substitution Procedures.
1.9 MODIFICATION AND WITHDRAWAL OF BIDS
A. Bids may be withdrawn upon request from the Bidder prior to opening
Northwest Campus Partial Roof Replacement Page 3 of 5 time. Withdrawn Bids may be resubmitted up to opening time. Negligence or error on the part of the Bidder in preparing his Bid confers no right for withdrawal of the Bid after it has been opened. No Bid may be withdrawn for 90 calendar days after opening except as provided by North Carolina G.S. 143- 129.1.
1.10 AWARD OR REJECTION OF BIDS
A. Award of Contract, if awarded, will be based on, but not limited to, the following criteria:
1. Award the contract to the lowest responsible bidder or bidders, taking into consideration quality, performance and the time specified in the proposals for the performance of the contract.
2. Submission of the Owner’s required qualification documents before or with the Bid.
3. Acceptance of the contractor’s qualifications based on the response to the contractor qualification documents demonstrating his past performance and ability to complete similar work.
4. Conformance with contract documents
5. Acceptable date of delivery
6. Acceptable Form of Bid Security
7. Other reasonable factors deemed fit, by the Owner.
B. A single Contract will be awarded.
C. To be considered, a minimum of three Bidders must submit for the Contract.
D. All bids are subject to the Owner’s right to reject any or all bids and to waive any informality in the bids or in the bidding. Failure to provide qualifications, complete all information required on the bid form, or provide adequate bid security may result in rejection of bid.
1.11 EXECUTION OF AGREEMENT
A. The successful Bidder, to whom the Contract is awarded by the Owner, shall, within 10 days after Notice of Award from the Owner, sign and deliver to the Owner all required copies of the Agreement.
B. Prior to or in conjunction with delivery of the executed Agreement, the Contractor shall deliver to the Owner documents described in the Project Manual and the policies or certificates of insurance as required by the Contract Documents. The Owner shall approve all bonds and policies or certificates of insurance before the Contractor may proceed with the Work.
C. Failure or refusal to furnish Bonds or insurance policies or certificates in a form satisfactory to the Owner shall subject the Bidder to forfeiture of Bid Security.
1.12 INTERPRETATION OF CONTRACT DOCUMENTS PRIOR TO BIDDING
Northwest Campus Partial Roof Replacement Page 4 of 5
A. If any person contemplating submitting a Bid for the construction of the Work is in doubt as to the true meaning of any part of the proposed Contract Documents or finds discrepancies in or omissions from any part of the Contract Documents, they may submit to the Architect a written request for interpretation or correction thereof, no later than 7 calendar days prior to the receipt of Bids.
B. Communications regarding this Work should be addressed to the Architect indicated in the Advertisement for Bids.
C. Interpretation or correction of the Contract Documents shall be made by written addendum and will be mailed, faxed, or delivered to each Bidder of record. The Owner will not be responsible for any other explanations or interpretation of the Contract Documents.
D. It is the responsibility of each Bidder to verify that they have received all Addenda before submitting a Bid. It is the responsibility of all sub-bidders and material suppliers to be familiar with and to include in their price, all Addenda issued up to the time of Bid opening. Requests for clarification or additional information shall be accepted only from Bidder submitting as the General Contractor, sub-Bidders and suppliers shall coordinate their requests through these Bidders.
1.13 PRE-BID CONFERENCE
A. A pre-bid conference will be held at time and location indicated in the Advertisement for Bids. All prospective bidders are requested to attend. The conference will include a discussion of the proposed site of the work, discussion of the scope and nature of the work, review of the proposed Contract Documents, and discussion of questions submitted by the Bidders.
1.14 CONSTRUCTION TIME AND LIQUIDATED DAMAGES
A. The Conditions of the Contract include stipulations that the Work be completed within the Contract Time expressed in calendar days.
Article 1.5: TIME OF CONSTRUCTION, of the Supplementary Conditions of the includes a stipulation, states that Liquidated Damages accrue per calendar day for each day Work remains incomplete beyond the Contract Completion Date.
Refer to the Document 00 31 13 - Preliminary Schedule included in the Project Manual for proposed start, completion, and intermediate milestones.
1.15 ROOF MANUFACTURER’S ACKNOWLEDGEMENT
A. The roof system manufacturer shall complete the Roof Manufacturer's Acknowledgement (Section 00 62 33) form. The Contractor shall enclose the signed Roof Manufacturer's Acknowledgement form from the manufacturer they intend to use on the project with their bid.
Northwest Campus Partial Roof Replacement Page 5 of 5
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION 00 21 13
Forsyth Technical Community College Section 002600 -Procurement Substitution Northwest Campus Partial Roof Replacement Page 1 of 3
SECTION 00 26 00
PROCUREMENT SUBSTITUTION PROCEDURES
1.1 SUMMARY
A. Administrative and procedural requirements for handling requests for substitutions prior to the Owner’s receipt of bids.
1.2 DEFINITIONS
A. Definitions used in this Article are not intended to change or modify the meaning of other terms used in the Contract Documents.
B. Substitutions: Requests for changes in products, materials, and equipment, of construction required by Contract Documents proposed by the Contractor are considered requests for substitutions. The following are not considered substitutions:
1. Substitutions that are requested by Bidders beyond the 10 days prior to bid opening submittal period
2. Revisions to Contract Documents requested by the Owner or Engineer
3. Specified options of products and construction methods included in
Contract Documents
4. The Contractor’s determination of and compliance with governing regulations and orders issued by governing authorities
1.3 SUBSTITUTION REQUEST
A. Request for substitution from Bidders, submitted Bid as General Contractor will be considered if received by the Engineer a minimum of 10 days prior to receipt of Bids.
1. Submit three (3) copies of each request for substitution for consideration.
2. Identify the product or method to be replaced in each request.
Include reference to related Specification Sections and drawing sheet number.
Northwest Campus Partial Roof Replacement Page 2 of 3
3. Provide complete documentation on both the product specified and the proposed substitution including the following information as appropriate.
a. Comparison of specified and proposed substitute product data, fabrication drawings, and installation procedures.
b. Samples where applicable or requested.
c. A detailed comparison of significant qualities of the proposed substitution with those of the work specified.
d. Coordination information, including a list of changes or modifications required to other parts of the Work and to construction performed by others that will become necessary to accommodate the proposed substitution.
4. Certification by the Bidder or the manufacturer that the proposed substitution is equal-to or better in every respect to that required by the proposed Contract Documents and that it will perform equal-to or superior to product specified in the application indicated. The Contractor waives any right to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.
B. Engineer’s Action: The Engineer may request additional information or documentation necessary for evaluation of the request. The Engineer will notify Bidders of acceptance of the proposed substitution by means of an addendum to the proposed Contract Documents.
C. Engineer’s Substitution Approval during bidding and subsequent addenda does not void the Contractor’s responsibility to submit the required shop drawings and comply with the requirements of the Contract Documents.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. The Engineer will consider Bidder's substitution request when the following conditions are satisfied, as determined by the Engineer; otherwise, requests will be returned without action except to record noncompliance with these requirements.
1. Extensive revisions to Contract Documents are not required.
2. Proposed changes are in keeping with the general intent of Contract
Northwest Campus Partial Roof Replacement Page 3 of 3
Documents.
3. The request is timely, fully documented and properly submitted.
4. The request is directly related to an “or equal” clause or similar language in the Contract Documents.
PART 3 – EXECUTION (NOT USED)
END OF SECTION 00 26 00
Forsyth Technical Community College Section 003113 -Preliminary Schedule
SECTION 00 31 13
PRELIMINARY SCHEDULE
END OF SECTION
Pre-Construction Start Finish
Construction Bid Advertisement Pre-Bid Meeting
Receive Bids Board Approval
♦ Issue Notice to Proceed
Construction Period ♦ Milestone 1 (rename as necessary/delete as necessary)
♦ Milestone 2 (rename as necessary/delete as
♦ Milestone 3 (rename as necessary/delete as
♦ Milestone 4 (rename as necessary/delete as
♦ Substantial Completion ♦ Final Completion
= Contractor milestone completion dates.
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
Forsyth Technical Community College Section 004113 -Bid Forms Northwest Campus Partial Roof Replacement Page 1 of 4
00 41 13
BID FORM STIPULATED SUM (SINGLE-PRIME CONTRACT)
PROJECT: Northwest Campus Partial Roof Replacement Forsyth Technical Community College
FACILITIES: Northwest Forsyth Center
BID DOCUMENTS: February 2026
CONTRACTOR: _________________________________________________________
ADDRESS: _________________________________________________________
(Telephone w/Area Code) ___________________________________________________
DATE: _______________________________
LICENSE/LIMITS: _______________________________________________________
NC LICENSE NUMBER: ______________________________________________________
INSURANCE CARRIER: ______________________________________________________
PRICE FOR WORK INCLUDED IN THE BID DOCUMENTS AND AS
OUTLINED IN THE SUMMERY OF WORK INCLUDING CONTINGENCIES:
Base Bid: (Roof Area 01.01 including $5,000 contingency)
Having visited the site of proposed Work and checked all dimensions of areas included in the Scope of Work.
AREA OF BASE BID: ______________________square feet
TIME TO COMPLETION IN CALENDAR DAYS, BASE BID: _________________
Time to completion may be considered in the award of the Contract.
We understand the requirements of the Specifications and Drawings for the project.
We acknowledge receipt of the following addenda to the Specifications (if none received, so state):
Prebid Meeting Minutes: _______
Addendum #1: ______
Addendum #2: ______
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
Northwest Campus Partial Roof Replacement Page 2 of 4
UNIT PRICES:
Unit prices shall be used for adjustments to the Contract at the discretion of the Owner in accordance with the General Conditions of the Contract and the Bid Documents. Unit Prices shall be for Work in place and shall include all costs, taxes, profit, and overhead.
• Attach Unit Pricing Sheet, Section 01 22 00, 3.1 LIST OF UNIT PRICES, to bid.
If additional work is required and is not covered by the Unit Prices, the Contractor shall perform the work at his actual cost plus the overhead and profit percentage given below. Percentages for extra work will be considered in the award of the Contract.
Cost plus _______________% Overhead and Profit
Cost shall be substantiated by certified material invoices and labor records maintained by the Contractor to be submitted to the Owner with his request for payment for additional required/requested Work.
SUB-CONTRACTORS: List all proposed sub-contractors by firm name. If no sub-contractors are anticipated, so state (NA).
Trade Contractor License
General Contractor
Plumbing Contractor
Mechanical Contractor
Electrical Contractor
The undersigned has enclosed the following with this Proposal:
______ Proposal
______ Unit Prices: Section 01 22 00 (Page 2)
______ 5% Bid Bond
______ MBE Affidavit A or B
______ E-Verify Affidavit
______ Identification of Minority Business Participation (As required)
______ Roof Manufacturer’s Acknowledgement
_____ Iran Divestment Act
CONTRACTOR:
ADDRESS:
BY:
TTTLE:
Print Name:
This Proposal shall be valid for _60_days from the date of submittal.
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
Northwest Campus Partial Roof Replacement Page 3 of 4
E-VERIFY AFFIDAVIT
FORSYTH TECHNICAL COMMUNITY COLLEGE
WINSTON SALEM, NORTH CAROLINA
I, ____________________________(the individual attesting below), being duly authorized by and on behalf of ________________________________ (the entity bidding on project hereinafter "Employer") after first being duly sworn hereby swears or affirms as follows:
1. Employer understands that E-Verify is the federal E-Verify program operated by the United States Department of Homeland Security and other federal agencies, or any successor or equivalent program used to verify the work authorization of newly hired employees pursuant to federal law in accordance with NCGS §64-25(5).
2. Employer understands that Employers Must Use E-Verify. Each employer, after hiring an employee to work in the United States, shall verify the work authorization of the employee through E-Verify in accordance with NCGS§64-26(a).
3. Employer is a person, business entity, or other organization that transacts business in this State and that employs 25 or more employees in this State. (mark Yes or No)
a. YES _____, or
b. NO _____
4. Employer's subcontractors comply with E-Verify, and if Employer is the winning bidder on this project Employer will ensure compliance with E-Verify by any subcontractors subsequently hired by Employer.
This ____ day of _______________, 2025.
Signature of Affiant
Print or Type Name: _________________________
FORSYTH TECHLICAL COMMUNITY COLLEGE
WINSTON SALEM, NORTH CAROLINA
Signed and sworn to (or affirmed) before me, this the _____ day of ________________, 2023.
My Commission Expires:
Notary Public
(Affix O fficial/N otarial Seal)
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
Northwest Campus Partial Roof Replacement Page 4 of 4
IRAN DIVESTMENT ACT
RFP Number (if applicable):
Name of Vendor or Bidder:
IRAN DIVESTMENT ACT CERTIFICATION
REQUIRED BY N.C.G.S. 14 -
As of the date listed below, the vendor or bidder listed above is not listed on the Final Divestment List created by the State Treasurer pursuant to N.C.G.S. 147-86.58.
The undersigned hereby certifies that he or she is authorized by the vendor or bidder listed above to make the foregoing statement.
Signature Date
Printed Name Title
Notes to persons signing this form:
N.C.G.S. 147-86.58 requires this certification for bids or contracts with the State of North Carolina, a North Carolina local government, or any other political subdivision of the State of North Carolina. The certification is required at the following times:
When a bid is submitted When a contract is entered into (if the certification was not already made when the vendor made its bid) When a contract is renewed or assigned
N.C.G.S. 147-86.58 requires that contractors with the State, a North Carolina local government, or any other political subdivision of the State of North Carolina must not utilize any subcontractor found on the State Treasurer’s Final Divestment List.
The State Treasurer’s Final Divestment List can be found on the State Treasurer’s website at the address www.nctreasurer.com/Iran and will be updated every 180 days.
http://www.nctreasurer.com/Iran
Forsyth Technical Community College Section 004313 -Form of Bid Bond Northwest Campus Partial Roof Replacement Page 2 of 1
00 43 13
FORM OF BID BOND
KNOW ALL MEN BY THESE PRESENTS THAT ________________
__________________________________________________________________ as principal, and _______________________________________________, as surety, who is duly licensed to act as surety in North Carolina, are held and firmly bound unto the Forsyth Technical Community College through _______________________________________________ as obligee, in the penal sum of ___________________________ DOLLARS, lawful money of the United States of America, for the payment of which, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
Signed, sealed and dated this day of 2 WHEREAS, the said principal is herewith submitting proposal for and the principal desires to file this bid bond in lieu of making the cash deposit as required by G.S. 143-129.
NOW, THEREFORE, THE CONDITION OF THE ABOVE OBLIGATION is such, that if the principal shall be awarded the contract for which the bid is submitted and shall execute the contract and give bond for the faithful performance thereof within ten days after the award of same to the principal, then this obligation shall be null and void; but if the principal fails to so execute such contract and give performance bond as required by G.S. 143-129, the surety shall, upon demand, forthwith pay to the obligee the amount set forth in the first paragraph hereof. Provided further, that the bid may be withdrawn as provided by G.S. 143-129.1
(SEAL)
(SEAL)
(SEAL)
(SEAL)
(SEAL)
MBGuidelines 2002 - i-
GUIDELINES FOR RECRUITMENT AND SELECTION OF MINORITY BUSINESSES FOR
PARTICIPATION IN STATE CONSTRUCTION CONTRACTS
In accordance with G.S. 143-128.2 (effective January 1, 2002) these guidelines establish goals for minority participation in single-prime bidding, separate-prime bidding, construction manager at risk, and alternative contracting methods, on State construction projects in the amount of $300,000 or more. The legislation provides that the State shall have a verifiable ten percent (10%) goal for participation by minority businesses in the total value of work for each project for which a contract or contracts are awarded. These requirements are published to accomplish that end.
SECTION A: INTENT
It is the intent of these guidelines that the State of North Carolina, as awarding authority for construction projects, and the contractors and subcontractors performing the construction contracts awarded shall cooperate and in good faith do all things legal, proper and reasonable to achieve the statutory goal of ten percent (10%) for participation by minority businesses in each construction project as mandated by GS 143-128.2. Nothing in these guidelines shall be construed to require contractors or awarding authorities to award contracts or subcontracts to or to make purchases of materials or equipment from minority-business contractors or minority-business subcontractors who do not submit the lowest responsible, responsive bid or bids.
SECTION B: DEFINITIONS
1. Minority - a person who is a citizen or lawful permanent resident of the United States and who is:
a. Black, that is, a person having origins in any of the black racial groups in Africa;
b. Hispanic, that is, a person of Spanish or Portuguese culture with origins in Mexico, South or
Central America, or the Caribbean Islands, regardless of race;
c. Asian American, that is, a person having origins in any of the original peoples of the Far
East, Southeast Asia and Asia, the Indian subcontinent, the Pacific Islands;
d. American Indian, that is, a person having origins in any of the original peoples of North
America; or
e. Female
2. Minority Business - means a business:
a. In which at least fifty-one percent (51%) is owned by one or more minority persons, or in the case of a corporation, in which at least fifty-one percent (51%) of the stock is owned by one or more minority persons or socially and economically disadvantaged individuals; and
b. Of which the management and daily business operations are controlled by one or more of the minority persons or socially and economically disadvantaged individuals who own it.
3. Socially and economically disadvantaged individual - means the same as defined in 15 U.S.C.
637. “Socially disadvantaged individuals are those who have been subjected to racial or ethnic prejudice or cultural bias because of their identity as a member of a group without regard to their individual qualities”. “Economically disadvantaged individuals are those socially disadvantaged individuals whose ability to compete in the free enterprise system has been impaired due to diminished capital and credit opportunities as compared to others in the same business area who are not socially disadvantaged”.
4. Public Entity - means State and all public subdivisions and local governmental units.
5. Owner - The State of North Carolina, through the Agency/Institution named in the contract.
6. Designer – Any person, firm, partnership, or corporation, which has contracted with the State of
North Carolina to perform architectural or engineering, work.
7. Bidder - Any person, firm, partnership, corporation, association, or joint venture seeking to be awarded a public contract or subcontract.
MBGuidelines 2002 - ii-
8. Contract - A mutually binding legal relationship or any modification thereof obligating the seller to furnish equipment, materials or services, including construction, and obligating the buyer to pay for them.
9. Contractor - Any person, firm, partnership, corporation, association, or joint venture which has contracted with the State of North Carolina to perform construction work or repair.
10. Subcontractor - A firm under contract with the prime contractor or construction manager at risk for supplying materials or labor and materials and/or installation. The subcontractor may or may not provide materials in his subcontract.
SECTION C: RESPONSIBILITIES
1. Office for Historically Underutilized Businesses, Department of Administration (hereinafter referred to as HUB Office).
The HUB Office has established a program, which allows interested persons or businesses qualifying as a minority business under G.S. 143-128.2, to obtain certification in the State of North Carolina procurement system. The information provided by the minority businesses will be used by the HUB Office to:
a. Identify those areas of work for which there are minority businesses, as requested.
b. Make available to interested parties a list of prospective minority business contractors and subcontractors.
c. Assist in the determination of technical assistance needed by minority business contractors.
In addition to being responsible for the certification/verification of minority businesses that want to participate in the State construction program, the HUB Office will:
(1) Maintain a current list of minority businesses. The list shall include the areas of work in which each minority business is interested.
(2) Inform minority businesses on how to identify and obtain contracting and subcontracting opportunities through the State Construction Office and other public entities.
(3) Inform minority businesses of the contracting and subcontracting process for public construction building projects.
(4) Work with the North Carolina trade and professional organizations to improve the ability of minority businesses to compete in the State construction projects.
(5) The HUB Office also oversees the minority business program by:
a. Monitoring compliance with the program requirements.
b. Assisting in the implementation of training and technical assistance programs.
c. Identifying and implementing outreach efforts to increase the utilization of minority businesses.
d. Reporting the results of minority business utilization to the Secretary of the
Department of Administration, the Governor, and the General Assembly.
2. State Construction Office
The State Construction Office will be responsible for the following:
a. Furnish to the HUB Office a minimum of twenty-one days prior to the bid opening the following:
(1) Project description and location;
(2) Locations where bidding documents may be reviewed;
(3) Name of a representative of the owner who can be contacted during the advertising period to advise who the prospective bidders are;
(4) Date, time and location of the bid opening.
(5) Date, time and location of prebid conference, if scheduled.
b. Attending scheduled prebid conference, if necessary, to clarify requirements of the general statutes regarding minority-business participation, including the bidders' responsibilities.
MBGuidelines 2002 - iii-
c. Reviewing the apparent low bidders' statutory compliance with the requirements listed in the proposal, that must be complied with, if the bid is to be considered as responsive, prior to award of contracts. The State reserves the right to reject any or all bids and to waive informalities.
d. Reviewing of minority business requirements at Preconstruction conference.
e. Monitoring of contractors’ compliance with minority business requirements in the contract documents during construction.
f. Provide statistical data and required reports to the HUB Office.
g. Resolve any protest and disputes arising after implementation of the plan, in conjunction with the
HUB Office.
3. Owner
Before awarding a contract, owner shall do the following:
a. Develop and implement a minority business participation outreach plan to identify minority businesses that can perform public building projects and to implement outreach efforts to encourage minority business participation in these projects to include education, recruitment, and interaction between minority businesses and non-minority businesses.
b. Attend the scheduled prebid conference.
c. At least 10 days prior to the scheduled day of bid opening, notify minority businesses that have requested notices from the public entity for public construction or repair work and minority businesses that otherwise indicated to the Office for Historically Underutilized Businesses an interest in the type of work being bid or the potential contracting opportunities listed in the proposal. The notification shall include the following:
1. A description of the work for which the bid is being solicited.
2. The date, time, and location where bids are to be submitted.
3. The name of the individual within the owner’s organization who will be available to answer questions about the project.
4. Where bid documents may be reviewed.
5. Any special requirements that may exist.
d. Utilize other media, as appropriate, likely to inform potential minority businesses of the bid being sought.
e. Maintain documentation of any contacts, correspondence, or conversation with minority business firms made in an attempt to meet the goals.
f. Review, jointly with the designer, all requirements of G.S. 143-128.2(c) and G.S. 143-128.2(f) – (i.e. bidders’ proposals for identification of the minority businesses that will be utilized with corresponding total dollar value of the bid and affidavit listing good faith efforts, or affidavit of self-performance of work, if the contractor will perform work under contract by its own workforce) - prior to recommendation of award to the State Construction Office.
g. Evaluate documentation to determine good faith effort has been achieved for minority business utilization prior to recommendation of award to State Construction Office.
h. Review prime contractors’ pay applications for compliance with minority business utilization commitments prior to payment.
i. Make documentation showing evidence of implementation of Owner’s responsibilities available for review by State Construction Office and HUB Office, upon request
4. Designer
Under the single-prime bidding, separate prime bidding, construction manager at risk, or alternative contracting method, the designer will:
a. Attend the scheduled prebid conference to explain minority business requirements to the prospective bidders.
b. Assist the owner to identify and notify prospective minority business prime and subcontractors of potential contracting opportunities.
c. Maintain documentation of any contacts, correspondence, or conversation with minority business firms made in an attempt to meet the goals.
d. Review jointly with the owner, all requirements of G.S. 143-128.2(c) and G.S.143-128.2(f) –
(i.e. bidders’ proposals for identification of the minority businesses that will be utilized with
MBGuidelines 2002 - iv-corresponding total dollar value of the bid and affidavit listing Good Faith Efforts, or affidavit of self-performance of work, if the contractor will perform work under contract by its own workforce) - prior to recommendation of award.
e. During construction phase of the project, review “MBE Documentation for Contract Payment” – (Appendix E) for compliance with minority business utilization commitments. Submit Appendix E form with monthly pay applications to the owner and forward copies to the State Construction Office.
f. Make documentation showing evidence of implementation of Designer’s responsibilities available for review by State Construction Office and HUB Office, upon request.
5. Prime Contractor(s), CM at Risk, and Its First-Tier Subcontractors Under the single-prime bidding, the separate-prime biding, construction manager at risk and alternative contracting methods, contractor(s) will:
a. Attend the scheduled prebid conference.
b. Identify or determine those work areas of a subcontract where minority businesses may have an interest in performing subcontract work.
c. At least ten (10) days prior to the scheduled day of bid opening, notify minority businesses of potential subcontracting opportunities listed in the proposal. The notification will include the following:
(1) A description of the work for which the subbid is being solicited.
(2) The date, time and location where subbids are to be submitted.
(3) The name of the individual within the company who will be available to answer questions about the project.
(4) Where bid documents may be reviewed.
(5) Any special requirements that may exist, such as insurance, licenses, bonds and financial arrangements.
If there are more than three (3) minority businesses in the general locality of the project who offer similar contracting or subcontracting services in the specific trade, the contractor(s) shall notify three (3), but may contact more, if the contractor(s) so desires.
d. During the bidding process, comply with the contractor(s) requirements listed in the proposal for minority participation.
e. Identify on the bid, the minority businesses that will be utilized on the project with corresponding total dollar value of the bid and affidavit listing good faith efforts as required by G.S. 143-128.2(c) and G.S. 143-128.2(f).
f. Make documentation showing evidence of implementation of PM, CM-at-Risk and First-Tier Subcontractor responsibilities available for review by State Construction Office and HUB Office, upon request.
g. Upon being named the apparent low bidder, the Bidder shall provide one of the following: (1) an affidavit (Affidavit C) that includes a description of the portion of work to be executed by minority businesses, expressed as a percentage of the total contract price, which is equal to or more than the applicable goal; (2) if the percentage is not equal to the applicable goal, then documentation of all good faith efforts taken to meet the goal. Failure to comply with these requirements is grounds for rejection of the bid and award to the next lowest responsible and responsive bidder.
h. The contractor(s) shall identify the name(s) of minority business subcontractor(s) and corresponding dollar amount of work on the schedule of values. The schedule of values shall be provided as required in Article 31 of the General Conditions of the Contract to facilitate payments to the subcontractors.
i. The contractor(s) shall submit with each monthly pay request(s) and final payment(s), “MBE Documentation for Contract Payment” – (Appendix E), for designer’s review.
j. During the construction of a project, at any time, if it becomes necessary to replace a minority business subcontractor, immediately advise the owner, State Construction Office, and the Director of the HUB Office in writing, of the circumstances involved. The prime contractor shall make a good faith effort to replace a minority business subcontractor with another minority business subcontractor.
MBGuidelines 2002 - v-
k. If during the construction of a project additional subcontracting opportunities become available, make a good faith effort to solicit subbids from minority businesses.
l. It is the intent of these requirements apply to all contractors performing as prime contractor and first tier subcontractor under construction manager at risk on state projects.
6. Minority Business Responsibilities
While minority businesses are not required to become certified in order to participate in the State construction projects, it is recommended that they become certified and should take advantage of the appropriate technical assistance that is made available. In addition, minority businesses who are contacted by owners or bidders must respond promptly whether or not they wish to submit a bid.
SECTION 4: DISPUTE PROCEDURES
It is the policy of this state that disputes that involves a person's rights, duties or privileges, should be settled through informal procedures. To that end, minority business disputes arising under these guidelines should be resolved as governed under G.S. 143-128(g).
SECTION 5: These guidelines shall apply upon promulgation on state construction projects. Copies of these guidelines may be obtained from the Department of Administration, State Construction Office, (physical address) 301 North Wilmington Street, Suite 450, NC Education Building, Raleigh, North Carolina, 27601-2827, (mail address) 1307 Mail Service Center, Raleigh, North Carolina, 27699-1307, phone (919) 807-4100, Website: www.nc-sco.com
SECTION 6: In addition to these guidelines, there will be issued with each construction bid package provisions for contractual compliance providing minority business participation in the state construction program.
MBGuidelines 2002 - vi-
MINORITY BUSINESS CONTRACT PROVISIONS (CONSTRUCTION)
APPLICATION:
The Guidelines for Recruitment and Selection of Minority Businesses for Participation in State Construction Contracts are hereby made a part of these contract documents. These guidelines shall apply to all contractors regardless of ownership. Copies of these guidelines may be obtained from the Department of Administration, State Construction Office, (physical address) 301 North Wilmington Street, Suite 450, NC Education Building, Raleigh, North Carolina, 27601-2827, (mail address) 1307 Mail Service Center, Raleigh, North Carolina, 27699-1307, phone (919) 807-4100, Website:
http://www.nc-sco.com
MINORITY BUSINESS SUBCONTRACT GOALS:
The goals for participation by minority firms as subcontractors on this project have been set at 10%.
The bidder must identify on its bid, the minority businesses that will be utilized on the project with corresponding total dollar value of the bid and affidavit (Affidavit A) listing good faith efforts or affidavit (Affidavit B) of self-performance of work, if the bidder will perform work under contract by its own workforce, as required by G.S. 143-128.2(c) and G.S. 143-128.2(f).
The lowest responsible, responsive bidder must provide Affidavit C, that includes a description of the portion of work to be executed by minority businesses, expressed as a percentage of the total contract price, which is equal to or more than the applicable goal.
OR
Provide Affidavit D, that includes a description of the portion of work to be executed by minority businesses, expressed as a percentage of the total contract price, with documentation of Good Faith Effort, if the percentage is not equal to the applicable goal.
OR
Provide Affidavit B, which includes sufficient information for the State to determine that the bidder does not customarily subcontract work on this type project.
The above information must be provided as required. Failure to submit these documents is grounds for rejection of the bid.
MBGuidelines 2002 - vii-
MINIMUM COMPLIANCE REQUIREMENTS:
All written statements, affidavits or intentions made by the Bidder shall become a part of the agreement between the Contractor and the State for performance of this contract. Failure to comply with any of these statements, affidavits or intentions, or with the minority business Guidelines shall constitute a breach of the contract. A finding by the State that any information submitted either prior to award of the contract or during the performance of the contract is inaccurate, false or incomplete, shall also constitute a breach of the contract. Any such breach may result in termination of the contract in accordance with the termination provisions contained in the contract. It shall be solely at the option of the State whether to terminate the contract for breach.
In determining whether a contractor has made Good Faith Efforts, the State will evaluate all efforts made by the Contractor and will determine compliance in regard to quantity, intensity, and results of these efforts. Good Faith Efforts include:
(1) Contacting minority businesses that reasonably could have been expected to submit a quote and that were known to the contractor or available on State or local government maintained lists at least 10 days before the bid or proposal date and notifying them of the nature and scope of the work to be performed.
(2) Making the construction plans, specifications and requirements available for review by prospective minority businesses, or providing these documents to them at least 10 days before the bid or proposals are due.
(3) Breaking down or combining elements of work into economically feasible units to facilitate minority participation.
(4) Working with minority trade, community, or contractor organizations identified by the Office for Historically Underutilized Businesses and included in the bid documents that provide assistance in recruitment of minority businesses.
(5) Attending any prebid meetings scheduled by the public owner.
(6) Providing assistance in getting required bonding or insurance or providing alternatives to bonding or insurance for subcontractors.
(7) Negotiating in good faith with interested minority businesses and not rejecting them as unqualified without sound reasons based on their capabilities. Any rejection of a minority business based on lack of qualification should have the reasons documented in writing.
(8) Providing assistance to an otherwise qualified minority business in need of equipment, loan capital, lines of credit, or joint pay agreements to secure loans, supplies, or letters of credit, including waiving credit that is ordinarily required. Assisting minority businesses in obtaining the same unit pricing with the bidder's suppliers in order to help minority businesses in establishing credit.
(9) Negotiating joint venture and partnership arrangements with minority businesses in order to increase opportunities for minority business participation on a public construction or repair project when possible.
(10) Providing quick pay agreements and policies to enable minority contractors and suppliers to meet cash-flow demands.
MBGuidelines 2002 - viii-
APPENDIX E
MBE DOCUMENTATION FOR CONTRACT PAYMENTS
Prime Contractor/Architect: _________________________________________________________
Address & Phone: _________________________________________________________________
Project Name: ____________________________________________________________________
Pay Application #: _________________ Period: ________________________________
The following is a list of payments made to Minority Business Enterprises on this project for the above-mentioned period.
MBE FIRM NAME * INDICATE
TYPE OF
MBE
AMOUNT
PAID
THIS MONTH
TOTAL
PAYMENTS TO
DATE
TOTAL
AMOUNT
COMMITTED
*Minority categories: Black, African American (B), Hispanic (H), Asian American (A), American Indian (I), Female (F), Social and Economically Disadvantage (D)
Date: ________________ Approved/Certified By: ___________________________________ Name
Title
Signature
SUBMIT WITH EACH PAY REQUEST & FINAL PAYMENT
(Revised on 3/14/2003)
Forsyth Technical Community College Section 004339 -MWSBE Program Northwest Campus Partial Roof Replacement Page 1 of 7
00 43 39
Identification of HUB Certified/ Minority Business Participation
I, ,do hereby certify that on (Name of Bidder) this project, we will use the following minority, women, or small business enterprises as construction subcontractors, vendors, suppliers or providers of professional services.
Firm Name, Address and Phone # Work type *M/W/SBE Category
*M/W/SBE categories: Black, African American (B), Hispanic (H), Asian American (A) American Indian (I), Female (F), Small (S), or Socially and Economically Disadvantaged (D)
The total value of M/W/SBE firms contracting will be ($) .
Attach this form and AFFIDAVIT A or this form and AFFIDAVIT B to the Bid
Northwest Campus Partial Roof Replacement Page 2 of 7
Attach to bid (as appropriate) Attach to bid (as appropriate) Attach to bid (as appropriate)
AFFIDAVIT A
Listing of Good Faith Efforts
County of Affidavit of (Name of Bidder)
I have made a good faith effort to comply under the following areas checked:
Bidders must earn at least 50 points from the good faith efforts listed for their bid to be considered responsive.
(1 NC Administrative Code 30 I.0101)
1 – (10 pts) Contacted minority businesses that reasonably could have been expected to submit a quote and that were known to the contractor, or available on State or local…