This document is a Non-Mandatory Pre-Bid Conference Agenda issued by Colorado Parks and Wildlife for the Mount Evans State Wildlife Area Shop Restroom Facility project (Project #C18NE6 DQ - 2019*56). The project involves furnishing and installing a 10' x 8' insulated and heated wood-framed restroom facility with a shower, toilet, and sink at the Mount Evans location. The pre-bid conference was held on August 1, 2018, at 1:00 PM. Written questions were to be submitted to Design Engineer Aaron Boonstra and would be accepted through August 6, 2018, at 5:00 PM MST, with responses provided in a final addendum posted to the Colorado Vendor Self Serve website. Sealed bids and email bids were due on August 15, 2018, by 1:00 PM MST at Colorado Parks and Wildlife Headquarters, 6060 Broadway, Denver, Colorado 80216. A Notice of Award was intended to be issued by end of business on the bid due date to the lowest responsible bidder, contingent upon the bid falling within the project budget. The contract time allows 90 calendar days for construction completion from the Notice to Proceed, expected in September 2018, with construction permitted Monday through Friday between sunrise and sunset unless otherwise approved in writing.
Bonding is required if a bid exceeds $150,000.00, and the contractor must provide all temporary electric, water, and sanitary facilities necessary for construction. Contract processing is expected to take two to three weeks following receipt of all required documents, including insurance certificates and W-9 forms. Colorado Parks and Wildlife will not require special permits other than electrical permits, which the awarded contractor must obtain from the Colorado Electrical Board if the electrical bid item is awarded. The attendance list from the pre-bid conference will be posted on the State Vendor Self Serve website. All addendums must be acknowledged on the bid proposal, and failure to acknowledge will result in bid rejection. Weather days may be granted at the Project Manager's discretion, and the project may be shut down due to unfavorable conditions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6060 Broadway, Denver, CO 80216 P 303-291-7387 | F 303-291-7108 Wildlife.state.co.us | Parks.state.co.us
NON-MANDATORY PRE-BID CONFERENCE AGENDA
AT MOUNT EVANS SWA
2017 SHOP RESTROOM FACILITY
PROJECT # C18NE6
DQ – 2019*56
08/01/2018 @ 1:00 PM
COLORAD PARKS & WILDLIFE COLORAD PARKS & WILDLIFE
DEVELOPMENT SECTION DEVELOPMENT SECTION
AARON BOONSTRA – DESIGN ENGINEER DAVE COFFMAN – PROJECT MANAGER
PHONE (303) 291-7176 PHONE (303) 291-7407
EMAIL aaron.boonstra@state.co.us
EMAIL david.coffman@state.co.us
1.General:
a. All questions shall be in writing and sent to Aaron Boonstra, Design Engineer via email.
b. Any Addendum will be posted on the State VSS website www.colorado.gov/VSS
c. If issued, all addendums must be acknowledged on the bid proposal. It is the bidder’s responsibility to check for addendums. Failure to acknowledge will result in rejection of bid.
d. Attendance List will be e-mailed to all those on the list. It will also be posted on the State Vendor
Self Serve website (www.colorado.gov/VSS).
2.Proposed Project Timing:
a. No further questions will be allowed after 5:00 PM MST on August 6, 2018. Any questions will be addressed in a Final Addendum that will be posted to the State VSS website.
b. Bids Due – August 15 by 1:00 PM MST @ the Parks and Wildlife Headquarters at 6060 Broadway, Denver, CO 80216. Sealed and e-mail bids will be accepted up to the due date/time. All bids shall be to the attention of Aaron Boonstra. Bids will be tabulated immediately following and sent to bidders.
c. Bonding – bonding, including bid bond, is required if a bid is over $150,000.00.
d. A Notice of Award is intended to be issued by the end of the day bids are due, to the lowest responsible bidder, as long as the bid falls within the Project’s budget. Notification and the Bid Tabulation will be sent to all Bidders.
e. Notice to Proceed – It is expected that a Contract will take 2-3 weeks to be processed once all required documents (insurance certificate, W-9, etc.) are received from the Awarded Contractor.
NON-MANDATORY PRE-BID CONFERENCE AGENDA
AT MOUNT EVANS SWA
2017 SHOP RESTROOM FACILITY
PROJECT # C18NE6
DQ – 2019*56
08/01/2018 @ 1:00 PM
f. Construction shall be allowed between sunrise and sunset, Monday –Friday, unless otherwise approved in writing.
g. From the Notice to Proceed – the Contractor shall have 90 calendar days to complete the project, unless otherwise provided for in the General Conditions (GC’s). Project may be shutdown due to unfavorable conditions.
h. Contractor must provide all temporary electric, water and sanitary facilities necessary for the construction improvements.
3.General Information:
a. The intent of this project is to furnish and install a 10’x8’ insulated and heated wood framed restroom facility with a shower, toilet and sink.
b. All quantities are estimates only and may be increased or decreased as needed and allowed per the GC’s. GC’s are attached as part of the bid posting.
c. A Notice to Proceed is expected to be issued in September 2018, and may be weather dependant.
d. The contract time allows 90 calendar days. Weather days may be granted at the Project
Managers discretion.
e. CPW will not require any special permits other than electrical (if awarded). If the electrical bid item is awarded, a permit must be obtained from the Colorado Electrical Board.
f. Please note, addendums will be an attachment in VSS with the word “addendum #” in the title and in the file. Addendums must be acknowledged on the bid schedule.
Amendments are part of the VSS posting system. These do not need to be acknowledged, but may have an addendum associated with them. For example, amendment #2 will likely be the posting of the pre-bid attendance list.
4.Questions?