This is a Statement of Work (SOW) for the fabrication of a new Salvage Pump Maintenance Tower at U.S. Coast Guard Air Station New Orleans in Belle Chasse, Louisiana. The contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel required to complete the fabrication and installation. The existing tower has been condemned due to excessive corrosion and non-compliance with current OSHA standards, which has prevented personnel from conducting necessary maintenance on aircraft dewater pumps required for Search and Rescue operations. All work must be built to specifications stated in COMDTINST 13520.1D and must comply with applicable federal safety regulations (29 CFR 1910 and 1926), EPA, OSHA, and State of Louisiana laws. Work shall be performed between 8:00 AM and 3:30 PM, Monday through Friday, to minimize interference with facility operations.
The contract timeline requires the contractor to submit all required submittals within 14 calendar days of award, with the government providing 7 calendar days for review. The contractor must provide a firm delivery date within 14 calendar days of award and has 14 calendar days to begin work and 30 calendar days to complete the project. Key deliverables include a detailed plan with repairs, work schedule, and timeline; warranty information; and final acceptance by the designated POC. The contractor is wholly responsible for work site safety, environmental compliance (including RCRA hazardous waste management), waste disposal off-site, and site restoration. A one-year workmanship warranty is required. The Service Contract Act applies to this procurement, and the contractor must schedule all work with the Technical Representative, ASTC Patrick McGinnis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1442.pdf | ||
| Construction Clauses Template 2026.pdf | ||
| Construction Wage Rates.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Air Station New Orleans’ Salvage Pump Maintenance Tower
Located at U.S. Coast Guard Air Station New Orleans 400 Russell Ave.
Belle Chasse, LA 70143
June 2026
Commanding Officer United States Coast Guard Air Station New Orleans, LA Aviation Engineering Department
ASTC Patrick McGinnis Air Station New Orleans, LA
PART 1: GENERAL
1. INTENT: The intent of this project is to fabricate a new Salvage Pump Maintenance Tower. All work shall be completed as outlined in this Scope of Work. No work is authorized without the authorization of the Contracting Officer (KO) or the Contracting Officers Representative (COR).
2. SCOPE OF WORK: Contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel to fabricate the new Salvage Pump Maintenance Tower. All waste materials will be disposed of off-site. No modifications outside of the Statement of Work criteria are authorized without permission from the contracting officer or their representative.
3. BACKGROUND: Current Salvage Pump Maintenance Tower has been condemned due to excessive corrosion and configuration not adhering to current OSHA standards. The degraded status has inhibited personnel from conducting appropriate maintenance to aircraft dewater pumps required for Search and Rescue operations.
4. QUALIFICATIONS: Contractor shall provide personnel who have the knowledge, qualifications, and working experience to perform the functions outlined in this Scope of Work.
5. CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facility’s normal operations. Perform all on-site work between the hours of 8:00 AM and 3:30 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s representative.
6. GOVERNMENT FURNISHED MATERIALS: None.
7. GOVERNMENT FACILITIES AND UTILITIES: Electrical power and water are available within proximity. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded. Telephone services will not be available for use by the contractor. Building restroom facilities are available for use.
8. SAFETY: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with and abiding by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1926 (series), State and Local safety laws, rules and regulations. Any operation defined as “Hot Work” as per OSHA/NFPA requires a permit to be issued. In the event of Hot Work, the Contractor will notify the COR with dates and times Hot Work will be performed. Contractor is to give at least 48 hours notification. This includes welding, cutting, brazing, grinding or any work that could produce sparks or heat and may initiate a fire.
9. ENVIRONMENTAL COMPLIANCE: Any waste generated because of the project shall either be recycled or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with Air Station New Orleans listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of IAW RCRA and all applicable federal, state (i.e. DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. Waste and recycling areas are reserved for RCF Tenants and shall not be used by Contractors at any time. All work will be performed IAW the Air Station New Orleans Spill Prevention Control and Countermeasures Plan. All chemicals required for this project shall be preapproved by the contract POC along with SDS’s. All solid waste shall be removed from the RCF after each working day. All extra chemicals and products shall be removed from the site upon work completion, as the Emergency Planning and Community Right-To-Know Act requires Coast Guard maintains an inventory of all Hazardous Materials located at the site. A laydown area as required and an Erosion and Sediment Control Plan, shall be preapproved by the COR as needed. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence.
10. SITE VISIT: All site visits should be scheduled with the Point of Contact. Any personnel coming on site without a TWIC, military or prior approved ID, will need to provide two forms of identification, proof of insurance, and vehicle registration at a minimum of (2) two business days prior to arrival, so a security badge can be created to allow access on the base. All personnel requiring access to Naval Air Station Joint Reserve Base Belle Chase must have REAL ID.
| Point of Contact (POC) | |
| ASTC Patrick McGinnis | |
| Cell: (912) 572-3819 | |
| Email: Patrick.G.McGinnis@uscg.mil |
11. MATERIALS:
a) The Contractor will furnish all materials, equipment, instruments, tools, safety lines and harnesses, and other items necessary for accomplishment of these services.
b) Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturer’s recommendations in a clean, dry, well-ventilated area. Stored materials shall be protected from sunlight and kept away from excessive heat. The contractor shall not store any highly flammable materials in the work area and all chemicals used shall be preapproved by POC. Laydown areas and parking should be on non-vegetated areas when possible.
c) The Contractor is required to comply with local VOC laws and regulations. All applicable Safety Data Sheets shall be available upon request.
12. LIABILITY OF CONTRACTOR: Any damage to government property caused by the contractor shall be repaired or replaced by the contractor at no cost to the government. The contractor shall not disconnect any service without approval from the Technical Representative.
PART 2: PERFORMANCE STANDARDS
1. PERFORMANCE REQUIREMENTS: Contractor shall provide all materials and personnel to complete fabricate a Salvage Pump Maintenance Tower, built to specifications stated in COMDTINST 13520.1D, provided as Enclosure 1 to this SOW
2. LABOR LAWS: The Service Contract Act applies to the procurement.
3. SITE RESTORATION & CLEAN UP: The work site shall be cleaned up at the completion of each workday. Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The Contractor shall properly dispose of any trash, extra materials, dirt, debris, or other litter that remains, off-site. There will be no final acceptance of the contract until the Contracting Officers Representative approves the appearance of the job site.
4. GOVERNMENT FACILITIES AND REGULATIONS: The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Base/ Unit regulations. All personnel employed on the project shall keep within the limits of the work area and shall not enter any other area outside of the work site unless to do so in the performance of their duties. There shall be No Smoking in any Coast Guard Building. All smoking must be done in the designated smoking area.
5. CONTRACT TIMELINE: The Contractor shall provide all required information and complete this contract within this time schedule, unless approved by the Contracting Officer.
a) Provide all required submittals to the Contracting Officer within 14 calendar days after contract award.
b) The U.S. Coast Guard will have 7 calendar days to review the submittals and respond to Contractor.
c) Contractor shall provide projected delivery schedule during proposal and provide a firm delivery date within 14 calendar days after the contract has been awarded.
d) The Contractor, upon receiving notification that the U.S. Coast Guard has approved the submittals and having received the Contractors firm delivery date schedule, will have 14 Calendar days to begin work on the project & 30 Calendar days to complete. The Contractor shall notify the Contracting Officer of any long lead time delivery of equipment, so that the Contracting Officer can modify the delivery date of the contract.
6. DELIVERABLES: Once awarded, the following list of submittals required for approval defines the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance of the material with these specifications and referenced specifications.
a) Prior to project execution submit detailed plan to include repairs, work schedule, and proposed timeline.
b) Warranty information
c) Designated POC will sign accept delivery of all materials and parts and verify compliance with build requirements.
7. EXECUTION: Installation, workmanship, fabrication, assembly, erection, examination, inspection and testing shall be in accordance with appropriate sections of 29 CFR 1910, 1926.
a) The Contractor shall schedule all work with the Technical Representative. The Contractor shall understand the importance to schedule and complete all work in a timely fashion. The Contractor shall minimize the impact for the command and/or mission of the personnel located at each location.
b) The Contractor shall perform all work IAW all Federal, EPA, OSHA, and State of Louisiana laws and regulations.
8. WARRANTY: Contractor shall provide a 1-year workmanship warranty.