This is a NOAA Atlantic Marine Center Standard Specification for conducting hydrostatic pressure tests on pressure vessels and piping systems aboard NOAA ships.

The specification establishes mandatory procedures for performing hydrostatic tests, including pre-test coordination with the Contracting Officer's Technical Representative (COTR). Test pressure shall be 125 percent of maximum allowable working pressure unless otherwise specified in the procurement document. The contractor must isolate and blank-off connected piping and equipment using blank flanges or suitable valves to prevent contamination. Relief valves must be removed prior to testing, inspected for proper operation, and reset to 105 percent of maximum operating pressure (or as specified), then tagged with test date and pressure setting. For air or vapor service vessels, additional temporary support must be provided to accommodate water weight. Potable water is required for potable water systems; fresh water for all other systems. All air must be vented and air pockets eliminated before pressure application. New welds and flanged joints shall remain uncovered until test acceptance by the COTR. Test equipment must include a self-actuated relief valve set at no greater than 110 percent of test pressure, a calibrated master pressure gage (calibrated within 12 months with graduation no greater than 2 percent of test pressure), a water pump capable of slow pressure application, and an isolation valve. The test pressure must be maintained for 10 minutes, followed by additional time as determined by the COTR for leak and stress inspection. After acceptance, all test water must be pumped and disposed of properly. Each pressure vessel test plate must be stamped with the date and test pressure. The COTR must witness all tests and relief valve settings, and the contractor must provide two copies of a test report to the COTR containing contractor name, test pressure, relief valve setting, and test date.

View the file

Other files for this federal contract opportunity

Other files attached to MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS, newest first.
File Type Posted
TJ-573-01 Cranes Deck and Boom O M.pdf PDF
TJ_FY2027 DD_Fire System Inventory_Fixed Semi-Cylinders.pdf PDF
NOAA Standard Specification MOC-167-1 Refurbishment of Water Tight Closures.pdf PDF
NOAA Standard Specification MOC-100-1A_Abs Load Line Survey.pdf PDF
NOAA Standard Specification AMC-505-1B_Valve Overhaul and Tests.pdf PDF
48026A-GI INDUSTRIAL-NOAA T JEFFERSON-POTBD_UTT.pdf PDF
1102-35 - Safe Use of Rigging Equipment (public).docx DOCX document
NF 57-07-12 - DryDock-UWILD Inspection Checklist (public).pdf PDF
Steyr Motors Marine Engines Manual.pdf PDF
TJ-233-03 EMD Engine 12-645F7B.pdf PDF
TJ-311-03 EDG Alternator.pdf PDF
Capstan_SA-1128 Manual for SA1014.pdf PDF
436-6634707 Machinery Alarm and Monitoring System Dk Pln - redline.pdf PDF
528-6634786E Plumbing and Deck Drains Arrangement and Details_130709483.pdf PDF
512-6634856_HVAC Arr and Details FCSLE Deck Fr 19-50.pdf PDF
TJ-079-03E Trim and Stability Booklet_101947795.pdf PDF
525-6634754E Fills Vents and Soundings Arrngmnt and Details.pdf PDF
TJ-528-009A - Grey Water and Sewage Modifications.pdf PDF
612-6634889D Lifelines Handrails and Stanchions.pdf PDF
TJ-611-6634891F DECK FITTINGS ARRANGEMENT and DETAILS.pdf PDF
163-6634821_Seachest Details.pdf PDF
243-6634740_Propeller Shafting Arrangement and Details.pdf PDF
TJ-582-002A New Transom Mooring Chock Inst.pdf PDF
636-6634911 Acoustic Tile Installation Arr.pdf PDF
601-6634921 Joiner Arrangement Main Deck.pdf PDF
320-6634691 Cable Wtrtight Penetrations - redline.pdf PDF
TJ_985_985-6634639_RevP_Sht1 THRU 3_ABS_FIRE CONTROL PLAN.pdf PDF
259-6634767 Diesel Engine Exhaust Arrangement.pdf PDF
514-3275003-12_91762335.pdf PDF
512-6634850F HVAC ARRNGMNT ENGRM_124644191.pdf PDF
TJ-583-022A Platform and Grating Mods.pdf PDF
101-6634867 Structural Module 8.pdf PDF
512-3275003-7 HVAC MODS 01 LVL AND ABV REV B.pdf PDF
801-6634641_Table of Offsets.pdf PDF
101-6634866_Structural Module Assembly No 7.pdf PDF
TJ-529-001A Cross Flooding Piping Installation.pdf PDF
TJ-562-001A Rudder Arrangment and Details_102457373.pdf PDF
562-6634741D Rudder Arrangement and Details.pdf PDF
073-6634629_Resilient and Dim Mounting List.pdf PDF
101-6634864 Structural Module 5.pdf PDF
259-6634766 Engine Exhaust System.pdf PDF
TJ-437-004 TLI Electrical Modifications.pdf PDF
TJ_FY2027 DD_Fire System Inventorya.pdf PDF
TJ_FY2027 DD_Fire System Inventory_Portables.pdf PDF
NOAA Standard Specification AMC-240-1 Propulsion Shafts and Propellers.pdf PDF
NOAA Standard Specification MOC-000-1G_General_Requirements for Ship Repair Work on NOAA_Ships.pdf PDF
NOAA Standard Specification 000-2D Temporary-Services-Contractor-Facility.pdf PDF
NOAA Standard Specification AMC-233-1A Overhaul of Diesel Engines.pdf PDF
NOAA Standard Specification AMC-583-1B General Requirements for Life Raft Inspections.pdf PDF
NOAA Standard Specification AMC-635-2 Thermal Insulation for Compartments.pdf PDF
Show all 50

MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMC-505-2

APRIL 1988

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

ATLANTIC MARINE CENTER

STANDARD SPECIFICATION AMC-505-2

HYDROSTATIC PRESSURE TESTS

1. SCOPE. This specification contains the general requirements for performing hydrostatic pressure tests on pressure vessels and piping systems of NOAA ships.

2. REFERENCES.

None

3. REQUIREMENTS.

3.1 Prior to conducting a hydrostatic pressure test, meet with the COTR or other designated NOAA representative and discuss preparations, precautions, and procedures to be followed during the test.

3.2 The test pressure will normally be specified in the detail specification or other procurement document which requires the test. In the event the test pressure is not specified, the test pressure shall be 125 percent of the maximum allowable working pressure of the pressure vessel or system being tested.

3.3 Isolate, disconnect, and blank-off piping, equipment and

other components to avoid contaminating or subjecting them to the test pressure. Isolation shall be by blank flanges or similar means. Valves may be used if suitable for the required test pressure. After completing the test, return the systems, piping and other components to the as-found condition.

3.4 Remove relief valves from the pressure vessel or piping

system prior to the test. Test each relief valve for proper operation and set pressure. Reset to the pressure specified in the detail specification or other procurement document. If the pressure is not specified, reset the relief valves to a pressure equal to 105 percent of the system's or pressure vessel's maximum operating pressure. Install a new seal and metal tag on each relief valve. The tag shall be stamped with the test date and pressure setting. After completing the hydrostatic pressure tests, reinstall the relief valves.

3.5 When testing pressure vessels or piping designed for air or vapor service, provide additional temporary support as needed to support the additional weight of the water during the test.

3.6 Potable water shall be used as the test medium to test

piping and pressure vessels connected to the ship's potable water system. Fresh water shall be used as the test medium for all other pressure vessel and piping system tests. When filling the system or pressure vessel, insure that all air has been vented and that all air pockets have been eliminated before applying the test pressure.

3.7 When testing new welds or flanged joints, do not insulate, paint or otherwise cover the welds or joints until the test has been accepted by the COTR or other designated NOAA representative.

3.8 Test equipment shall contain the following:

3.8.1 A self-actuated and resetting relief valve set at a

pressure no greater than 110 percent of the test pressure.

3.8.2 A master pressure gage having a low range of 0 and a

high range which equals 125-200 percent of the test pressure.

The largest graduation of the master pressure gage shall be no more than 2 percent of the test pressure. The gage shall have been calibrated within the past 12 months and have a label attached which identifies the calibration date and facility. The gage shall be mounted where it can be easily seen by the pump operator and the COTR.

3.8.3 A water pump capable of slowly applying the required

pressure.

3.8.4 An isolation valve located between the pump and the

master pressure gage to allow the pump to be isolated while the gage indicates the pressure in the pressure vessel or system.

3.9 Hold the test pressure for 10 minutes. Then hold the

pressure an additional time as needed by the COTR to conduct an inspection for leaks and excessive stress.

3.10 After the hydrostatic test has been accepted, pump and

dispose of the water used for the test. The Contractor may drain the water to the ship's bilges only if the water will be subsequently pumped from the bilges and disposed of by the Contractor.

3.11 Stamp the date and test pressure on the test plate attached to each pressure vessel. If all available spaces on the test plate have been previously used, install a new test plate with the required test data stamped on it. The new test plate shall have sufficient spaces for at least 4 additional tests to be stamped.

4. QUALITY ASSURANCE.

4.1 The COTR or another designated NOAA representative shall

witness all hydrostatic tests and relief valve settings.

4.2 Provide to the COTR two copies of a test report containing the Contractor's name, test pressure, relief valve setting, and date for each test performed.

END OF SPECIFICATION