NOAA Standard Specification 0940.0.docx.pdf
PDF 76 KB Posted
- Attached to
- FY27 NOAA Ship Gordon Gunter Drydock REFERENCES Federal contract opportunity
- Solicitation number
- 1305M226Q0144REF
About this file
This is a NOAA Standard Specification (NOAA-STDSPEC-0940.0) for dock and sea trials performed on NOAA vessels, effective 2025.
The specification establishes requirements for two sequential trial phases. The dock trial must be conducted approximately one week before the vessel departs the contractor's facility for a duration of one working day, with the date requiring Contracting Officer's Representative (COR) approval. The contractor must submit a testing schedule to the COR at least 48 hours in advance, covering all equipment and systems on which work was performed. Ship's force personnel operate all equipment during dock trials, and all utilities except telephone service are transferred to the vessel. Testing must occur during normal working hours, and no contractor work is permitted during trials without prior COR approval. The contractor must provide a supervisor with access to personnel across all trades to oversee repairs and adjustments, and must deliver a dock trial report documenting all deficiencies and resolutions.
The sea trial follows satisfactory completion of dock trials and consists of one day of testing for repaired or newly installed equipment and machinery. The sea trial date must be approved by the COR, with a minimum 72-hour notice provided to all required attendees, including manufacturers' technical representatives. The trial agenda must run between eight and 24 hours and constitute an underway at sea condition (river and channel transits do not qualify). Prior to departure, the contractor must submit personnel information including names, citizenship, addresses, and emergency contact numbers. All dock trial discrepancies must be corrected before the sea trial begins, and all sea trial deficiencies must be resolved before the vessel departs the contractor's facility. The specification notes that ABS or USCG representatives are typically required for trials, and the contractor must ensure appropriate parking and vessel access for surveyors and inspectors.
View the file
Other files for this federal contract opportunity
Show all 50
FY27 NOAA Ship Gordon Gunter Drydock REFERENCES has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA-STDSPEC-0940.0
NOAA Standard Specification 0940.0
NOAA VESSELS DOCK AND SEA TRIALS
1.0 SCOPE
1.1 This item contains the requirements for dock and sea trials performed on NOAA vessels.
2.0 REFERENCES
2.1 None.
3.0 DEFINITIONS
3.1 None.
4.0 REQUIREMENTS
4.1 Conduct Dock Trial
4.1.1 Approximately one week before the ship is scheduled to leave the Contractor's facility, or at the CORs discretion; conduct one working day of dock trials. The date for the dock trials must be approved by the COR.
4.1.2 Submit a schedule to the COR at least 48 hours before dock trials for testing all equipment and systems on which the Contractor has performed work.
4.1.3 All equipment will be operated by ship's force personnel.
4.1.4 During the dock trials, all utilities, except telephone service, will be transferred to the ship.
4.1.5 Schedule testing during normal working hours.
4.1.6 No Contractor work shall be performed during dock trials without the prior approval of the COR.
4.1.7 Provide a supervisor with access to Contractor personnel in all trades to oversee the repair/adjustment of equipment repaired by the Contractor.
4.1.8 Provide a dock trial report including all deficiencies and their resolutions.
4.2 Conduct Sea Trial
4.2.1 Following satisfactory completion of dock trials, schedule and participate in a one-day sea trial to witness testing of all repaired or newly installed equipment and machinery. Coordinate the sea trial date with manufacturers' technical representatives as required, and provide at least 72 hours' notice to all required attendees.
4.2.2 The date for the sea trial must be approved by the COR. The sea trial agenda shall be set for no less than eight hours and no more than 24 hours. Prior to departure, submit a list of Contractor's/subcontractor's personnel who will ride the ship for sea trials and include Name, Citizenship, Address and telephone number of person to be notified in case of an emergency.
4.2.3 Correct all dock trial discrepancies prior to the sea trial.
4.2.4 The sea trial shall be an underway at sea condition for a duration of at least eight hours, departing from and returning to the contractor's facility. Transits in a river and/or channel, to and from the contractor's facility shall not constitute an underway at sea condition. The COR may elect to shorten the duration of the sea trial in consultation with the ship's command, dependent on the performance of all ship's equipment and systems to be operated and tested.
4.2.5 All equipment will be operated by ship's force.
4.2.6 No Contractor work will be allowed during the sea trial without the prior approval of the COR.
4.2.7 Provide a sea trial report including all deficiencies and their resolutions.
4.2.8 Correct all sea trial discrepancies before the ship leaves the Contractor's facility.
5.0 NOTES
5.1 In most cases, an ABS or USCG representative will be required to conduct dock or sea trials. Ensure the surveyor/inspector has parking and can embark and disembark the vessel.