NNM16568754R ATTACHMENT J-9
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)
ENGINEERING SERVICES AND SCIENCE CAPABILITY AUGMENTATION (ESSCA)
ATTACHMENT J-9
CONTRACT WORK BREAKDOWN STRUCTURE (CWBS)
CONTRACT WORK BREAKDOWN STRUCTURE (CWBS)
This attachment shall be used to define the requirements of the Contract Work Breakdown Structure (CWBS), otherwise known as the task order number.
The CWBS for the ESSCA contract is intentionally structured to be skill based. The skill based structure focuses the Contractor on management of the skills across the MSFC organizational structure. Depending on the diversity of scope an organization has been requested to support, the organization may choose to have: more than one task order per skill, one task order for a given skill with multiple sub-tasks, or both.
The CWBS provides a coding structure that will work for the technical management of the effort and also matches the coding structure used by the MSFC financial community for cost accounting.
The Contractor shall develop, deliver, and maintain DRD 1563MA-007, Financial Management Report (533M), and DRD 1563MA-006, Task Order Activity Reports. The CWBS and financial Data Requirements Descriptions (DRDs) are written to allow the Government to calculate Earned Value Management (EVM) from the delivered data.
The Contractor shall develop, deliver, and maintain the Contract Work Breakdown Structure (CWBS) Crosswalk in accordance with DRD 1563MA-005.
The Contractor shall utilize the following CWBS decimal coding structure that indicates a minimum of six levels for identification of the task and financial tracking information:
PSID
Sub-Task aaaa.bb.cc.dddd.eee.ff Level 1 Level 2 Level 3 Level 4 Level 5 Level 6
In the above task order number or CWBS, the first three levels of the CWBS make up the Performing Organization, Skill, and Task ID (PSID) (Levels 1-3). The last three levels make up the Sub-Task—the Funding Source, Funding Sub-Source, and Activity (Levels 4-6).
Level 1
Code: “aaaa” (4-digit Alpha/Numeric)
Description: Identifies the Performing Organization (e.g., Branch, Division, Office, etc.) where the TO originates. Potential codes are listed in table below with “XX” denoting the number for the Branch, Division, Office, etc. This information will be provided by the Government to the Contractor.
| Organizational Symbol |
| Organizational Name |
| EDXX |
| Engineering Directorate |
| EEXX |
| Chief Engineers Office |
| EMXX |
| Materials and Processes Laboratory |
| EOXX |
| Mission Operations Laboratory |
| ERXX |
| Propulsion Systems Department |
| ESXX |
| Space Systems Department |
| EVXX |
| Spacecraft and Vehicle Systems Department |
| XPXX |
| Space Launch System Program Office |
| CSXX |
| Office of Strategic Analysis & Communications |
| FPXX |
| Flight Programs & Partnership Office |
| HSXX |
| Office of Human Capital |
| ZPXX |
| Science & Technology Office |
| QDXX |
| Safety & Mission Assurance Office |
| SFXX |
| Michoud Assembly Facility |
Level 2
Code: “bb” (2-digit Numeric Only)
Description: Identifies the Skill (e.g., Avionics, Propulsion, Systems Engineering) required for performance of the TO. The Skill code number aligns with those listed in the table below and identified in Attachment J-1, Performance Work Statement (PWS). This information will be provided by the Government to the Contractor.
| 01 |
| Aero-Science Design, Development, and Test |
| 02 |
| Avionics & Electrical Systems Design, Analysis and Test |
| 03 |
| Flight Software and Ground Test Design, Analysis and Test |
| 04 |
| Materials Research, Analysis, Testing, Process, and Hardware Development |
| 05 |
| Operability Design, Analysis and Test |
| 06 |
| Optics Design, Analysis and Test |
| 07 |
| Propulsion Systems Design, Analysis, and Test |
| 08 |
| Scientific Disciplines Design, Analysis, and Test |
| 09 |
| Structural and Mechanical Design and Analysis |
| 10 |
| Systems Engineering and Management |
| 11 |
| Test Design and Operations |
| 12 |
| Thermal and Fluids Design, Analysis and Test |
Level 3
| Code: | “cc” (2-digit Numeric Only) |
| Description: | Identifies the Task ID (e.g., 01, 02, 03) number and provides the ability to have multiple TOs per the Performing Organization. The Performing Organization may require 1) multiple TOs for a given skill, 2) a TO with multiple sub-tasks, or 3) a combination of the two. This information will be provided by the Government to the Contractor. |
Level 4
| Code: | “dddd” (4-digit Alpha/Numeric) |
| Description: | Identifies an acronym or nomenclature for the Funding Source (e.g., SBOO – SLS Booster, ECLS – Environmental Control Life Support) that supplies the funds for the work to be performed on the TO. This information will be provided by the Government to the Contractor. |
Level 5
| Code: | “eee” (3-digit Alpha/Numeric) |
| Description: | If utilized, identifies an acronym or nomenclature for the Funding Sub-Source (e.g., RSS – Range Safety, IDL – SEI Level I) which will track to a lower level of the Funding Source for the work to be performed on the TO. If not needed, the identifier will utilize “000,” “XXX,” or some other means to keep the placeholder in the CWBS coding structure. This information will be provided by the Government to the Contractor. |
Level 6
Code: “ff” (2-digit Numeric Only)
| Description: | If utilized, identifies a particular Activity (e.g., 01, 02, 03) number to keep track of different activities or events on the TO. If not needed, the identifier will utilize “00,” “XX,” or some other means to keep the placeholder in the CWBS coding structure. This information will be provided by the Government to the Contractor. |
| CWBS EXAMPLES |
ER31.10.01.SSEI.IVG.01
| Level Description |
| (Performing Organization) |
| (Skill) |
| (Task ID) |
| (Funding Source) |
| (Funding Sub-Source) |
| (Activity) |
| CWBS Level |
| ER31 |
| 10 |
| 01 |
| SSEI |
| IVG |
| 01 |
| CWBS Level Description |
| Propulsion Systems Department Turbo Machinery Design & Development Branch |
| Systems Engineering and Management |
| Task #1 within the Performing Organization |
| Space Launch System (SLS) Systems Engineering and Integration |
| VM Guidance, Navigation, and Control |
| Activity Identifier #1 |
EV74.08.02.TEXA.RSS.00
| Level Description |
| (Performing Organization) |
| (Skill) |
| (Task ID) |
| (Funding Source) |
| (Funding Sub-Source) |
| (Activity) |
| CWBS Level |
| EV74 |
| 08 |
| 02 |
| TEXA |
| 000 |
| 00 |
| CWBS Level Description |
| Spacecraft and Vehicle Systems Department, Systems Analysis Branch |
| Scientific Disciplines Design, Analysis, and Test |
| Task #2 within the Performing Organization |
| Technical Excellence Award |
| Funding Sub-Source Identifier Not Used |
| Activity Identifier Not Used |