March 24, 2010 Solicitation No. NIHOF2010210 NIH Building No. 3 Construction Pre-Bid

Introduction – Aaron Crawford

This project is for 8(a) prime firms only. Teaming is acceptable however the 8(a) must be the lead. Other arrangements will be rejected.
The A/E is currently evaluating questions submitted. An amendment is pending.
There have been changes to the handout from the presentation. This document contains the actual (updated) presentation. The updated information will be posted.
The bid due date is April 12, 2010 at noon.
The cut-off date for questions is March 29, 2010 at noon.
The bid bond requirement is 20% of the bid or $3 Million, whichever is less.
The project is being done with ARRA funding. There is more documentation required than other projects. This is not grounds for a change order.
FAR clause 52-219-14 is hereby made part of this solicitation. The 8(a) prime must self perform a minimum of 15% of the work.
A performance bond is required per the solicitation.

Project Team Project Officer: Dexroy Chism Contract Officer: Aaron Crawford

NIH CQM: TBD

A/E: WFT Engineering GC Teaming Partner National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

Team introduction: Project officer; Contracting Officer; A/E.
This project is a good opportunity for an 8(a) company to do a good job and develop a good past performance record at NIH.

Project

Mandatory Qualifications Single available project bonding capacity of not less than $15 million ($15,000,000) 8(a) Small Business Classification 236220 - Commercial and Institutional Building Construction

National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

The above criteria are go/no go requirements.
Bidders must meet the above criteria in ordered to be considered further.

General Information NIH Bethesda Campus Historic - Built in 1938 Red Brick Georgian Style 49,243 GSF on 6 levels Occupancy Change Decommissioned in 2002

National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

The decommissioning has been done back to bare walls and included the removal of the walls, flooring, mechanical and electrical systems.
There is still lead at the site which has to be removed as part of this project.

Project Description Scope Overview Provide Modern Office Space Open and Closed Offices Furniture Systems Supplemental Spaces Infrastructure Upgrades Commissioning LEED Silver BIM - Revit

National Institutes of Health Building No. 3 – Pre-Bid Meeting

Site/Civil
Architecture /Interiors
Mechanical/Plumbing
Electrical
Life Safety / Security
Hazmat
ADA
ARRA Documentation
The requirement for BIM has been removed from the project.
The site civil work includes: steam; chilled water; sewer, telecom and other utility replacements back at least to the first manhole.
The completion of the ARRA documentation must be as per the solicitation.
The removal of the hazmat – lead – is part of this contract.
Bid Amendment is pending.

Vicinity Constraints Site Location Security Entering Campus – CVIF Dynamic 24/7 Campus Sensitive Surroundings Noise, Dirt, Deliveries National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

The project is located in the heart of campus and is surrounded by sensitive administration buildings and labs with ongoing research.
There is no parking at the site.
Contractors must enter the site through either the Commercial Vehicle Inspection Faculty (CVIF) or the main gateway. There is minimal paid parking at the gateway.
All personnel will need to get badged to enter the site.
All bids will need to take parking and security into account. Compliance with the dirt, noise and delivery restrictions at NIH will not be grounds for delay.

Site Constraints Construction Fence Access control Trailers (opt) Lay Down Area Utility work Nearby Buildings National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

There will need to be a 6’ tall security fence around the site as shown on the plans. This is not the LOD. The LOD will be the area of the site / civil work.
The circular drive in front of building #1, 2 and 3 must be keep clear at all times for bus traffic.
This project will share an access road on the SW corner with building 8. The drive will need to be kept clear and later milled/resurfaced after the work is competed.
There is no parking at the site.
The trailer locations on the site are for possible demonstration purposes only and not meant to imply the installation of trailer at the site. There will not be any lay down areas outside the building. The lay-down area will need to be inside the building.
There are significant site utility upgrades required. This work on the site will need to be phased. The area of utility work will need to be protected and identified as the LOD.
The government trailer is approved and is to be provide as shown.
The project is not subject to JAACO requirements.
There will be a new handicapped ramp on the NW corner of the building.
Much of the existing slate roof has been repaired. This contract will need to warranty the entire roof at the completion of the project.
The asphalt roof on the lower levels will need to be replaced as part of this contract.
There is lead abatement and regrouting required at the exterior of the building.
The windows will be blast resistant. This is indicated in the documents and similar to building #6.
No parking in shared drive line.
Building #8 gets constant deliveries similar to the truck shown above.
There will be lead abatement on the top floor.
Many of the existing holes have been patched but they will need to be made safe under this contract.
There is lead paint that will need to be removed in the stair tower.

Basement Level Mechanical Room – NW Corner Electrical Room – SW Corner National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

Large mechanical room in the NW corridor.
Telecom, electrical service entrance on the SW corner.
There are vertical utility risers throughout the building.

First Floor

Toilet rooms are typically stacked.
The layouts shown represent the proposed system furniture layouts.

Second Floor

Third Floor

Fourth Floor

Fifth Floor

Summary of Services All Plans and Specs 100% Complete in 511 days PM Management Software Electronic Reporting NIH/DRM and FDM Detailed Cost Loaded Schedule

National Institutes of Health Building No. 3 – Pre-Bid Meeting

Utility Coordination
Site Restoration
ARRA Reporting
LEED Submissions
The project must be totally complete in 511 days including, but not limited to:
Commissioning
Training
O&M’s
As-builts
Keys
Site repair (sod)
LEED
Driveway repair
Punch list
Substantial completion must be within the 511 days and shown in proposal schedule.
Liquidated damages are $4500 per day / no limit.
The project schedule must include 21 days for utility shutdown requests. Shut downs requested are not guaranteed. No change order will be granted for inability to get shut-downs.
Contractor’s can’t shut off utilities. Utility shut downs must be by NIH.
A LEED score card will be provided as part of a pending amendment.
The electronic reporting will include RFI’s, submittals etc. per the documents.
The site will need to be repaired including mill the drive and providing sod.

Evaluation Criteria Technical "Best Value" procurement, which will permit the Government to confirm the Offeror's understanding of the requirements and challenges of the Project, evaluate the Offerors' capability to meet those challenges, and award to the Offeror whose offer presents the greatest overall value to the Government, cost and other factors considered.

Factor 1: Offeror's Past performance Evaluation by the Government Each Offeror will be evaluated on its performance under existing and prior contracts for similar services

Factor 2: Offeror's Relevant Experience The Offeror actively performed general construction services substantially similar to the size and scope of the Building 3 renovation National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

Bidders need to refer to the solicitation for the exact evaluation criteria.
The bidders must have met the prior go/no go criteria to get to these evaluation criteria.
NIH may or may not call the references submitted. NIH may unilaterally contact other references.
The relevant experience should include 1 to 3 projects.
NIH will accept both corporate and individual surety bonding for the prime 8(a).

Evaluation Criteria Technical Factor 3: Experience of Key Personnel Professional construction management experience, education and training for their particular roles / discipline on similar types construction projects

Factor 4: Offeror's Management Plan and Project Schedule Offeror's Management Plan and Project Schedule prepared SPECIFICALLY for the Building 3 renovation project in accordance with the construction documents

Factor 5: Knowledge of and business relationship with the local marketand trades
Offeror's proposed sub-contractors by CSI division

National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism

Management plan needs to have a clear line of authority as to: process for decisions made and roles played.
JV and mentor /protégé arrangements must be submitted and include the agreement and what has been sent to and approved by SBA. Final contract award pending on approval of SBA on teaming arrangement.
For the purpose of the schedule assume May 1, 2010 is the contract award date.
Schedule must show the logic as appropriate for this project.
The schedule for the bid does not have to be cost loaded.
The government can’t require the use of primavera for the bid.
Must include the subs intended for use on this job.
Evaluation criteria based on the RFP.

Clarifications 365 working days in the specification is the same as 511 calendar in the solicitation.

Project to be complete, not just substantially complete, in 511 days.

Pending addendum will address BIM requirements.

Pending addendum will provide a LEED score card.

Schedule for evaluation factor 4 to be as per section 01320 2.1.D without loaded cost schedule and the QC plan.

$2,000,000 in the bid form is for owners cont.

National Institutes of Health Building No. 3 – Pre-Bid Meeting

Presentation – Dexroy Chism The owner contingency is listed on section B. This money is not for the contractor and is not part of the amount required to be bonded. This money is for the sole use of NIH, on this contract, for new scope items.

Bid Questions Question must be submitted to the Contracting Officer Questions must contain:

Date Submitted Plan Sheet Specification Section Question Description

Possible Award Schedule

Solicitation Posted:March 11, 2010
Pre-Bid Walk-thruMarch 24, 2010
Question Cut offMarch 29, 2010
Response Date:April 12, 2010
NIH Review / Negotiations:6 Weeks
Contract Award:TBD
Construction Start:10 Days after award
100% Complete:511 Days

Questions

Presentation – Dexroy Chism

Bidders can visit the site at any time however they are required to register in building 13/ Room 210 and understand all NIH required safety procedures / requirements.
Additional site visits must have at least two (2) people.
Progressive collapse is not required for this project. Blast requirements (i.e. windows and loading dock) are indicated in the documents.
This project is negotiated and not a firm fixed price bid and will require support of the pricing submitted.
NIH to review the solicitation to see if there are duplicate bid/ pricing forms.

Other files

File Type Posted
Buildign 3 -- Questions and Answers —
SF 30 -- Amendment 000009.pdf PDF
Section B Table B2 Revised.pdf PDF
Buildign 3 -- Questions and Answers —
SF 30 -- Amendment 000008.pdf PDF
Section B —
SF 30 —
Buildign 3 -- Questions and Answers —
16442-Panelboards.pdf PDF
10410 - EMERGENCY BUILDING ACCESS CABINETS.pdf PDF
SK-1.pdf PDF
SF 30 —
SF 30 —
01770 closeout procedures.pdf PDF
Buildign 3 -- Questions and Answers —
01781 project record documents.pdf PDF
SF 30 —
Article G.3 —
Section C —
Article H.14 —
08871 - privacy film.pdf PDF
Section B —
SF 30 —
8(a) RFP Cover Page.pdf PDF
Buildign 3 -- Questions and Answers —
NIH Bldg 3 - LEED NCv2 2 - Scorecard 02-23-10 - MW —
08630 - METAL-FRAMED SKYLIGHTS.PDF PDF
Schedule of Charges for Basic Award Period.xls XLS spreadsheet
SF 30 —
Buildign 3 -- Questions and Answers —
Section J —
Attachment 11 -- Self-performed_Work_Calculaton.pdf PDF
Attachment 9 -- MD080056_dvb.pdf PDF
Pre-bid sign in.pdf PDF
SF 30 —
Solicitation Number NIHOF2010210 —
Solicitation Number NIHOF2010210 —
Section J Attachments.zip ZIP file
Specifications.zip ZIP file
Drawings.zip ZIP file
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .