Statement of Work Summary: 21 CS Communications Cabinet Installation

This is a Statement of Work (SOW) for the U.S. Space Force's 21st Communications Squadron detailing cabinet installation services at Peterson Space Force Base, Colorado. The project encompasses the removal of two existing communications cabinets (208 and 207) and the installation of four new GL840ES-2442-B-MS cabinets in Building 1038's tech control facility located at 175 E Stewart Avenue, Peterson SFB, CO 80914.

The work is divided into two scopes. Scope A involves replacing two existing cabinets in their current location, requiring site preparation with photography and cable labeling, temporary cable tray support fabrication, disconnection of four horizontal PDUs, removal of existing cabinets to a designated staging area, positioning and anchoring new cabinets to the concrete floor, re-alignment of Unistrut cable trays, installation of Eaton SRGROUND grounding systems in each new cabinet, and final inspection and cleanup. Scope B entails installing two additional new cabinets at the row-end location on the concrete floor, including site preparation to mark and remove decorative tile at anchor points, cabinet positioning and alignment, floor anchoring, installation of Eaton SRGROUND grounding systems, and final inspection. All work must be completed during normal business hours (Monday through Friday, 7:00 a.m. to 3:00 p.m. local time, excluding holidays). The SOW assumes that 21 CS will provide necessary materials, personnel support, facility access, badging, and that no security clearance, change control procedures, or aerial work platforms are required.

View the file

Other files

File Type Posted
Sources Sought - NGG Server Cabinet Replacement.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

21 CS – Communications Cabinet Installation

Table of Contents

1 Project Scope/Pricing Summary

1.1 Project Tasks

1.1.1 Scope A

1.1.2 Scope B

1.2 Project Sites

2 Assumptions

1 Project Scope/Pricing Summary Provide services for U.S. SPACE FORCE for the removal of two existing cabinets and the installation of four new cabinets that will be provided the 21 CS in Bldg. 1038 tech control facility.

1.1 Project Tasks

1.1.1 Scope A

Remove existing cabinets 208 and 207 and install two new cabinets in the same location.

− Conduct Site prep photograph existing state, label any cables on tray, confirm temp support anchor method

− Fabricate and install temporary support legs (Unistrut + hardware) to carry cable tray load during swap

− Disconnect and remove four horizontal PDUs (two per cabinet) − Detach Unistrut from front and rear top rails of both existing cabinets;

transfer load to temp support − Removed cabinets shall be returned to 21 CS-designated staging area within server room − Position two new GL840ES-2442-B-MS cabinets, align to row − Anchor new cabinets to concrete floor (drill through decorative tile, concrete anchor) − Re-drill/align Unistrut bolt pattern on new cabinet top rails; reattach

Unistrut, reinstall threaded posts and dual cable tray layers − Remove temporary support structure − Install Eaton SRGROUND in each new cabinet two; connect existing ground lug cable to bus bar − Conduct Final inspection, and cleanup

1546866455A Highlight

1.1.2 Scope B

Black Cabinet New Install: Install two new cabinets on concrete floor at row end, including floor anchoring and ground-out − Contractor Shall:

Conduct Site prep mark floor anchor locations, score and remove decorative tile at anchor points Position two new GL840ES-2442-B-MS cabinets at concrete floor row-end location, align to row Anchor both cabinets to concrete floor (drill and set concrete anchors, front and rear feet) Install Eaton SRGROUND in each cabinet two; connect existing ground lug cable to bus bar Conduct Final inspection and cleanup

1.2 Project Sites

Services performed as part of this SOW will occur onsite and/or remotely in support of the following location(s):

Bldg 1038 175 E Stewart Ave Peterson SFB, CO 80914

2 Assumptions 21 CS shall designate a single Point of Contact to contractor where communications may be addressed, and who has the authority to act on behalf of 21 CS with respect to contractor performance; such contact shall be available during normal hours of business (Monday through Friday, 7:00am to 3:00pm local time, excluding holidays)

21 CS shall make available the escort, program management, technical and security personnel required to permit contractor performance in accordance with contract requirements and this SOW

Unless otherwise specified in the contract, contractor performance shall be completed during normal business hours between 7:00am and 3:00pm project site local time, Monday through Friday, excluding observed holidays

21CS shall provide contractor access to all 21 CS sites, facilities, and equipment applicable to contract requirements, as required to permit contractor performance in accordance with this SOW

This SOW has been developed based on the assumption that there are no scheduled cutover/change windows or change control requirements. If change control or scheduled cutovers are required, this will be managed through the Change Order process

21 CS will provide badging/keys for resources to access work areas.

21 CS will assist in the processing of any required facility specific permits.

All 21 CS provided materials necessary to complete this project are on-site and in useable condition.

No security clearance is required.

No aerial work platforms are required.