About this file

This document package contains a deliverable items list and schedule (DILS) for the Wide Field Infrared Survey Telescope (WFIRST) High Gain Antenna System (HGAS) jitter damper, as well as a sources sought notice for the WFIRST jitter damper.

The DILS outlines 46 deliverables required from the contractor to the National Aeronautics and Space Administration (NASA) Goddard Space Flight Center (GSFC), including design documents, analysis reports, test plans and reports, data packages, hardware, and meetings. Key deliverables include a kickoff meeting two weeks after award, design reviews three and seven months after award, one engineering test unit and one flight unit due 12 months after award, and an option for an additional flight unit. The deliverables have defined due dates and specify whether NASA approval, review, or information is required for each item.

The sources sought notice requests capability statements from businesses to design, analyze, manufacture, and test the WFIRST HGAS jitter damper. Interested parties must indicate prime contractor or subcontractor capabilities and summarize relevant experience by January 23, 2020. NASA intends to release a request for proposal to determine the appropriate level of small business goals for this requirement, which includes one engineering test unit, one flight unit, and an option for an additional flight unit.

View the file

Other files for this federal contract opportunity

Other files attached to Sources Sought for WFIRST Jitter Damper, newest first.
File Type Posted
WFIRST-MECH-SPEC-0128_DRAFT.pdf PDF
WFIRST-MECH-SOW-0036_DRAFT.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Effective Date: <Date>

Expiration Date: <Date> [as required]

National Aeronautics and Space Administration

Goddard Space Flight Center Greenbelt, Maryland

WFIRST-MECH-LIST-0078, Revision [-, A]

Wide Field Infrared Survey Telescope (WFIRST), Code 448

High Gain Antenna System (HGAS)

Jitter Damper

Deliverable Items List and Schedule

(DILS)

DRAFT

HGAS Jitter Damper DILS WFIRST-MECH-LIST-0078, Revision Number Draft

Check FPD BCI Document Management Guidance to verify that this is the correct version prior to use

400-FORM-0002 (4/16/2014)

HGAS Jitter Damper

Deliverable Items List and Schedule

(DILS)

Review/Signature/Approval Page

Prepared by: Lia Sacks, Code 591

Approved by:

Electronic Approval available on-line in the WFIRST CM Tool https://fpdspi.gsfc.nasa.gov/sites/fpdat/BCI/SitePages/Document%20Management%20Guidance ii

Preface

This document is a Wide Field Infrared Survey Telescope (WFIRST)

Configuration Management (CM)-controlled document. Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee.

Proposed changes shall be submitted to the WFIRST CM Office (CMO), along with supportive material justifying the proposed change.

In this document, a requirement is identified by “shall,” a good practice by “should,” permission by “may” or “can,” expectation by “will,” and descriptive material by “is.”

Questions or comments concerning this document should be addressed to:

WFIRST Configuration Management Office

Mail Stop 448

Goddard Space Flight Center

Greenbelt, Maryland 20771 iii

Change History Log

Revision Effective Date Description of Changes

(Reference the CCR & CCB/ERB Approval Date) iv

Table of TBDs/TBRs/TBSs [optional]

Item No. Location Summary Individual/

Organization

Actionee

Due Date v

Table of Contents

1 INTRODUCTION

1.1 Purpose

1.2 Scope

1.3 Related Documentation

1.3.1 Applicable Documents [and Forms]

1.3.2 Reference Documents

2 DELIVERABLES

APPENDIX A ABBREVIATIONS AND ACRONYMS

List of Tables

Table 1. Data Delivery Documentation and Schedule

1 INTRODUCTION

1.1 Purpose

The Wide Field InfraRed Survey Telescope (WFIRST) is a mission responding to the 2010

National Research Council New Worlds, New Horizons (NWNH) Astronomy and Astrophysics

Decadal Survey top priority recommendation in the large space mission category. The science program includes two dedicated investigations to tackle outstanding questions in dark energy research and exoplanet exploration, and includes a substantial General Observer program to enable targeted investigations of astrophysical phenomena to advance other goals from the

Decadal Survey. A coronagraph instrument is included in the payload for purposes of advancing the present state of the art of coronagraph technology. This document is the Wide Field Infrared

Survey Telescope (WFIRST) High Gain Antenna System (HGAS) jitter damper Deliverable

Items List and Schedule (DILS).

1.2 Scope

This document lists all of the deliverables for HGAS jitter damper, the SOW paragraph number where the deliverable is described further, the type of response required from NASA GSFC, the format of the deliverable, and the schedule for delivery.

1.3 Related Documentation

The latest versions of all documents below should be used. WFIRST documents can be obtained in the WFIRST CM Tool.

1.3.1 Applicable Documents [and Forms]

The following documents are referenced within this document and are directly applicable or contain policies or other directive matters that are binding for the contents of this document. In the event of conflict between an Applicable Document and the content of this document, the

WFIRST Project Configuration Change Board has the final authority for conflict resolution.

Document Number Title

WFIRST-MECH-SOW-

WFIRST High Gain Antenna System Jitter Damper Statement of

Work (SOW)

1.3.2 Reference Documents

The following documents are referenced herein and amplify or clarify the information presented in this document. These documents are not binding on the content of this document.

Document Number Title

WFIRST-MECH-

SPEC-0128

WFIRST High Gain Antenna System Jitter Damper Specification

2 DELIVERABLES

Description: This provides the Title of the deliverable item.

Reference: This provides the reference back to the pertinent document calling out the deliverable.

Category:

A = Approval – Items in this category require approval from the National Aeronautics and Space Administration (NASA)/Goddard Space Flight Center (GSFC) Contracting

Officer (CO). In general, documents shall be provided in contractor format as long as required content, as specified in the Wide Field Infrared Survey Telescope (WFIRST)

HGAS Jitter Damper Statement of Work (WFIRST-MECH-SOW-0036), is addressed.

The NASA GSFC CO reserves the time-limited right of disapproval for each submission.

The time-limited period is 30 working days from receipt of documents.

R= Review – Items in this category do not require formal NASA GSFC CO approval, but will be reviewed by the GSFC or its designated representatives in order to determine contractor effectiveness in meeting contract objectives. When Government review reveals inadequacies, the contractor may be requested to correct the inadequacies. GSFC will review and comment within 20 working days of receipt.

I = Information – Items in this category are informal and are for information only.

Format: This provides the format for the deliverable. For documents, the following format applies:

E = Electronic – Provide submittal in electronic format to the COR, and Contracting

Officer. The vendor and COR shall jointly determine the type of electronic format (e.g., Word, Excel, PowerPoint, PDF, MATLAB) acceptable for each deliverable.

Table 1. Data Delivery Documentation and Schedule

Item

Description Reference Category Category/Format

1 SOW Compliance Matrix SOW 1.2 With Proposal Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

2 Monthly Status Report SOW 2.2 Fourteen (14) calendar days following the month being reported.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

For Information Purposes.

3 Milestone List SOW 2.2 With Proposal

4 Notifications SOW 2.3 Seven (7) calendar days in advance of all mandatory hardware inspections, test activities, TIM’s, and deliveries.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

5 Kick Off Meeting SOW 2.4.1 Fourteen (14) calendar days after contract award

In person at Contractor

Facility.

Review Required.

6 Kick Off Meeting Package SOW 2.4.1 Three (3) working days before the meeting

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required

7 Design Conformance Review

(DCR)

SOW 2.4.2 Three (3) months after

Award of Contract

In person at Contractor

Facility.

Review Required.

8 Design Conformance Review

Presentation Package

SOW 2.4.2 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

9 Design Conformance Review

Report

SOW 2.4.2 Fourteen (14) calendar days after completion of DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

10 Pre-Environmental Review

(PER)

SOW 2.4.3 Seven (7) calendar days before start of environmental testing on first Flight Unit

In person at Contractor

Facility.

Review Required.

Description Reference Category Category/Format

11 Pre-Environmental Review

Presentation

SOW 2.4.3 At PER Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

12 Flight Unit(s) Pre-Ship

Review (PSR)

SOW 2.4.4 Seven (7) calendar days prior to delivery of each

Flight Unit

In person at Contractor

Facility.

Approval Required.

13 Flight Unit(s) Pre-Ship

Review Presentation Package

SOW 2.4.4 At PSR Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

14 Flight Unit(s) End Item Data

Package(s) (EIDP)

SOW

2.4.4, 6.7.3,6.7.6, 6.8.2

With each delivered Flight

Unit and available at PSR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

15 TIM SOW 2.4.5 As Negotiated In person at Contractor

Facility.

Review Required.

16 Interface Control Document(s) SOW 3.1 Preliminary at Kick-off

Meeting

Final at fourteen (14) calendar days before

DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

17 Drawing Package SOW 3.2 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

18 Computer Models SOW 3.3 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

For Information Purposes.

19 Structural Analysis Report SOW 3.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

20 Structural Finite Element

Model

SOW 3.5 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Description Reference Category Category/Format

Review Required.

21 Thermal Analysis Report SOW 3.6 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

22 Thermal Model &

Documentation

SOW 3.7 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

24 Error Analysis Report SOW 3.9 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

27 Reserved

28 Verification Plan (Including

Verification Matrix)

SOW 5.1,

6.5.1

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

29 Individual Verification Test

Plan(s) (if needed)

SOW 5.1 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

30 Verification Test Procedure(s) SOW 5.2 Twenty-eight (28) calendar days before start of testing and as changes occur.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

31 Verification Test Report(s) SOW 5.3 At PSR Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

32 Mission Assurance

Implementation Plan / Quality

Assurance Plan

SOW 6.1 Twenty-eight (28) calendar days after contract award

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

33 Class I Configuration

Management (CM) Changes

SOW 6.2 Seven (7) calendar days after Contractor CM review

Electronic – Provide submittal in electronic format to the COR and

Description Reference Category Category/Format

Approval Required.

34 Class II CM Changes SOW 6.2 Seven (7) calendar days after Contractor CM review

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

See

As-Built Materials List SOW 6.7.3 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

38 Materials Usage Agreement SOW 6.7.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

Materials Certificate of

Compliance

SOW 6.8.6 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

39 Additive Manufacturing &

Qualification Plan SOW

6.7.5.2.2

Thirty (30) calendar days before hardware fabrication

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

40 Fastener Integrity Control

Plan SOW

6.7.5.4.1

Thirty (30) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

41 List of Critical Fasteners

SOW

6.7.5.4.1

Thirty (30) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

Cleanliness Certification

Report

SOW 6.8.2 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

42 Thermal Vacuum Bakeout

Plan

SOW 6.8.3 Twenty-eight (28) calendar days prior to beginning of

Thermal Vacuum Bakeout

Tests

Electronic – Provide submittal in electronic format to the COR and

Approval Required.

Description Reference Category Category/Format

43 Thermal Vacuum Bakeout

Test Results (if not part of

Thermal Vacuum Report)

SOW 6.8.3 Fourteen (14) calendar days after completion of Thermal

Vacuum Bakeout Tests

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

44 HGAS Jitter Damper Flight

Unit(s)

Qty: 1

SOW 4.2 12 months after contract award (ACA)

As specified in Clause

GSFC 52.247-94

Approval Required.

45 HGAS Jitter Damper

Engineering Test Unit

SOW 4.2 12 months after contract award (ACA)

As specified in Clause

GSFC 52.247-94

Approval Required.

46 Optional HGAS Jitter Damper

Flight Unit(s)

Qty: 1

SOW 4.2 12 months after contract award (ACA)

As specified in Clause

GSFC 52.247-94

Approval Required

Appendix A Abbreviations and Acronyms

Abbreviation/

Acronym

DEFINITION

HGAS Jitter

Damper

High Gain Antenna System Jitter Damper

ACA After contract award

CIR Configuration Initial Release

CCB Configuration Control Board

CCR Configuration Change Request

CM Configuration Management

CMO Configuration Management Office

CO Contracting Officer

COR Contracting Officer's Representative

DCR Design Conformance Review

DILS Deliverable Items List and Schedule

EEE Electrical, Electronic, and Electromechanical

EIDP End Item Data Package(s)

FMEA Failure Modes and Effects Analysis

FMECA Failure Modes and Effects Criticality Analysis

GIDEP Government Industry Data Exchange Program

GSE Ground Support Equipment

GSFC Goddard Space Flight Center

I Information

INST Instrument

NASA National Aeronautics and Space Administration

NDE Nondestructive Evaluation

PDL Product Design Lead

PEM Plastic Encapsulated Microcircuit

PER Pre-Environmental Review

PSR Pre-Ship Review

PWB Printed Wiring Board

R Review

SOW Statement of Work

TBD To Be Determined

TBR To Be Resolved

TIM Technical Interchange Meeting

WFIRST Wide Field Infrared Survey Telescope

Yrs years

File details come from the government source that posted it. Updated .