This document is a justification for other than full and open competition for an Alternate Care Facility (ACF) at Van Cortlandt Park in New York. The U.S. Army Corps of Engineers Engineering District New York awarded contract W912DS20C0012 to Parsons Corporation on an urgent and compelling basis on April 3, 2020 for $40 million. The contract provided design-build construction services to retrofit space at Van Cortlandt Park into an ACF to serve non-acute and critical care COVID-19 patients. The justification cites the national emergency declaration and need to increase hospital capacity as the basis for the unusual and compelling urgency exception to full and open competition.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
New York ACF Van Cortlandt Park
Control # NAN 20-009
AFTER-THE-FACT JUSTIFICATION REVIEW DOCUMENT
OTHER THAN FULL AND OPEN COMPETITION
PROJECT/EQUIPMENT: Limited Sources Phase II COVID19 ACF CONTROL NO: NAN 20-009
AUTHORITY: 10 U.S.C. 2304 (C) (2) AMOUNT: $40,000,000
PREPARED BY:
CONTRACT SPECIALIST
NAME: Alyssa Tornatore
PHONE: 917-790-8389
DATE:
CONTRACTING OFFICER
NAME: Nicholas Emanuel
PHONE: 917-790-8069
TECHNICAL
NAME: Matthew Emigholz
PHONE: 917-790-8248
REQUIREMENTS
SIGNATURES ARE REQUIRED BELOW:
I have reviewed this J&A and find the justification adequate to support other than full and open competition.
DISTRICT SMALL BUSINESS
SPECIALIST
SIGNATURE:
NAME: Justin Helfman
PHONE: 917-790-8004
PROJECT MANAGER
DISTRICT COUNSEL
NAME: Lorraine Lee
PHONE: 917-790-8055
DISTRICT CONTRACTING
CHIEF
NAME: Francis Cashman
PHONE: 917 790-8173
SCO/HQ COUNSEL
NAME: Tristan Brown
PHONE: 202-761-1259
SCO ATLANTA/ALTERNATE
COMMAND ADVOCATE FOR
COMPETITION
NAME: Laura Eichhorn
PHONE: 404-562-5051
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
Typewritten Text 21 April 2020
S0CT9LJE
27 April 2020
After-the-Fact Justification and Approval for
Other than Full and Open Competition
1. CONTRACTING AGENCY: U.S. Army Corps of Engineers (USACE), New York District
(CENAN), Contracting Division, New York, NY
2. DESCRIPTION OF ACTION: In support of Presidential National Emergency Declaration
Concerning the Novel Coronavirus Disease (COVID-19) Outbreak, dated 13 March 2020, after-the-fact approval is requested for a Justification and Approval (J&A) for a two-phase design-build construction, firm fixed price (FFP) Letter Contract awarded to Parsons Corporation, 5875
Trinity Pkwy Suite 300, Centreville, VA 20120-1971, on an other than full and open competition/sole-source basis under circumstances of Unusual and Compelling Urgency. The action was awarded as an Undefinitized Contract Action (UCA) and will be definitized as a FFP
“C-type” contract. The type of funds utilized are Federal Emergency Management
Administration (FEMA) Disaster Relief funds. There were no options identified for the contract.
3. DESCRIPTION OF SUPPLIES/SERVICES: The purpose of this contract was to provide design-build construction services in accordance with the Presidential National Emergency
Declaration. Work effort consisted of the design and construction at Van Cortlandt Park to retrofit the selected space into an Alternate Care Facility (ACF) to serve patients ranging from
Non-Acute Non-COVID patients up to critical care COVID patients. This work is providing an
ACF meeting basic healthcare functions with an emphasis on patient isolation, infection control, fire protection, and life safety. This Justification is for Atlernate Care Facilities (ACFs) Van
Cortlandt Park in New York. The estimated total value of the contract awarded under this J&A is $40,000,000, based on the not-to-exceed (NTE) amount for the awarded UCA. This amount is based upon the Government’s estimate for the project and the NTE for the awarded contract. The period of performance for the design-build contract was anticipated to be 3 weeks in total and performance began immediately upon award of the UCA in order to meet this aggressive schedule.
4. AUTHORITY CITED: 10 U.S.C. § 2304(c)(2), as implemented by Federal
Acquisition Regulation (FAR) 6.302-2, Unusual and Compelling Urgency.
5. REASON FOR AUTHORITY CITED: Consistent with Defense Federal Acquisition
Regulation Supplement (DFARS) Procedures, Guidance and Information (PGI) 206.302-
2(b), “use of this [unusual and compelling urgency] authority may be appropriate . . . [for] construction needed at once because of fire, flood, explosion, or other disaster.” In support of the
Presidential National Emergency Declaration, the agency’s need for this construction was of such an unusual and compelling urgency that the Government would have been seriously injured unless the agency was permitted to sole-source a contract to the single firm selected from the group of firms that were down-selected after Phase I of this two-phase design-build acquisition.
Background/Selection of Sole Source Contractor: As discussed in Paragraph 8, Market
Research, CENAN conducted this procurement in accordance with the Two-Phase Design-Build
Selection Procedures in FAR 36.3. To that end, CENAN issued a limited competition Phase I design-build request for proposals to a total of ten firms (supported by a J&A approved by the
S0CT9LJE
Typewritten Text The requirement was subsequently canceled and performance was suspended on 14 April.
S0CT9LJE
Negotiations for the termination settlement are still ongoing.
Senior Procurement Executive, Control No. CENAN 20-003, 26 March 2020), and adequate competition was obtained in Phase I. The Government conducted its Phase I evaluation and down-selected to eight firms that were determined to be the most highly qualified firms.
CENAN continued sole-source negotiations as part of Phase II of the design-build acquisition only with Parsons Corporation for the particular requirements of New York State Alternative
Care Facilities (ACFs) – Van Cortlandt Park.
Parsons Corporation was determined to be the highest qualified firm for the New York State
Alternative Care Facilities (ACFs) – Van Cortlandt Park because of their demonstrated qualifications. Parsons Corporation submitted several projects in their proposal of which multiple ones were considered very relevant to this requirement. Parsons Corporation’s past performance rating was based on strengths that resulted in a high expectation that the Offeror will successfully perform the required effort. Parsons also is well equipped to respond to emergency situations as demonstrated by their past performance submission for this contract. These qualifications made them uniquely suited for New York State Alternative Care Facilities (ACFs) – Van Cortlandt
Park because Parsons has demonstrated experience building hospital facilities in metropolitan areas similar to Van Cortlandt Park. Parsons has a substantial presence in New York capable to commence the work immediately. Further, Parsons Corporation emphasized their large organization with built-in supply chain in the local area.
Justification: The President declared a national emergency on 13 March 2020. FEMA assigned USACE to support Emergency Support Function (ESF) #3 “Public Works and
Engineering.” On 22 March 2020, FEMA assigned the CENAN a mission assignment that included the above referenced ACF work. The nature of this work was of such an unusual and compelling urgency that work had to commence immediately. As described by the President, “[t]he spread of COVID-19 within our Nation’s communities threatens to strain our Nation’s healthcare systems. As of March 12, 2020, 1,645 people from 47 States have been infected with the virus that causes COVID-19. It is incumbent on hospitals and medical facilities throughout the country to assess their preparedness posture and be prepared to surge capacity and capability.”
USACE has been requested to provide design and construction support to increase the capacity of our Nation’s healthcare system and needed to undertake design and construction as quickly as possible, to provide the necessary surge capacity.
Without limiting the number of sources from which the Government solicited a Phase II proposal to a single firm, the Government would have been unable to undertake construction quickly enough to meet the immediate need for additional ACF capacity in this area and would not have met the necessary delivery schedule to provide additional capacity as close to the projected surge date as possible. A traditional design-build project acquired in accordance with the requirement for full and open competition under the Competition in Contracting Act (CICA) could take upwards of 6-9 months to award based upon historical averages of contracts of this dollar amount.
The time savings achieved through use of other than full and open competition was 6-9 months, as this entire two phase process took little more than three days. This time savings was critical in order for construction to begin as quickly as possible, supporting the unusual and compelling nature of the urgency of this procurement and the national emergency.
Alternatives: CENAN examined several alternatives for fulfilling these requirements, but no other alternative would have allowed for performance to begin immediately. The only viable alternative was to select a single firm from the group of firms that were down-selected after Phase I of this two-phase design-build acquisition with whom the Government negotiated, in conjunction with utilizing a UCA or letter contract to allow the contractor to begin performance immediately and definitize the contract at a later date. A Determination and Findings to award an UCA that will ultimately be definitized as a FFP “C-type” contract was approved by the Senior Contracting
Official on 26 March 2020.
Impact: As determined by the President, the current COVID-19 outbreak presents a public health crisis and constitutes a national emergency. Because of the magnitude and gravity of the emergency, the President declared that hospitals must be prepared to surge capacity and capability, and that additional measures are needed to successfully contain and combat the virus in the United States. USACE is the only entity with the capacity to build the infrastructure needed to support response to this emergency, but could only do so if certain exceptions to full and open competition were implemented. Failure to select a single firm from the group of firms down-selected after Phase 1 of this two-phase design-build acquisition, utilize a letter contract, undertake construction immediately, and complete within 3 weeks, would have resulted in delays in design and construction of medical infrastructure required to adequately respond to the
COVID-19 outbreak and would have had severe adverse impacts on the safety and the public health of the United States. This J&A enabled CENAN to expedite award for urgently needed design and construction services identified above in Paragraph 3.
6. EFFORTS TO OBTAIN COMPETITION: CENAN solicited from as many firms as was practicable for Phase I. A limited sources J&A approved by the Senior Procurement Executive, Control No. CENAN 20-003, 26 March 2020, supported other than full and open competition for
Phase I. It was necessary to negotiate a contract with a single source selected from the group of firms down-selected after Phase I of this two-phase design-build acquisition. As discussed in
Paragraph 5, “Alternatives,” no other alternative would have allowed performance to begin immediately. The notice required at FAR 5.201 will not be published based on the exception at
FAR 5.202(a)(2), Unusual and Compelling Urgency.
7. ACTIONS TO INCREASE COMPETITION: CENAN is mindful of the requirement in
FAR 6.302-2 to request offers from as many potential sources as is practicable under the circumstances, and therefore did perform a limited competition for Phase I of the design-build procurement. Understanding the latitudes afforded under FAR 6.302-2, CENAN did not want to completely divest itself of a competitive environment and issued a limited competition Phase I design-build request for proposal to ten firms. The Government conducted its Phase I evaluation and down-selected to the most highly qualified firms, and only then undertook sole-source negotiations as part of Phase II with Parsons Corporation. It was not practicable to request an offer from more than one source under Phase II of a design-build procurement, because without issuing a UCA letter contract on a sole-source basis, CENAN would have been unable to undertake construction immediately and would not be able to meet the delivery schedule of three weeks.
8. MARKET RESEARCH: Based upon the Presidential National Emergency Declaration, CENAN determined the most expeditious tool available to fulfill this urgent and compelling
COVID-19 requirement. Immediately, a review of existing contract vehicles was conducted.
CENAN identified firms from prior experience which were known to have capacity to complete the ACF Mission. CENAN also utilized other sources of market research, including qualifications submitted to USACE by firms volunteering to help with the COVID mission, to the extent practical within the time constraints of the emergency. Across the ACF mission, the
Government attempted to maximize competition to the greatest extent practicable in accordance with FAR Part 6, and provided opportunities to locally based contractors. Market research was conducted as part of the Phase I process, and the Phase II process was limited to only consideration of those firms down-selected after Phase I.
9. INTERESTED SOURCES: In this instance, the need to undertake construction as soon as possible was of such an unusual and compelling urgency that the Government and the public would have been seriously injured unless CENAN was able to limit the number of sources from which it solicited a Phase II proposal to one.
10. OTHER FACTS: After award and Notice to Proceed, this contract was terminated for the convenience of the government. The effort to respond to COVID-19 pandemic was dynamic, with information rapidly changing by the day and even the hour. Efforts to forecast the need for increased hospital capacity even weeks in advance was an estimation based on the best available information from state and federal experts at that time. As projections of infection rates and hospital capacity changed, FEMA and the State of NY ultimately determined that the situation evolved to the point that this facility was no longer necessary, and it was in the best interest of the government to discontinue its construction. While there is no longer an urgent need for this facility, there was, at the time of award, an unusual and compelling urgency to this requirement based on the understanding of the facilities necessary to respond to the COVID pandemic at that time.
11. TECHNICAL CERTIFICATION: I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.
Name: Matthew Emigholz
Title: Program Manager Signature: ______________________________
(date in electronic signature)
12. REQUIREMENT CERTIFICATION: I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.
Name: Matthew Emigholz
Title: Program Manager Signature: _______________________________
13. FAIR AND REASONABLE COST DETERMINATION:
I hereby determine that the anticipated cost or price to the Government for this contract action will be fair and reasonable.
This will be determined by conducting a detailed cost and price analysis of the offeror’s definitization proposal, taking into consideration all pertinent information including field pricing assistance, audit reports and technical analysis, fact-finding results, independent Government cost estimates, and price histories. The contractor will be required to submit their price/cost proposal in accordance with FAR Part 15, and Certified Cost or Pricing Data will be required in accordance with FAR 15.403-4.
Name: Nicholas Emanuel
Title: Contracting Officer Signature: _____________________________
14. CONTRACTING OFFICER CERTIFICATION: I certify that this justification is accurate and complete to the best of my knowledge and belief.
Name: Nicholas Emanuel
Title: Contracting Officer Signature: ___________________
APPROVAL
Based on the foregoing justification, I hereby approve after-the-fact this contract to provide design-build construction services in support of the Alternate Care Facilities effort for
Alternative Care Facilities (ACFs) – Van Cortlandt Park in New York on an other than full and open competition basis pursuant to the authority of 10 U.S.C. § 2304(c)(2), Unusual and
Compelling Urgency, subject to the availability of funds, and provided the work herein described was otherwise authorized for acquisition.
Name: Ms. Jill E. Stiglich, SES
Title: Head of the Contracting Activity Signature: _____________________________
| 2020-04-21T13:35:00-0400 | |
| HELFMAN.JUSTIN.1368284110 |
| 2020-04-21T13:38:55-0400 | |
| EMIGHOLZ.MATTHEW.W.1266892248 |
| 2020-04-21T13:39:23-0400 | |
| EMIGHOLZ.MATTHEW.W.1266892248 |
| 2020-04-21T13:39:41-0400 | |
| EMIGHOLZ.MATTHEW.W.1266892248 |
| 2020-04-21T14:25:47-0400 | |
| EMANUEL.NICHOLAS.1298804880 |
| 2020-04-21T14:26:08-0400 | |
| EMANUEL.NICHOLAS.1298804880 |
| 2020-04-21T14:38:04-0400 | |
| CASHMAN.FRANCIS.1386668368 |
| 2020-04-21T15:39:28-0400 | |
| LEE.LORRAINE.C.1228825367 |
| 2020-04-21T17:05:53-0400 | |
| BROWN.TRISTAN.S.1394813717 |
| 2020-04-27T20:39:25-0400 | |
| EICHHORN.LAURA.J.1026254783 |
| 2020-04-28T13:14:06-0400 | |
| STIGLICH.JILL.E.1093489817 |