This is a Request for Proposal (RFP) issued by the Naval Air Warfare Center Weapons Division (NAWCWD) for engineering services. The contract is a cost-plus-fixed-fee type with a performance period from June 1, 2026 to May 31, 2031, with a total estimated effort of 460,682 labor hours. The solicitation includes multiple contract line items (CLINs) for engineering services, travel, materials, data requirements, and contractor-acquired property, with a total maximum contract value of $99,203,150.72.

The RFP requires offerors to submit detailed proposals including an executive summary, price/cost proposal, and contract administration information. The government estimates $12,921,474.84 for travel and $733,613.60 for materials. Labor categories include various engineering roles such as management, principal, senior, and support engineers, with specific hour allocations for each category. The solicitation emphasizes compliance with Service Contract Labor Standards and requires detailed cost breakdowns, fully burdened labor rates, and comprehensive documentation of proposed rates and personnel.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 05:00 PM local time 14 Oct 2025

X

A X B X C X D

EX

X

G F 48 - 66

67 - 77 X H candice.n.gonzalez.civ@us.navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A5 1 77

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N68936 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

CANDICE N. GONZALEZ (760) 608-4805

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

1 - 2 3 - 8

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

9 - 13

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

15 - 16 17 - 18

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 19 - 25 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 26 - 27 M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

28 - 46

PART II - CONTRACT CLAUSES

CDR NAWCWD CODE E250000

ATTN: C. GONZALEZ

(760) 608-4805

575 I. AVE., BLDG 36, SUITE 1116

POINT MUGU CA 93042-5049

(760) 608-4805

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.

1301193567

5. DATE ISSUED

28 Aug 2025

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N6893625R0005

Section A - Solicitation/Contract Form

CLAUSES INCORPORATED BY FULL TEXT

A-TXT-02 FOR YOUR INFORMATION – POINT MUGU (NAWCWD) (JUL 2024)

The following addresses and points of contact are provided:

Contract Specialist Name: Candice Gonzalez Phone: (760) 608-4805 Email address: candice.n.gonzalez.civ@us.navy.mil

Contracting Officer Name: Bretton West Phone: (760) 793-3494 Email address: bretton.a.west.civ@us.navy.mil

U.S Postal Service Mailing Address:

COMMANDER

CODE E251000 (B. West – 760-793-3494)

NAVAIRWARCENWPNDIV

575 "I" AVE SUITE 1 BLDG 36 STOP 0275

POINT MUGU, CA 93042-5049

Direct Delivery Address (UPS, FedEx, etc.):

COMMANDER

CODE E251000 (B. West)

NAVAIRWARCENWPNDIV

BLDG 36 RM 1116 STOP 0275

POINT MUGU, CA 93042-5049

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot Engineering Services

CPFF

The Contractor shall provide Engineering Services in accordance with Section J, Attachment 1, Statement of Work. The fixed fee is $TBD per hour. Term versus completion will be determined at the Task Order level.

FOB: Destination

PURCHASE REQUEST NUMBER: 1301193567

PSC CD: J015

ESTIMATED COST

FIXED FEE

TOTAL EST COST + FEE

0002 1 Lot ODC-Travel

COST

The Contractor shall provide travel as necessary to support this effort in accordance with Section J, Attachment 1, Statement of Work. This CLIN is a nonfee bearing CLIN.

FOB: Destination

0003 1 Lot ODC-Material

COST

The Contractor shall provide materials/other direct costs in the performance of Section J, Attachment 1, Statement of Work. This CLIN is a non-fee bearing

CLIN.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0004 1 Lot Contract Data Requirements List

COST

The Contractor shall provide Data in accordance with Exhibit A, Contract Data Requirements List (CDRL), DD Form, 1423.

0005 1 Lot Contractor Acquired Property (CAP)

COST

Delivery of all contractor acquired property no longer needed for performance in accordance with SOW

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

1.00 $100,000.00 10,000.00 $99,203,150.72

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

1.00 $100,000.00 10,000.00

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

BTXT.211-9503 LEVEL OF EFFORT (COST REIMBURSEMENT) (NAVAIR)(DEC 2012)

(a) The level of effort estimated to be ordered during the term of this contract is 460,682 man-hours of direct labor including authorized subcontract labor, if any. The contractor shall not, under any circumstances, exceed one hundred (100%) percent of the total level of effort specified in this basic contract. The estimated composition of the total man-hours of direct labor by classification is as follows:

Categories Hours Engineer - Management (CE1, DE1) 106,690

Engineer - Principal (CE2, DE2) 123,680

Engineer - Senior (CE3, DE3) 25,866

Engineer (CE4, DE4) 30,406

Tech Ops - Mgt/Prin (CM5, DM5) 22,110

Engineering Support (CE7, DE7) 29,140

Tech Ops (CM7, DM7) 80,180

Business Ops - Mgt (CE8, DE8) 5,590

Business Ops (CE9) 8,220

Program Manager (CE3, DE3) 28,800

Total 460,682

(b) FAR Clause 52.232-20, "Limitation of Cost" applies to fully funded orders and FAR Clause 52.232-22, "Limitation of Funds" applies to incrementally funded orders. Nothing in this clause amends the rights or responsibilities of the parties hereto under either of those two clauses. In addition, the notifications required by this clause are separate and distinct from any specified in either FAR Clause 52.232-20 or FAR Clause 52.232-22.

(c) In the event that less than one hundred (100%) percent of the established level of effort of the contract/order is actually expended by the end of the performance period, the Government shall have the option of:

(1) Requiring the Contractor to continue performance, subject to the provisions of the FAR Clause 52.232-20 or 52.232-22, as applicable, until the effort expended equals 100% of the established Level of Effort; or

(2) Effecting a reduction in the fixed fee by the percentage by which the total expended man-hours is less than one hundred (100%) percent of the established Level of Effort.

(d) The contractor agrees that effort performed in fulfillment of level of effort obligations under this contract shall include only verifiable effort in direct support of the work specified. It shall not include efforts such as work performed in transit to or from an employee's usual workplace, work during lunchtime activities, or effort performed at other non-work locations.

(e) In performing the contract/order, the contractor may use any reasonable combination of hours for the labor categories in support of section C of this contract/order.

BTXT.215-9535 PRICE AT LINE ITEM LEVEL (NAVAIR) (OCT 2005)

Offerors shall insert in Section B of the Schedule unit prices and amounts at the line item level only (e.g., Item 0001, 0002, etc.), even though subline items are also shown in the Schedule.

BTXT.216-9506 MINIMUM AND MAXIMUM QUANTITIES (NAVAIR)(MAR 1999)

As referred to in paragraph (b) of FAR 52.216-22 " Indefinite Quantity" of this contract, the contract minimum quantity is 1,561 hours; the maximum quantity is 460,682 hours.

B-TXT-STRMLND STREAMLINED ORDERING PROCEDURES FOR COST PLUS

FIXED FEE TERM LEVEL OF EFFORT ORDERS (NAWCWD) (JUL 2024)

Level Of Effort (LOE) Orders will be issued under this contract using the following streamlined ordering procedures:

(1) For each proposed order, the contracting officer will provide the contractor with a Statement of Work

(SOW) and an Independent Government Cost Estimate (IGCE). The IGCE is an estimate of labor hours by labor category utilizing the estimated and negotiated Composite Labor rates table below to calculate the total estimated cost for the proposed Task Order (TO). The TO fixed fee is calculated using HTXT.232-

9510 PAYMENT OF FIXED FEE (NAVAIR).

(2) These composite labor rates are estimates, and invoicing will be based upon actual costs incurred. Ceiling for Other Direct Costs (ODC) will be priced in accordance with the Government estimate. TOs crossing multiple years will be estimated by the Government using the composite rates for each year in proportion to the period of performance of the TO.

(3) Within three (3) working days of receipt of the SOW and IGCE, the contractor will respond:

(i) If the contractor agrees that it can perform the TO within the parameters of the SOW/IGCE, they will notify the contracting officer within three (3) working days of receipt of the SOW and IGCE.

If the requirement remains valid, a priced order will be issued to the contractor.

(ii) If the contractor does not agree with the SOW or IGCE the contractor shall submit a proposal to the contracting officer within five (5) working days of receipt of the SOW and IGCE, addressing only the specific areas of difference in labor categories and/or hours in the IGCE. Once the differences are resolved between the contracting officer and the contractor, and the requirement remains valid, a priced order will be issued to the contractor.

(iii) If the contractor fails to respond to the proposed order within five (5) working days of receipt of the TO, the contracting officer may unilaterally issue the TO or extend the deadlines above when in the best interest of the Government.

Labor Category B-1 COMPOSITE LABOR RATES (Exclusive of Fee)

Year 1 Year 2 Year 3 Year 4 Year 5 6/1/2026- 5/31/2027

6/1/2027- 5/31/2028

6/1/2028- 5/31/2029

6/1/2029- 5/31/2030

6/1/2030- 5/31/2031

Engineer - Management (CE1, DE1) TBD TBD TBD TBD TBD Engineer - Principal (CE2, DE2) TBD TBD TBD TBD TBD Engineer - Senior (CE3, DE3) TBD TBD TBD TBD TBD Engineer (CE4, DE4) TBD TBD TBD TBD TBD Tech Ops - Mgt/Prin (CM5, DM5) TBD TBD TBD TBD TBD Engineering Support (CE7, DE7) TBD TBD TBD TBD TBD Tech Ops (CM7, DM7) TBD TBD TBD TBD TBD Business Ops - Mgt (CE8, DE8) TBD TBD TBD TBD TBD

Business Ops - Mgt (CE9) TBD TBD TBD TBD TBD

Program Manager - CE3, DE3 TBD TBD TBD TBD TBD

Section C - Descriptions and Specifications

STATEMENT OF WORK

Statement of Work is provided in Section J as Attachment 1.

CTXT.204-9505 SYSTEM AUTHORIZATION ACCESS REQUEST (SAAR) REQUIREMENTS FOR

INFORMATION TECHNOLOGY (IT) (NAVAIR) (FEB 2025)

(a) Contractor personnel assigned to perform work under this contract may require access to Navy Information Technology (IT) resources (e.g., computers, laptops, personal electronic devices/personal digital assistants (PEDs/PDAs), NMCI, RDT&E networks, websites such as MyNAVAIR, and Navy Web servers requiring Common Access Card (CAC) Public Key Infrastructure (PKI)). Contractor personnel (prime, subcontractor, consultants, and temporary employees) requiring access to Navy IT resources (including those personnel who previously signed SAAR DD Form 2875) shall submit a completed System Authorization Access Request (SAAR) DD Form 2875 or latest version thereof, and have initiated the requisite background investigation (or provide proof of a current background investigation) prior to accessing any Navy IT resources. The form and instructions for processing the SAAR form are available at: https://www.esd.whs.mil/Directives/forms/dd2500_2999/DD2875/.

(b) SAAR forms will be submitted by the contractor’s Facility Security Officer (FSO) via the National Help Desk Service Management (NHDSM) Service Catalog at: https://nhdsm.navair.navy.mil. For those contractors that do not have a FSO or that cannot access the NHDSM, or for NAVAIR organizations that have not transitioned to the NHDSM SAAR system, SAAR forms shall be submitted directly to the designated SAAR Government Sponsor or Technical Point Of Contact (TPOC). Copies of the approved SAAR forms may be obtained through the designated SAAR Government Sponsor or TPOC. Resources related to the SAAR process and step by step instructions can be found at the following link for those with access to Flank Speed: https://flankspeed.sharepoint-mil.us/sites/NAVAIR_NAWCAD_DNA/SitePages/SAAR.aspx. For additional questions or information related to the SAAR process and requirements, please contact the National Help Desk at 301-342-3104 or 1-888-292-5919.

(c) In order to maintain access to Navy IT resources, the contractor shall ensure completion of initial and annual IA/Cyber Awareness training, monitor expiration of requisite background investigations, and initiate re-investigations as required. If requested, the contractor shall provide to the designated SAAR Government Sponsor or TPOC documentation sufficient to prove that it is monitoring/tracking the SAAR requirements for its employees who are accessing Navy IT resources. For those contractor personnel not in compliance with the requirements of this text, access to Navy IT resources will be denied/revoked.

(d) The SAAR form remains valid throughout contractual performance, inclusive of performance extensions and option exercises where the contract number does not change. Contractor personnel are required to submit a new SAAR form only when they begin work on a new or different contract.

CTXT.211-9502 GOVERNMENT INSTALLATION WORK SCHEDULE (NAVAIR)(APR 2022)

(a) The Holidays applicable to this contract are: New Year's Day, Birthday of Martin Luther King Jr., Washington’s Birthday (President's Day), Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, and Christmas Day.

(b) In the event that any of the above holidays occur on a Saturday or Sunday, or alternate Friday, then such holiday shall be observed as they are by the assigned Government employees at the using activity.

(c) The Naval Air Warfare Center Weapons Division works a 4/5/9 work schedule. Therefore alternate Fridays are not a part of the normal workweek for work performed on-site at a Naval Air Warfare Center Weapons Division site. The majority of the Government offices are closed on alternate Fridays.

(d) No deviation in the normal workweek will be permitted without express advance approval by the designated Contracting Officer with coordination of the using departments.

CTXT.211- 9510 CONTRACTOR EMPLOYEES (NAVAIR)(MAY 2011)

(a) In all situations where contractor personnel status is not obvious, all contractor personnel are required to identify themselves to avoid creating an impression to the public, agency officials, or Congress that such contractor personnel are Government officials. This can occur during meeting attendance, through written (letter or email) correspondence or verbal discussions (in person or telephonic), when making presentations, or in other situations where their contractor status is not obvious to third parties. This list is not exhaustive. Therefore, the contractor employee(s) shall:

(1) Not by word or deed give the impression or appearance of being a Government employee;

(2) Wear appropriate badges visible above the waist that identify them as contractor employees when in Government spaces, at a Government-sponsored event, or an event outside normal work spaces in support of the contract/order;

(3) Clearly identify themselves as contractor employees in telephone conversations and in all formal and informal written and electronic correspondence. Identification shall include the name of the company for whom they work;

(4) Identify themselves by name, their company name, if they are a subcontractor the name of the prime contractor their company is supporting, as well as the Government office they are supporting when participating in meetings, conferences, and other interactions in which all parties are not in daily contact with the individual contractor employee; and

(5) Be able to provide, when asked, the full number of the contract/order under which they are performing, and the name of the Contracting Officer’s Representative.

(b) If wearing a badge is a risk to safety and/or security, then an alternative means of identification maybe utilized if endorsed by the Contracting Officer’s Representative and approved by the Contracting Officer.

(c) The Contracting Officer will make final determination of compliance with regulations with regard to proper identification of contractor employees.

CTXT.232-9509 TRAVEL APPROVAL AND REIMBURSEMENT PROCEDURES (NAVAIR)(OCT 2013)

(a) General. Performance under this contract may require travel by Contractor personnel. If travel, domestic or overseas, is required, the Contractor is responsible for making all necessary arrangements for its personnel. These include but are not limited to: medical examinations, immunizations, passports/visas/etc., and security clearances.

(b) Travel Approval Process. Prior approval is required for all travel under this contract. Travel shall be reviewed and approved/disapproved as follows:

(1) The Contractor shall provide the Contracting Officer's Representative (COR) a written request for authorization to travel at least 30 days in advance of the required travel date, when possible. The request should include: purpose of travel, location, travel dates, number of individuals traveling, and all estimated costs associated with the travel (e.g., lodging, meals, transportation costs, incidental expenses, etc.).

(2) The COR will review the travel request and provide, in writing, an approval or disapproval of the travel request to the Contractor and the Procuring Contracting Officer

(c) Travel Policy.

(1) Travel arrangements shall be planned in accordance with the Federal Travel regulations, prescribed by the General Services Administration for travel in the conterminous 48 United States, (hereinafter the FTR) and the Joint Travel Regulation, Volume 2, DoD Civilian Personnel, Appendix A, prescribed by the Department of Defense (hereinafter the JTR).

(2) The Government will reimburse the Contractor for allowable travel costs incurred by the Contractor in performance of the contract in accordance with FAR Subpart 31.2.

(3) For purposes of reimbursement of travel expenses, the Contractor's official station is defined as within 50 miles of the Contractor's regular work site. (If Contractor has more than one regular work site, the official station is defined as within 50 miles of each of its regular work sites.)

(4) The Contractors documentation for the reimbursement of travel costs (e.g., receipts) shall be governed as set forth in FAR Subpart 31.2, the FTR, and the JTR.

(5) Car Rental for a team on temporary duty (TDY) at one site will be allowed provided that only one car is rented for every four (4) members of the TDY team. In the event that less than four (4) persons comprise the TDY team, car rental will be allowed if necessary to complete the mission required.

(6) Whenever work assignments require TDY aboard a Government ship, the Contractor will be reimbursed at the per diem identified in the JTR.

CTXT.242-9520 PROCEDURES AND APPROVALS REQUIRED PRIOR TO INCURRING DIRECT

MATERIAL COSTS (APR 2022)

(a) General.

(1) These procedures apply to CLIN 0003.

(2) Any material procured as a direct cost under this contract by the Contractor is subject to the requirements of the Federal Acquisition Regulation (FAR), the Defense Federal Acquisition Regulation Supplement (DFARS), the Navy Marine Corps Acquisition Regulation Supplement (NMCARS), and any other Department of Defense or Department of the Navy policies and procedures.

(3) Performance of this contract may require the contractor to procure material. If material incidental to performance of this service contract is required and will be a direct cost consistent with the contractor’s disclosure statement, the Contractor shall follow the procedures outlined herein before making a purchase. No material item with a unit cost greater than the Simplified Acquisition Threshold (SAT) (FAR 2.101) may be procured under this contract. No single procurement with a total value, i.e., the total sum of all items, greater than the Truthful Cost or Pricing Data Act threshold (FAR 15.403-4(a)(1)) may be procured under this contract. Procurements shall not be split to circumvent these thresholds or the approval thresholds set forth in paragraph (b) below. Procurement of material that is not incidental to and necessary for contract performance, or approved in accordance with these procedures, may be determined to be an unallowable cost pursuant to FAR Part 31 and DFARS Part 231.

(b) Procedures. All material procurements to be directly charged to CLIN(s) 0003 of this contract are subject to the following review and/or approval procedures:

(1) Approval Authorities.

Notification Only (No Approval Required)

Contracting Officer Representative (COR)

Approval COR and Contracting Officer

Approval Items listed in para. (c), excluding sole source procurements and software licenses, with a total cost of less than or equal to the micro-purchase threshold (FAR 2.101)

Items listed in para. (c), excluding sole source procurements and software licenses, with a total cost greater than the micro-purchase threshold (FAR 2.101) but less than or equal to “the SAT (FAR 2.101)”.

Items listed in para. (c) with a total cost greater than the SAT (FAR 2.101).

Items listed in para. (c) procured on a sole source basis (regardless of dollar value)

Software licenses (regardless of dollar value)

Any item not listed in para. (c) (regardless of dollar value)

(2) Contractor Requests and Notifications. For all material procurements subject to these procedures, the Contractor shall submit a material procurement request (or notification, for procurements that do not require approval) that includes the following: 1) a list of the material items to be procured, 2) an explanation of the need for the material, 3) a listing of quotes received, 4) the reason for the selected source, and 5) the determination of price reasonableness. If the procurement is sole source to a particular supplier, the request shall also include the rationale for limiting the procurement to that supplier. When approval is required per paragraph (b)(1), the Contractor shall not proceed with the procurement until receiving approval. All requests requiring approval shall be submitted to the COR for disposition. For requests within the COR approval threshold, the COR will provide written approval or disapproval to the Contractor. For requests within the Contracting Officer’s approval threshold, the COR will forward the request with a recommendation of approval or disapproval to the Contracting Officer. The Contracting Officer will provide written approval or disapproval to the COR and the Contractor. When approval is not required, the Contractor shall provide an email notification to the COR containing the required content prior to procuring the material.

(3) Urgent Requirements. For direct material procurements that require COR approval only, urgent requests may be verbally requested and verbally approved. A request is considered urgent when it is necessary for the Contractor to procure material to immediately respond to a requirement. If the COR concurs with the urgent nature of the request, verbal approval of the request will be provided to the Contractor. All urgent requests verbally approved by the COR shall be followed up with a Contractor email request to the COR within one business day of the verbal approval, containing the minimum content set forth in paragraph (b)(2) above and referencing the date of the verbal approval by the COR. The COR shall thereafter respond via email to provide written confirmation of the verbal approval.

(c) List of Applicable Materials:

Adhesives (adhesive-sealant silicone, cyanoacrylate rite), lubricants (dry film lubricant, grease, O-ring, WD-40), tape (silicon, red, blue, fiberglass, low-outgassing, duct, aluminum, aluminum foil glass cloth tape, aluminized fiberglass), locktite 272, strain gauges (uniaxial), tie-cable adjustable black electrical, tie bases, RTV 106, ablative/encapsulation compound white paste, primer-silicone; 2-part epoxy, thread locker-ceramic bottle, TWT wipes, tongue depressors, alcohol, syringes, Q-Tips, canned air, safety wire, Room Temperature Vulcanization Activator, mixing cups, screw, cap, socket head, washer flat, and clover si-carbide lapping compound, freight, and shipping.

CTXT.245-9520 ASSOCIATE CONTRACTOR CLAUSE (NAVAIR) (OCT 2005)

(a)(1) This clause is intended to ensure that there will be appropriate coordination/integration of work by the PTMO associate contractors to ensure complete compatibility between equipment, data, and services for PTMO to prevent unnecessary duplication of effort and in order to maximize commonality.

(2) The price of this contract makes provision for the performance of the work called for in the Associate Contractor Agreements as required by this clause, in support of this contract.

(b) The Associate Contractors are as follows: Systems Application & Technologies Inc

(c) The contractor shall work and maintain close liaison with the associate contractors listed in paragraph (b) above. In order to assure accomplishment of this objective, the contractor shall enter into a written Associate Contractor Agreement with each of the other applicable associate contractors.

(d) Each Associate Contractor Agreement between the contractor and an associate contractor shall provide for complete and unbiased exchange of technical information and interface data (data) relating to their detailed responsibilities and procedures. The following is a guide to be used in the development of each agreement:

(1) Identification of the data to be furnished among the associate contractors to facilitate procedures/schedules for the exchange of data. Descriptive detail of the data to be furnished or exchanged, with a specific date for delivery of each item thereof and containing such other mutual covenants and agreements that may be desirable or required to assure delivery or exchange of said data in a timely manner and in a condition suitable for use by the recipient.

(For example, this may extend to all information pertaining and essential to the design, development, fabrication, test, interface, modification and installation of equipment and provision of services hereunder to the extent that each party may require such information to ensure the compatibility of their respective equipment, data and services.)

(2) Services to be provided by one contractor to another (including such services as clerical support to visiting associate contractor personnel, unscheduled maintenance and technical support for equipment, etc.) to facilitate the performance of the respective contracts and the period(s) of time the services are to be provided to assure necessary interface actions and support activities.

(3) The materials to be provided to each other by the respective contractors in performance.

(4) The facilities and their location to be provided by each contractor to accommodate personnel assigned to provide the associate contractor's integration and support services, assurance of adequate working areas, power requirements, office space and communication equipment which are essential for timely completion of the integration/support services.

(5) Delineation of respective interface responsibilities.

(6) Provision for furnishing copies to communications relative to performance of associate contractor responsibilities.

(e) In the event this exchange of data results in the need to obtain access to proprietary information, the contractor agrees to include in the Associate Contractor Agreements the terms and conditions under which the contractor and associate contractors agree to exchange such proprietary information. The Contractor hereby agrees not to use, modify, reproduce, release, perform, display, or disclose such proprietary information unless specifically authorized in writing to do so under the Associate Contractor Agreements.

(f) The Associate Contractor Agreements shall permit the exchange of data between the associate contractors. The Agreements shall be structured so that all contractors and associate contractors are obligated to protect proprietary information from all unauthorized use or disclosure for as long as such information remains proprietary.

(g) "Proprietary Information" means information that embodies trade secrets developed at private expense or business, commercial, or financial information that is privileged or confidential provided that such information:

[__X__] is not known or available from other sources without obligations concerning its confidentiality;

[__X__] has not been made available by the owners to others without obligation concerning its confidentiality;

[__X__] is not already available to the Government without obligation concerning its confidentiality; and [__X__] has not been developed independently by persons who have had no access to the information.

(h) Each Associate Contractor Agreement shall be submitted to the Government for review prior to execution.

Following Government concurrence and execution by both associate contractors, each Associate Contractor Agreement may be made an attachment to this contract. The Associate Contractor Agreements are for information purposes only and shall not be subject to or governed by this contract. In the event of a conflict between the terms of this contract and terms of the aforesaid agreement, the terms of this contract shall control.

(i) Where the contractor and an associate contractor fail to agree upon action to be taken in connection with their respective responsibilities, each contractor shall promptly notify the cognizant PCO and furnish the contractor's recommendations for a solution. The contractor shall not be relieved of its obligations to make timely deliveries or be entitled to any other adjustment because of the contractor and its associate failure to: (1) resolve Associate Contractor Agreements disputes; (2) promptly refer matters to the PCO; or (3) to implement PCO directions.

Section D - Packaging and Marking

DTXT.223-9501 MATERIAL SAFETY DATA SHEET (MSDS)(NAVAIR) (APR 2009)

(a) The contractor shall forward an electronic copy of the Material Safety Data Sheet (MSDS) required under FAR Clause 52.223-3, "Hazardous Material Identification and Material Safety Data", to Mar-navyhmirs@med.navy.mil and the Naval Inventory Control Point (NICP) at wraps.prime.fct@navy.mil.

(b) One copy of the MSDS shall be enclosed with the shipping documents. If the shipment is received without an attached copy of the MSDS, the Government has the right to refuse receipt.

DTXT.247-9507 PACKAGING AND MARKING OF REPORTS (NAVAIR)(OCT 2021)

(a) All unclassified data shall be prepared for shipment in accordance with best commercial practice. Classified reports, data and documentation, if any, shall be prepared for shipment in accordance with the National Industry Security Program Operating Manual, 32 CFR Part 117.

(b) The contractor shall prominently display on the cover of each report the following information:

(1) Name and business address of contractor.

(2) Contract Number/Delivery/Task order number.

(3) Contract/Delivery/Task order dollar amount.

(4) Whether the contract was competitively or non-competitively awarded.

(5) Name of sponsoring individual.

(6) Name and address of requiring activity.

DTXT.247-9508 PROHIBITION AND LIMITATIONS FOR PACKAGING MATERIALS (NAVAIR)(AUG

2019) The use of loose fill materials, asbestos, excelsior, newspaper and shredded paper (all types) are prohibited. In addition, all Wood Packaging Materials (WPM) shall be heat treated or chemically treated in accordance with the requirements of the International Standards for Phytosanitary Measures (ISPM) 15:2009, "Regulation of Wood Packaging Material in International Trade."

DTXT.247-9514 TECHNICAL DATA PACKING INSTRUCTIONS (NAWCWD) (FEB 2025)

Technical Data and Information produced or handled in support of this contract shall be packed and packaged for domestic shipment in accordance with best commercial practices. The package or envelope should be clearly marked with any special markings specified in this contract (or delivery/task order), e.g., Contract Number, CLIN, Device No., and document title must be on the outside of the package. Classified reports, data and documentation, if applicable, shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM) codifying 32 Code of Federal Regulation Part 117, NISPOM Rule.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-5 Inspection Of Services Cost-Reimbursement APR 1984

ETXT.246-9512 INSPECTION AND ACCEPTANCE (NAVAIR)(OCT 2005)

(a) Inspection and acceptance of the supplies or services to be furnished hereunder shall be performed by the

COR.

(b) Acceptance of all Contract Line Items/Sub Line Items (CLINs/SLINs) shall be made by signature of the accepting authority on a DD 250 submitted through the WAWF system. Acceptance will only occur when the accepting authority is sure that inspections performed demonstrate compliance with contract requirements.

ETXT.246-9514 INSPECTION AND ACCEPTANCE OF TECHNICAL DATA AND INFORMATION

(NAVAIR)(FEB 1995)

Inspection and acceptance of technical data and information will be performed by the Procuring Contracting Officer (PCO) or his duly authorized representative. Inspection of technical data and information will be performed by ensuring successful completion of the requirements set forth in the DD Form 1423, Contract Data Requirements List (CDRL) and incorporation/resolution of Government review comments on the data items. Acceptance will be evidenced by execution of an unconditional DD Form 250, Material Inspection and Receiving Report, as appropriate, and/or upon receipt of a second endorsement acceptance by the PCO on the attachment to this contract entitled EXHIBIT A, CDRLS. The attached form will not be used for high cost data such as drawings, specifications, and technical manuals.

ETXT.246-9517 CONSTRUCTIVE ACCEPTANCE PERIOD (NAVAIR) (MAR 1999)

For the purpose of FAR Clause 52.232-25, "Prompt Payment", paragraph (a)(5)(i), Government acceptance shall be deemed to have occurred constructively on the 30th day after the contractor delivered the supplies or performed the services.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 01-JUN-2026 TO

31-MAY-2031

N/A CDR NAWCWD CODE EB4210M

MARY DUBE

575 “I” AVE SUITE 1 BLDG 36

POINT MUGU CA 93042

(805) 909-3961

N68936

0002 POP 01-JUN-2026 TO

31-MAY-2031

N/A (SAME AS PREVIOUS LOCATION)

0003 POP 01-JUN-2026 TO

N/A (SAME AS PREVIOUS LOCATION)

0004 POP 01-JUN-2026 TO

N/A (SAME AS PREVIOUS LOCATION)

0005 N/A N/A N/A N/A

52.242-15 Alt I Stop-Work Order (Aug 1989) - Alternate I APR 1984 52.247-34 F.O.B. Destination JAN 1991

FTXT.211-9507 PERIOD OF PERFORMANCE (NAVAIR) (MAR 1999)

(a) The contract shall commence on 01 June 2026 and shall continue until 31 May 2031. However, the period of performance may be extended in accordance with the option provisions contained herein.

(b) If FAR Clause 52.216-18, “Ordering”, is incorporated into this contract, then the period in which the Government can issue orders under the contract will be extended at the exercise of an option, and extended to the end of that option period.

FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR)(FEB 1995)

Technical Data and Information shall be delivered in accordance with the requirements of the Contract Data Requirements List, DD Form 1423, Exhibit A, attached hereto, and the following:

(a) The contractor shall concurrently deliver technical data and information per DD Form 1423, Blocks 12 and 13 (date of first/subsequent submission) to all activities listed in Block 14 of the DD Form 1423 (distribution and addresses) for each item. Complete addresses for the abbreviations in Block 14 are shown in paragraph (g) below.

Additionally, the technical data shall be delivered to the following cognizant codes, who are listed in Block 6 of the DD Form 1423.

(1) PCO, Code E251000

(2) COR, Code EB4210M

(b) Partial delivery of data is not acceptable unless specifically authorized on the DD Form 1423, or unless approved in writing by the PCO.

(c) The Government review period provided on the DD Form 1423 for each item commences upon receipt of all required data by the technical activity designated in Block 6.

(d) A copy of all other correspondence addressed to the Contracting Officer relating to data item requirements (i.e., status of delivery) shall also be provided to the codes reflected above and the technical activity responsible for the data item per Block 6, if not one of the activities listed above.

(e) The PCO reserves the right to issue unilateral modifications to change the destination codes and addresses for all technical data and information at no additional cost to the Government.

(f) Unless otherwise specified in writing, rejected data items shall be resubmitted within thirty (30) days after receipt of notice of rejection.

(g) DD Form 1423, Block 14 Mailing Addresses:

bretton.a.west.civ@us.navy.mil mary.a.dube6.civ@us.navy.mil

Section G - Contract Administration Data

252.204-7006 Billing Instructions--Cost Vouchers MAY 2023

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either “Invoice 2in1” or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC HQ0339

Issue By DoDAAC N68936

Admin DoDAAC** S4420A

Inspect By DoDAAC N68936

Ship To Code N68936

Ship From Code N/A

Mark For Code N/A

Service Approver (DoDAAC) N68936

Service Acceptor (DoDAAC) N68936

Accept at Other DoDAAC N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC N/A

Other DoDAAC(s) N/A

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert “See Schedule” or “Not applicable.”)

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

Not applicable. Reference (2) below for assistance.

(Contracting Officer: Insert applicable information or “Not applicable.”)

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

GTXT.201-9501 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

(COR)(NAVAIR)(APR 2022) - ALT I (APR 2022)

(a) The Contracting Officer has designated the following as an authorized Contracting Officer's Representatives

(COR):

COR 1: Mary Dube, mary.a.dube6.civ@us.navy.mil, Code EB4210M, and (805) 989-7844, to perform the following functions, duties, and/or responsibilities: as delineated in the NAVAIR COR Designation Form (NAVAIR 4200/39) dated TBD at award.

(b) The Contracting Officer has designated the following as an authorized Alternate Contracting Officer's Representatives (ACOR):

ACOR 1: Annette Cordero, annette.l.cordero.civ@us.navy.mil, Code EB4210M, and (805) 989-5745 to perform the functions, duties, and/or responsibilities outlined below in the absence of Mary Dube.

ACOR 1 Functions, Duties, and/or Responsibilities: as delineated in the NAVAIR COR Designation Form (NAVAIR 4200/39) dated TBD at award.

(c) The effective period of the COR designation is the period of performance of this contract.

GTXT.232-0001 PAYMENT INSTRUCTIONS (NAVAIR) (MAY 2023)

Note: Payment Clause 52.216-7 is applicable.

For Government Use Only

Contract/Order Payment Clause

Type of Payment Request

Su pp ly

Se rv ic e

C on st ru ct io n

Payment Office Allocation Method

52.212-4 (Alt I), Cost Voucher X X N/A Line item specific proration.

Contract Terms and If there is more than one ACRN Conditions— within a deliverable contract line Commercial Products item, the funds will be allocated in and Commercial the same proportion as the Services; amount of funding currently 52.216-7, Allowable unliquidated for each ACRN on Cost and Payment; the line item billed.

52.232-7, Payments Under Time-and- Materials and Labor- Hour Contracts

52.232-1, Payments, Navy X X N/A Line item specific by fiscal year.

252.217-7007, Shipbuilding If there is more than one ACRN Payments Invoice (Fixed within a deliverable line or (vessel repair and alterations) Price) deliverable subline item, the funds will be allocated using the oldest funds first. In the event of a deliverable line or deliverable subline item with two or more ACRNs with the same fiscal year, those amounts will be prorated to the available unliquidated funds for that year.

52.232-1, Payments; Invoice X X N/A Line item specific proration.

52.232-2, Payments If there is more than one ACRN Under Fixed-Price within a deliverable line item or Research and deliverable subline item, the Development funds will be allocated in the Contracts; same proportion as the amount 52.232-3, Payments of funding currently unliquidated Under Personal for each ACRN on the deliverable Services Contracts; line or deliverable subline item for 52.232-4, Payments which payment is requested.

Under Transportation Contracts and Transportation-Related Services Contracts; and 52.232-6, Payments Under Communication Service Contracts With

Common Carriers st ru ct

52.232-5, Payments Under Fixed-Price Construction Contracts

Construction Payment Invoice

N/A N/A X Line item specific by fiscal year. If there is more than one ACRN within a deliverable line or deliverable subline item, the funds will be allocated using the oldest funds first. In the event of a deliverable line or deliverable subline item with two or more ACRNs with the same fiscal year, those amounts will be prorated to the available unliquidated funds for that year.

52.232-16, Progress Progress X X N/A Contract-wide proration.

Payments Payment* Funds shall be allocated in the (excluding contracts same proportion as the amount with multiple lot of funding currently unliquidated progress payments) for each ACRN. Progress payments are considered contract level financing, and the “contract price” shall reflect the fixed-price portion of the contract per FAR 32.501-3.

52.232-16, Progress Payments;

252.232-7018, Progress Payments— Multiple Lots

Progress Payment*

X X N/A Lot-wide proration (applies to lots specifically identified in the contract).

If there is more than one ACRN within a lot, the funds will be allocated in the same proportion as the amount of funding currently unliquidated for each ACRN on the lot for which payment is requested.

See PGI 204.7108 paragraph (c) for multiple lot CLIN structure.

st ru ct

52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services;

52.232-30, Installment Payments for Commercial Products and Commercial Services

Commercial Product and Commercial Service Financing*

X X N/A Specified in approved payment. The contracting officer shall specify the amount to be paid and the account(s) to be charged for each payment approval in accordance with FAR…