Question and Answers.docx

DOCX document 14 KB Posted

Attached to
Security System Upgrade and Installation Federal contract opportunity
Solicitation number
N6893625Q0023
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

This document contains a set of Questions and Answers related to a federal contract opportunity for a Security System Upgrade and Installation. The key details are:

The contract opportunity is for the Naval Air Warfare Center, Weapons Division at China Lake, CA to upgrade their security system. This is a sole source requirement with competition among authorized distributors of the specified manufacturers. The Statement of Work and required parts list are provided as attachments. The solicitation or Request for Quote (RFQ) will be posted on beta.SAM.gov around 10/30/2024. Interested parties must be registered in SAM.gov, and a notarized letter identifying the authorized Entity Administrator is required within 30 days of registration. The Questions and Answers provide clarification on the floor plan, cable/conduit requirements, and installation specifications. This appears to be a service-based contract requirement using the Service Contract Act wage determinations.

View the file

Other files for this federal contract opportunity

Other files attached to Security System Upgrade and Installation, newest first.
File Type Posted
25Q0023 Amendment 1.docx DOCX document
Updated Floor Plan.pdf PDF
25Q0023 Solicitation.docx DOCX document
C05 SOW.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A

1) Is there any way that I can get a floor plan with equipment location? See attached Updated Floor Plan.

2) The final page shows a basic floor plan. Can you advise the scale of this floor plan, or estimated size of the space, so I know about how much cable or conduit is needed? Also, is there suspended ceiling throughout?

The dimensions are about 40’ x 120’ The location of the motions, BMS, Expanders, and controller (head-in) is noted on the attached drawing.

3.2 The Contractor shall use existing conduit or provide new EMT conduit to conceal all wiring from the panels to above the ceiling or between panels. All installation cable above suspended ceiling must be supported to protect from being damage in accordance with NFPA 70 National Electric Code.

It is acceptable to free wire above the ceiling when using proper cable support.

Since EMT conduit is only required at the controller location and above the door to wire BMS door sensor.

The about of cable is subjective. The installer can mount the DMP expanders in a serviceable location (below drop ceiling) to minimize cable usage as noted in the attached drawing.