Statement_of_Work.docx
DOCX document 156 KB Posted
- Attached to
- Service: Process Engineering Package Federal contract opportunity
- Solicitation number
- N6893619Q0324
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CDRL.pdf | ||
| 19Q0324_Commercial_Solicitation.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Large Scale Synthesis Laboratory Design Package 01 February 2019
1.0 BACKGROUND
Chemical obsolescence is a current and evolving challenge to the U.S. energetics research and production community. Several materials critical to fielded weapon systems are no longer produced by an approved CONUS source, and a great number more are in danger of such. Additionally, research and development of energetic materials relies heavily on commercial sources of materials, however the quantities needed are often so small as to be disincentivizing to the manufacturer. Mitigation strategies and measures are currently being implemented at a high level within the DOD and industry, but those solutions will be long term and will likely fail to address the specific and immediate needs of on-going research.
An additional dimension to the overall challenge is the shelf-life and storability of certain materials. Some energetic materials are less amenable to long term storage than others. Storing these materials long term, as is common in the R&D community, incurs significant cost and risk. These materials are often of limited availability from commercial sources for all the aforementioned reasons.
In order to bridge the gap between the current shortage of materials and a long term solution in the greater community, it is proposed that the Naval Air Warfare Center at NAWCWD modernize its capability to make small quantities of specialty chemicals to support energetic material research at NAWCWD and partner DOD facilities. This capability would include the ability to make a wide range of energetic and specialty materials, on-demand, and to-quantity. The proposed funding source for this effort is an FY2019/FY2020 Capital Improvement Project (CIP).
When this CIP is complete, NAWC-WD will have the capability to safely support the warfighter by making energetic chemicals as needed. This includes the ability to transition research discoveries from material readiness level 1 through material readiness level 8/9. Activities like this are required if the US Navy is to regain dominance. Updating our current laboratory will greatly improve process safety, and it will increase the scope of NAWC-WD capabilities to produce fine chemicals and explosives.
2.0 SCOPE
The current chemical pilot plant at NAWC-WD is obsolete. The current batch reactor, while operational and sufficient for the proposed usage in-and-of itself, is not attached to any other unit operations that would make it usable. Additionally, it is located in a space that makes it impossible to establish such connections The proposed solution will create a design which utilizes the existing equipment in a new usable configuration integrated with several other unit operations. This will provide the initial design for follow-on projects to establish the capability to produce specialty chemicals and energetics, via batch reactions at the pilot scale.
3.0 REQUIREMENTS
The contractor shall provide a process engineering package consisting of specifications and drawings of the equipment, controls, and processes for a design of a Large Scale Synthesis Laboratory that meets the requirements defined in section 3.1. Deliverables for the process engineering package are defined in section 3.2.
Please note that the numbering system for the design requirements matches that in the Systems Engineering Plan wherein they were first documented. For that reason, the numbering of the requirements begins with R.2 (Large Scale Synthesis) and is decomposed into a hierarchy, see Figure 1, below.
Figure 1 Design Requirements Hierarchy
3.1 LARGE SCALE SYNTHESIS DESIGN REQUIREMENTS
Large Scale Synthesis Subsystem Level Requirements Generally, the production of chemicals in accomplished in either batch or continuous modes. The particular mode chosen will depend on both the particular chemical being produced and the amount required. Generally, the batch mode of production is most useful for small quantities of either solid or liquid material, whereas the continuous mode is useful for liquids in intermediate and large quantities. The chemical pilot plant system must be capable of producing materials in the batch mode. Rarely are chemicals, energetic or otherwise, produced in a useable form in a single step. In the majority of cases, the material must be recovered from the reaction mixture and purified in a process called recovery.
Table 1 Large Scale Synthesis Subsystem Level Requirements
| Requirement |
| Name |
| Description |
| R.2 |
| Large Scale Synthesis |
| The system must be capable of production campaigns, in which research level quantities of material are synthesized. |
| R.2.1 |
| Batch Production |
| The system must be capable of production accomplished in a single operation, wherein ingredients are added to a reactor in specified amounts at the prescribed time. The chemical reaction takes place within the reactor, producing the desired material. |
| R.2.3 |
| Recovery |
| The system must be capable of recovering product from reaction mixtures. |
Figure 2 Large Scale Synthesis Requirements
Batch Production Requirements Batch production will use existing equipment E.1., a 50 gallon, glass-lined, jacketed, stirred-tank reactor. Several subsystems will comprise the batch production. A secondary vessel capable of supporting E.1 during nitration chemistries and work-up steps (e.g. a quench vessel) must be installed.
Table 2 Batch Production Requirements
| Requirement |
| Name |
| Description |
| R.2.1.1 |
| Utilize E.1 |
| The batch production system must utilize E.1, a glass-lined, jacketed, agitated, hazardous environment rated, 150 L reactor, currently residing in BLDG A. Its current configuration severely limits its usefulness. In order to increase the usefulness of this asset, and to avoid the cost of purchasing a new reactor, E.1 will be utilized as the primary reactor in the batch production system of the large scale synthesis laboratory. |
| R.2.1.2 |
| Temperature Control |
| The system must be able to maintain a specified reaction mixture temperature, within the E.1 reactor. |
| R.2.1.3 |
| Agitation Control |
| The system must be capable of controlling the agitation of the reaction mixture. |
| R.2.1.4 |
| Material Control |
| The system must be capable of controlling the mass flow into and out of E.1. |
| R.2.1.5 |
| Secondary Vessel |
| A secondary vessel capable of supporting E.1 during nitration chemistries and work-up steps (e.g. a quench vessel) must be installed. |
Figure 3 Batch Production Requirements
Utilize E.1 The existing equipment E.1 is suited to the purpose of energetic material synthesis generally. In order to integrate E.1 into the Pilot Plant system, several requirements must be met, see Table 3. Currently, E.1 is installed in BLDG A and must be moved to the proposed location, BLDG B. The reactor will also need to be integrated with the existing gantry, such that the top of the body of the reactor is level with the gantry platform. This will allow better access to both the bottom drain and ports on the lid. It will also be necessary to ensure secondary containment of the reactor system. Installation of E.1 will necessitate a regulatory compliance review and survey for the specified facility and room.
Table 3 Batch Production Requirements
| Requirement |
| Name |
| Description |
| R.2.1.1.1 |
| Move E.1 |
| E.1 must be moved from current location at BLDG A to BLDG B. |
| R.2.1.1.2 |
| Install E.1 |
| E.1 must be installed and integrated into existing gantry structure. The design and installation must allow and provide for the removal of the reactor lid to accommodate cleaning operations. |
| R.2.1.1.3 |
| Secondary Containment |
| A secondary containment of sufficient volume must be installed to protect against releases from E.1 and associated equipment. |
Figure 4 Utilize E.1 Requirements
Temperature Control E.1 is a jacketed reactor vessel, giving it the ability to heat or cool reaction mixtures via a liquid heat transfer medium, typically a propylene glycol-water solution. The heat transfer medium must be conditioned by heating and cooling equipment external to the reactor. E.1 is also equipped with a thermowell with three RTDs at staggered depths.
Table 4 Temperature Control Requirements
| Requirement |
| Name |
| Description |
| R.2.1.2.1 |
| Monitor Temperature |
| The system must be capable of monitoring and recording temperatures utilizing the E.1 integrated RTD thermowell, as well as inlets and outlets for heat transfer medium. The system will utilize the existing three-wire P100 RTDs (American wiring standard) in the thermowell, and appropriately specified thermocouples or RTDs elsewhere; Type K and Three-Wire P100 as defaults. |
| R.2.1.2.2 |
| Heating and Cooling |
| Temperature Range: minimum nominally -25 °C not greater than -15°C and not less than -29°C, maximum nominally 100°C not greater than 120°C and not less than 85°C. Utilize appropriate heat transfer medium suitable for use with energetic materials. Heating will utilize plant supplied, approximately 100 psi saturated steam. Cooling shall utilize domestic water for heat rejection (site precludes the use of air). Operating pressure must be no more than 125 psi, nominally 100 psi. |
Figure 5 Temperature Control Requirements
Agitation Control E.1 is equipped with an integrated agitator with an electric drive.
Table 5 Agitation Control Requirement
| Requirement |
| Name |
| Description |
| R.2.1.3 |
| Agitation Control |
| The system must be capable of monitoring, recording, and controlling the agitator speed and power. |
Material Control Requirements It will be necessary to control the mass flow into and out of the reactor. Solid, liquid, and gas streams will be required to accomplish the wide range of syntheses desired. Additionally, the reactor is equipped with a mechanical agitator, which must be electronically controlled.
Table 6 Material Control Requirements
| Requirement |
| Name |
| Description |
| R.2.1.4.1 |
| Condenser |
| The batch production system must a have a condenser of sufficient capacity to accommodate the reflux and distillation of common solvents. Specifications for condenser will be determined by designer. Maximum boiling point of solvents to be refluxed or distilled is 115°C at atmospheric pressure. Condenser shall be rated for full vacuum if determined by the designer during equipment inspection that E.1 is capable of vacuum. |
| R.2.1.4.2 |
| Solid Feed |
| The design shall include a solids feeder suitable for use with energetic materials with a nominal feed rate of 15 kg/min of material with particle size no smaller than 3 um, and bulk densities no less than 0.45 kg/L. |
| R.2.1.4.3 |
| Liquid Feed |
| The system must have the capability to add up to three liquid streams, one being domestic water, into the reactor at a specified rate. The design shall consist of an assortment of pumps (number and specifications to be determined by designer) suited to moving quantities of liquids ranging from 0.5 L to 55 gallons, capable or configurable for pumping concentrated mineral acids (supporting direct nitration), and continuous, remoted control of flowrate utilizing a loss-in-weight control loop. The pumps shall utilize standard interfaces to allow for the use of alternate pumps in the future. |
| R.2.1.4.4 |
| Pressure Regulation |
| The system must have the capability to add a reactant gas, an inert gas, and air to the reactor at a specified pressure and flowrate, as well as the capability to draw vacuum on the reactor. |
R.2.1.4.5
| Material Evacuation |
| The bottom drain valve must have remote continuous actuation capability. |
| R.2.1.4.6 |
| Level Indicator |
| The system must be capable of monitoring the fill of the reactor vessel. |
Figure 6 Material Control Requirements
Recovery Requirements In a typical recovery of a solid product, the material is physically filtered from the reaction mixture and then washed with solvent to remove impurities. Liquid products are often either extracted; mixed with a non-miscible solvent that traps contaminants or distilled, wherein the solvent or product is driven off the reaction mixture as a vapor using heat. The material can then be treated with additives to protect it, such as antioxidants, or mixed with diluting or inerting agents for shipment.
Table 7 Recovery Processes
| Requirement |
| Name |
| Description |
| R.2.3.1 |
| Filtration |
| The filtration subsystem must be a self-contained unit capable of completing all phases of a typical filtration process: slurry, caking, washing, heating, drying (with vacuum), and discharging finished product; e.g. a Nutsche-style filtration system. |
| R.2.3.2 |
| Extraction |
| The system must be capable of liquid/liquid extractions with common solvents, to be carried out in E.1. |
| R.2.3.3 |
| Distillation |
| The system must be capable of separating components of a mixture via distillation. |
Figure 7 Recovery Requirements Constraints Beyond the capability requirements of the Chemical Pilot Plant, there will be several constraints that will directly impact the contracting, design, and installation efforts. These constraints will be developed in an iterative manner, as project matures. The relevant stakeholders in each area will direct the development of these constraints.
Explosive Safety NAVSEA OP 5 Ammunition and Explosives Safety Ashore Provides explosives safety information and regulations regarding conventional ammunition, ammunition components, explosives, and related hazardous material operations at all DON facilities. Compliance with explicit safety rules and regulations specified in this publication are mandatory.
OPNAV Instruction 5530.13C Physical Security Instruction for Conventional Arms, Ammunition, and Explosives (AA&E) Provides DON policy and guidance for the protection of conventional AA&E against loss or theft.
Occupational Safety and Health OSHA 29 CFR 1910 Occupational Safety and Health Standards Federal regulator guidance including, but not limited to sections:
38 - Emergency action plans.
39 - Fire prevention plans.3. 1910.94 - Ventilation.
95 - Occupational noise exposure.
101 - Compressed gases (general requirements) 106 - Flammable liquids.
119 - Process safety management of highly hazardous chemicals.
120 - Hazardous waste operations and emergency response.
132 - General requirements.
133 - Eye and face protection.
134 - Respiratory Protection 138 - Hand Protection.
141 - Sanitation.
151 - Medical services and first aid.
157 - Portable fire extinguishers 176 - Handling materials - general.
212 - General requirements for all machines.
307 - Hazardous (classified) locations. (Electrical) 1003 - 13 Carcinogens (4-Nitrobiphenyl, etc.).
1200 - Hazard Communication.
1450 - Occupational exposure to hazardous chemicals in laboratories.
Chemical Hygiene NAWCWD Instruction 5100.7 Chemical Hygiene Plan Chemical hygiene policy and practices at the Naval Air Warfare Center, Weapons Division.
Environmental Protection Regulatory information withheld by stakeholder. Per NAWCWD Environmental Protection Specialists, environmental concerns will only be addressed after the system is fully designed and/or specified in contracts; i.e. during a Site Design Review.
Information Technology Regulatory information withheld by stakeholder. Per the NAWCWD Energetics ISSO, IT concerns will only be addressed after the system is fully designed and/or specified in contracts; i.e. during a Site Design Review.
3.2 Process Engineering Package Deliverables
The contractor shall provide a Process Engineering Package, consisting of the deliverables described in Table 7.
Table 7 Process Engineering Package Deliverables
| Deliverable |
| Name |
| Description |
| D.1.1 |
| Site Visit |
| The contractor will travel to NAWCWD for the purpose of meeting with personnel to review the requirements, obtain information, and inspect E.1 and facilities. |
| D.1.2 |
| Process Simulation |
| A process simulation will be created based on the requirements and used to determine the operating conditions that will be used to specify equipment. |
| D.1.3 |
| Process Flow Diagrams with Mass and Energy Balance |
| Process Flow Diagrams (PFDs) will be generated, including tabulated process conditions. |
| D.1.4 |
| Equipment Specifications |
| Based on the design requirements, process simulations, and PFDs, equipment will be specified and equipment data sheets generated. |
| D.1.5 |
| Piping and Instrumentation Diagrams |
| Piping and Instrumentation Diagrams will be developed to schematically depict the equipment, piping, and instrumentation. |
| D.1.6 |
| 3D Model |
| A 3D digital model will be created to show equipment and building features. |
| D.1.7 |
| Electrical Classification Drawings |
| Drawings that show the location of hazardous areas will be generated. |
| D.1.8 |
| Functional Specification |
| The control system architecture including batch sequence and controls will be described. |
| D.1.9 |
| Site Design Review |
| The contractor will present the Process Engineering Package |
| D.1.10 |
| Process Hazard Analysis |
| The contractor shall travel to NAWCWD and facilitate a Process Hazard Analysis review with NAWCWD personnel. |
| D.1.11 |
| Cost Estimate |
| The contractor shall provide a definitive cost estimate (also known as a Project Control estimate) for the detailed design and installation of the system. |
| D.1.12 |
| Schedule |
| The contractor shall provide a project schedule for the detailed design and installation of the system. |
4.0 Contractor Requirement
| Contractor must be able to provide personnel who can obtain access to NAWCWD China Lake in order to complete deliverable D.1.1 Site Visit. Eligible personnel must be U.S. citizens and must be able to pass the appropriate background check. |
| Contractor must have previous experience with the designing and implementation of chemical/manufacturing facilities on DOD installations. |
5.0 Schedule Requirement
Contractor must be able to provide completed Process Engineering Package within 18 weeks of contract award.
6.0 Conclusion
This Statement of Work describes the Navy’s need for a Process Engineering Package supporting a Capital Improvement Project to modernize the NAWCWD Chemical Pilot Plant. The Process Engineering package is defined as a set of deliverables, which in turn are based on a set of design requirements, both described herein.
image3.emf
Microsoft_Visio_Drawing12.vsdx image4.emf image5.emf image6.emf image7.emf image1.emf
Microsoft_Visio_Drawing1.vsdx image2.emf
File details come from the government source that posted it.