N6893617R0049
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| MAX QUANTITY |
| UNIT |
| UNIT PRICE |
| MAX AMOUNT |
Labor
CPFF
The Contractor shall provide Resources and Survey Analysis (Labor) in accordance with Attachment 1, SOW.
FOB: Destination
PURCHASE REQUEST NUMBER: 1300645773
MAX COST
FIXED FEE
TOTAL MAX COST + FEE
| ITEM NO |
| SUPPLIES/SERVICES |
| MAX QUANTITY |
| UNIT |
| UNIT PRICE |
| MAX AMOUNT |
Other Direct Costs (ODCs)
COST
The Contractor shall provide materials and conduct travel in accordance with Attachment 1, SOW.
MAX COST
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Technical Data
FFP
The Contractor shall provide technical data in accordance with Exhibit A, DD Form 1423, Contract Data Requirements List (CDRL).
NET AMT
CLAUSES INCORPORATED BY FULL TEXT
| 5252.211-9503 | LEVEL OF EFFORT (COST REIMBURSEMENT) (NAVAIR)(DEC 2012) |
| (a) The level of effort (LOE) estimated to be ordered during the term of this contract is 211,200 man-hours of direct labor including authorized subcontract labor, if any. The contractor shall not, under any circumstances, exceed one hundred (100%) percent of the total level of effort specified in this basic contract. The estimated composition of the total man-hours of direct labor by classification is as follows: |
| Labor Category |
| Estimated LOE |
| Supervisory Archeologist* |
| 9,600 |
| Administrative Assistant |
| 9,600 |
| Curation Specialist |
| 9,600 |
| Field Archeologist |
| 19,200 |
| Environmental Specialist |
| 9,600 |
| Natural Resource Specialist |
| 9,600 |
| Total Estimated LOE |
| 211,200 |
* denotes Key Personnel labor categories
| (b) FAR Clause 52.232-20, "Limitation of Cost" applies to fully funded orders and FAR Clause 52.232-22, "Limitation of Funds" applies to incrementally funded orders. Nothing in this clause amends the rights or responsibilities of the parties hereto under either of those two clauses. In addition, the notifications required by this clause are separate and distinct from any specified in either FAR Clause 52.232-20 or FAR Clause 52.232-22. | |
| (c) In the event that less than one hundred (100%) percent of the established level of effort of the contract/order is actually expended by the end of the performance period, the Government shall have the option of: | |
| (1) Requiring the Contractor to continue performance, subject to the provisions of the FAR Clause 52.232-20 or 52.232-22, as applicable, until the effort expended equals 100% of the established Level of Effort; or |
| (2) Effecting a reduction in the fixed fee by the percentage by which the total expended man-hours is less than one hundred (100%) percent of the established Level of Effort. |
| (d) The contractor agrees that effort performed in fulfillment of level of effort obligations under this contract shall include only verifiable effort in direct support of the work specified. It shall not include efforts such as work performed in transit to or from an employee's usual workplace, work during lunchtime activities, or effort performed at other non-work locations. | |
| (e) In performing the contract/order, the contractor may use any reasonable combination of hours for the labor categories in support of section C of this contract/order. | |
Section C - Descriptions and Specifications
C-TXT-ECMRA REQUIRED ENTERPRISE-WIDE CONTRACTOR MANPOWER REPORTING APPLICATION (ECMRA) INFORMATION (NOV 2017)
| The contractor shall report contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for NAVAIR via a secure data collection site. Contracted services, excluded from reporting are based on Product Service Codes (PSCs). The excluded PSCs are: | |
| (1) W, Lease/Rental of Equipment; |
| (2) X, Lease/Rental of Facilities; |
| (3) Y, Construction of Structures and Facilities; |
| (4) D, Automatic Data Processing and Telecommunications, IT and Telecom - Telecommunications Transmission (D304) and Internet (D322) ONLY. |
| (5) S, Utilities ONLY; |
| (6) V, Freight and Shipping ONLY. |
| The contractor is required to completely fill in all required data fields using the following web address "https://www.ecmra.mil.” | |
| Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at "https://www.ecmra.mil.” | |
Section D - Packaging and Marking
| 5252.247-9507 | PACKAGING AND MARKING OF REPORTS (NAVAIR)(OCT 2005) | |
| (a) All unclassified data shall be prepared for shipment in accordance with best commercial practice. Classified reports, data and documentation, if any, shall be prepared for shipment in accordance with the National Industry Security Program Operating Manual, DoD 5220.22-M. | |
| (b) The contractor shall prominently display on the cover of each report the following information: | |
| | (1) Name and business address of contractor. |
| | (2) Contract Number/Delivery/Task order number. |
| | (3) Contract/Delivery/Task order dollar amount. |
| | (4) Whether the contract was competitively or non-competitively awarded. |
| | (5) Name of sponsoring individual. |
| | (6) Name and address of requiring activity. |
| 5252.247-9508 | PROHIBITED PACKING MATERIALS (NAVAIR)(JUN 1998) |
| The use of asbestos, excelsior, newspaper or shredded paper (all types including waxed paper, computer paper and similar hydroscopic or non-neutral material) is prohibited. In addition, loose fill polystyrene is prohibited for shipboard use. |
| 5252.247-9514 | TECHNICAL DATA PACKING INSTRUCTIONS (NAVAIR)(SEP 1999) |
| Technical Data and Information shall be packed and packaged for domestic shipment in accordance with best commercial practices. The package or envelope should be clearly marked with any special markings specified in this contract (or delivery/task order), e.g., Contract Number, CLIN, Device No., and document title must be on the outside of the package. Classified reports, data and documentation, if applicable, shall be prepared for shipment in accordance with Defense Industrial Manual for Safeguarding Classified Information, DoD 5220.22M. |
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| Destination |
| Government |
| Destination |
| Government |
| 0002 |
| Destination |
| Government |
| Destination |
| Government |
| 0003 |
| Destination |
| Government |
| Destination |
| Government |
CLAUSES INCORPORATED BY REFERENCE
| 52.246-5 |
| Inspection Of Services Cost-Reimbursement |
| APR 1984 |
| 5252.246-9514 | INSPECTION AND ACCEPTANCE OF TECHNICAL DATA AND INFORMATION (NAVAIR)(FEB 1995) |
| Inspection and acceptance of technical data and information will be performed by the Procuring Contracting Officer (PCO) or his duly authorized representative. Inspection of technical data and information will be performed by ensuring successful completion of the requirements set forth in the DD Form 1423, Contract Data Requirements List (CDRL) and incorporation/resolution of Government review comments on the data items. Acceptance will be evidenced by execution of an unconditional DD Form 250, Material Inspection and Receiving Report, as appropriate, and/or upon receipt of a second endorsement acceptance by the PCO on the attachment to this contract entitled Exhibit A, CDRLs. The attached form will not be used for high cost data such as drawings, specifications, and technical manuals. |
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC / CAGE |
06-NOV-2023
06-NOV-2023
| 52.242-15 Alt I |
| Stop-Work Order (Aug 1989) - Alternate I |
| APR 1984 |
| 5252.211-9507 | PERIOD OF PERFORMANCE (NAVAIR)(SEP 2013) |
| (a) The contract shall commence on [insert effective date] and shall continue [insert either "for a period of months" or provide a calendar date ]. However, the period of performance may be extended in accordance with the option provisions contained herein. |
| (b) If DFAR Clause 252.216-7006, "Ordering", is incorporated into this contract, then the period in which the Government can issue orders under the contract will be extended at the exercise of an option, and extended to the end of that option period. |
*To be completed at contract award.
| 5252.216-9506 | MINIMUM AND MAXIMUM QUANTITIES (NAVAIR)(MAR 1999) |
| As referred to in paragraph (b) of FAR 52.216-22 " Indefinite Quantity" of this contract, the contract minimum quantity is $10,000; the maximum quantity is [*]. |
| 5252.247-9505 | TECHNICAL DATA AND INFORMATION (NAVAIR)(FEB 1995) | |
| Technical Data and Information shall be delivered in accordance with the requirements of the Contract Data Requirements List, DD Form 1423, Exhibit A, attached hereto, and the following: | |
| (a) The contractor shall concurrently deliver technical data and information per DD Form 1423, Blocks 12 and 13 (date of first/subsequent submission) to all activities listed in Block 14 of the DD Form 1423 (distribution and addresses) for each item. Complete addresses for the abbreviations in Block 14 are shown in paragraph (g) below. Additionally, the technical data shall be delivered to the following cognizant codes, who are listed in Block 6 of the DD Form 1423. | |
| | (1) PCO, Code [insert code]. |
| | (2) ACO, Code [insert code]. |
| | [insert additional code addresses, as necessary] |
| (b) Partial delivery of data is not acceptable unless specifically authorized on the DD Form 1423, or unless approved in writing by the PCO. | |
| (c) The Government review period provided on the DD Form 1423 for each item commences upon receipt of all required data by the technical activity designated in Block 6. | |
| (d) A copy of all other correspondence addressed to the Contracting Officer relating to data item requirements (i.e., status of delivery) shall also be provided to the codes reflected above and the technical activity responsible for the data item per Block 6, if not one of the activities listed above. | |
| (e) The PCO reserves the right to issue unilateral modifications to change the destination codes and addresses for all technical data and information at no additional cost to the Government. | |
| (f) Unless otherwise specified in writing, rejected data items shall be resubmitted within thirty (30) days after receipt of notice of rejection. | |
| (g) DD Form 1423, Block 14 Mailing Addresses: [insert the abbreviation and mailing address to match] | |
Section G - Contract Administration Data
| 252.204-7006 |
| Billing Instructions |
| OCT 2005 |
| 252.232-7006 | WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013) | |
| (a) Definitions, as used in this clause-- | |
| "Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization. | |
| "Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF). | |
| "Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system. | |
| (b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports. | |
| (c) WAWF access. To access WAWF, the Contractor shall-- | |
| | (1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and |
| | (2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site. |
| (d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/. | |
| (e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol. | |
| (f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order: | |
| | (1) Document type. The Contractor shall use the following document type(s). |
| ___________________________________________________________________________ | |
| (Contracting Officer: Insert applicable document type(s). Note: If a "Combo" document type is identified but not supportable by the Contractor's business systems, an "Invoice" (stand-alone) and "Receiving Report" (stand-alone) document type may be used instead.) | |
| | (2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer. |
| ___________________________________________________________________________ | |
| (Contracting Officer: Insert inspection and acceptance locations or "Not applicable.") | |
| | (3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system. |
| Routing Data Table* | | | | |
| Field Name in WAWF | | | Data to be entered in WAWF | |
| Pay Official DoDAAC: | | | _________________________ | |
| Issue By DoDAAC: | | | _________________________ | |
| Admin DoDAAC: | | | _________________________ | |
| Inspect By DoDAAC: | | | _________________________ | |
| Ship To Code: | | | | _________________________ |
| Ship From Code: | | | _________________________ | |
| Mark For Code: | | | _________________________ | |
| Service Approver (DoDAAC): | | _________________________ | | |
| Service Acceptor (DoDAAC): | | _________________________ | | |
| Accept at Other DoDAAC: | | _________________________ | | |
| LPO DoDAAC: | | | _________________________ | |
| DCAA Auditor DoDAAC: | | _________________________ | | |
| Other DoDAAC(s): | | | _________________________ | |
| (*Contracting Officer: Insert applicable DoDAAC information or "See schedule" if multiple ship to/acceptance locations apply, or "Not applicable.") | | | | |
| (4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request. | | | |
| (5) WAWF email notifications. The Contractor shall enter the email address identified below in the "Send Additional Email Notifications" field of WAWF once a document is submitted in the system. | | | |
(Contracting Officer: Insert applicable email addresses or "Not applicable.")
| (g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact. For Navy WAWF questions call DFAS Customer Care 1-800-756-4571 option 6 | |
| (2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988. |
| 5252.201-9501 | DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE (COR) (NAVAIR)(SEP 2012) |
| (a) The Contracting Officer has designated [insert name, mailing address, code, and telephone number] as the authorized Contracting Officer's Representative (COR) to perform the following functions, duties, and/or responsibilities:[Insert functions, duties, and/or responsibilities of the COR]. |
| (b) The effective period of the COR designation is [insert "the period of performance of this contract" OR "from _______ to ________."] |
| 5252.204-9503 | EXPEDITING CONTRACT CLOSEOUT (NAVAIR) (JAN 2007) |
| (a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $1,000 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party might be considered to the extent permitted by law. |
| (b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered. |
| 5252.232-9510 | PAYMENT OF FIXED FEE (NAVAIR) (OCT 2005) |
| (a) The fixed fee, as specified in Section B of this contract, subject to any adjustment required by other provisions of this contract, will be paid in installments. The fixed fee will be paid not more frequently than bi-weekly based on the allowable cost. The amount of each such installment shall be in the same ratio to the total fixed fee as the dollars per hour (based on the fixed fee divided by the level of effort in hours) for CLIN 0001. Payment shall be made in accordance with FAR Clauses 52.216-7, "Allowable Cost and Payment," and 52.216-8, "Fixed Fee." |
| (b) In the event of termination of the work in accordance with the FAR Clause 52.232-22, "Limitation of Funds," the fixed fee shall be redetermined by mutual agreement equitably to reflect the reduction of the work performed. The amount by which such fixed fee is less than or exceeds payments previously made on account of fee, shall be paid to (or repaid by) the contractor. |
| (c) The balance of the fixed fee shall be payable in accordance with other clauses of this contract. |
| (d) For indefinite delivery type contracts the terms of this clause apply to each delivery/task order there under. |
| 5252.242-9511 | CONTRACT ADMINISTRATION DATA (NAVAIR)(NOV 2017) | |
| (a) Contract Administration Office. | |
| | (1) Contract administration functions (see FAR 42.302(a) and DFARS 242.302(a)) are assigned to: See the ADMINISTERED BY Block on the face page of the contract, modification, or order. |
| (b) Special Instructions (see FAR 42.202(b) and (c)): | |
| | (1) The following contract administration functions are retained (see FAR 42.302(a) and DFARS 242.302(a)): |
| | Functions Retained |
| Retained for Performance By: | |
| [Insert function from FAR 42.302(a) or DFARS 242.302(a)] |
| [Insert PCO, COR, Requiring Activity, or TPOC for each function.] |
[Repeat as necessary.
(2) The following additional contract administration functions are assigned (see FAR 42.302(b)):
| Additional Functions |
| Retained for Performance By: |
| [Insert function from FAR 42.302(b) or other function identified as necessary for administration of the contract.] |
| [Insert "See the ADMINISTERED BY Block on the face page of the contract, modification or order," PCO, COR, Requiring Activity, or TPOC for each function.] |
[Repeat as necessary.
(c) Inquiries regarding payment should be referred to: MyInvoice through the Wide Area Workflow eBusiness Suite: https://wawf.eb.mil.
| G-TXT-0001 | PAYMENT INSTRUCTIONS (FEB 2018) |
| FOR GOVERNMENT USE ONLY |
| Contract/Order Payment Clause |
| Type of Payment Request |
| Supply |
| Service |
| Construction |
| Payment Office |
Allocation Method
52.212-4 (Alt I), Contract Terms and Conditions—Commercial Items 52.216-7, Allowable Cost and Payment 52.232-7, Payments under Time-and-Materials and Labor-Hour Contracts
| Cost Voucher |
| X |
| X |
| N/A |
| Line item specific proration. If there is more than one ACRN within a deliverable line or deliverable subline item, the funds will be allocated in the same proportion as the amount of funding currently unliquidated for each ACRN on the deliverable line or deliverable subline item for which payment is requested. |
| 52.232-1, Payments |
| Navy Shipbuilding Invoice (Fixed Price) |
| X |
| N/A |
| N/A |
| Line Item specific by fiscal year. If there is more than one ACRN within a deliverable line or deliverable subline item, the funds will be allocated using the oldest funds. In the event of a deliverable line or deliverable subline item with two ACRNs with the same fiscal year, those amounts will be prorated to the available unliquidated funds for that year. |
52.232-1, Payments;
52.232-2, Payments under Fixed-Price Research and Development Contracts;
52.232-3, Payments under Personal Services Contracts;
52.232-4, Payments under Transportation Contracts and Transportation-Related Services Contracts; and 52.232-6, Payments under Communication Service Contracts with Common Carriers
| Invoice |
| X |
| X |
| N/A |
| Line Item Specific proration. If there is more than one ACRN within a deliverable line or deliverable subline item, the funds will be allocated in the same proportion as the amount of funding currently unliquidated for each ACRN on the deliverable line or deliverable subline item for which payment is requested. |
| 52.232-5, Payments Under Fixed-Price Construction Contracts |
| Construction Payment Invoice |
| N/A |
| N/A |
| X |
| Line Item specific by fiscal year. If there is more than one ACRN within a deliverable line or deliverable subline item, the funds will be allocated using the oldest funds. In the event of a deliverable line or deliverable subline item with two ACRNs with the same fiscal year, those amounts will be prorated to the available unliquidated funds for that year. |
| 52.232-16, Progress Payments |
| Progress Payment* |
| X |
| X |
| N/A |
| Contract-wide proration. Funds shall be allocated in the same proportion as the amount of funding currently unliquidated for each ACRN. Progress Payments are considered contract level financing, and the “contract price” shall reflect the fixed price portion of the contract per FAR 32.501-3. |
52.232-29, Terms for Financing of Purchases of Commercial Items;
52.232-30, Installment Payments for Commercial Items
| Commercial Item Financing* |
| X |
| X |
| N/A |
| Specified in approved payment. The contracting officer shall specify the amount to be paid and the account(s) to be charged for each payment approval in accordance with FAR 32.207(b)(2) and 32.1007(b)(2). |
| 52.232-32, Performance-Based Payments |
| Performance-Based Payments* |
| X |
| X |
| N/A |
| Specified in approved payment. The contracting officer shall specify the amount to be paid and the account(s) to be charged for each payment approval in accordance with FAR 32.207(b)(2) and 32.1007(b)(2). |
| 252.232-7002, Progress Payments for Foreign Military Sales Acquisitions |
| Progress Payment* |
| X |
| X |
| N/A |
| Allocate costs among line items and countries in a manner acceptable to the Administrative Contracting Officer. |
*Liquidation of Financing Payments. Liquidation will be applied by the payment office against those ACRNs which are identified by the payment instructions for the delivery payment and in keeping with the liquidation provision of the applicable contract financing clause (i.e., progress payment, performance-based payment, or commercial item financing).
| G-TXT-03 | CONTRACTOR ACCESS TO NAVAL AIR WARFARE CENTER WEAPONS DIVISION CHINA LAKE |
| Contractors requiring access to the Naval Air Warfare Center Weapons Division China Lake are required to enroll with RAPIDGate or obtain a day pass from the Pass and ID Office. The Government will not be responsible for work delays or work stoppages due to failure to comply with these access requirements. Questions should be directed to Tina Todd at (760)939-3154. |
| G-TXT-06 | SECURITY ASSIGNMENT (APR 2002) |
| Defense Security Service, * is hereby assigned administrative responsibility for safeguarding classified information. |
(* To be completed at contract award.)
Section H - Special Contract Requirements
| 5252.204-9502 | REQUIREMENTS FOR LOCAL SECURITY SYSTEM (NAVAIR)(OCT 2005) |
| The contractor agrees to provide locator information regarding all employees requiring a permanent badge for authorized entrance to the Naval Air Weapons Stations China Lake, CA. Entrance is authorized by this contract as a result of tasks associated with performance of the Statement of Work only. Initial information shall be provided as each individual is assigned to this contract by using the Locator Form provided as an attachment to this contract. Thereafter, quarterly reports (due at the beginning of each quarter by the fifth day of the month) will be provided with gains/losses (identification of new and replaced or added individuals) and any changes to current personnel (such as telephone number, building number and room number). A point of contact is to be named on each quarterly report for any questions/additional information needed by the Government recipient. The quarterly reports are to be addressed to [*]. All losses are to have the permanent badges returned to [*] on the last day of the individual's task requirement. |
* To be completed at contract award.
| 5252.204-9505 | SYSTEM AUTHORIZATION ACCESS REQUEST NAVY (SAAR-N) REQUIREMENTS FOR INFORMATION TECHNOLOGY(IT) (NAVAIR)(NOV 2017) |
| (a) Contractor personnel assigned to perform work under this contract may require access to Navy Information Technology (IT) resources (e.g., computers, laptops, personal electronic devices/personal digital assistants (PEDs/PDAs), NMCI, RDT&E networks, websites such as MyNAVAIR, and Navy Web servers requiring Common Access Card (CAC) Public Key Infrastructure (PKI)). Contractor personnel (prime, subcontractor, consultants, and temporary employees) requiring access to Navy IT resources (including those personnel who previously signed SAAR DD Form 2875) shall submit a completed System Authorization Access Request Navy (SAAR-N), OPNAV 5239/14 (Jul 2008) form or latest version thereof, and have initiated the requisite background investigation (or provide proof of a current background investigation) prior to accessing any Navy IT resources. The form and instructions for processing the SAAR-N form are available at: https://navalforms.documentservices.dla.mil/formsDir/_OPNAV_5239_14_7631.pdf. Instruction Note: SAAR-N forms are required to be downloaded and then completed. The "E-MAIL SUBMIT" button on the SAAR-N form is not to be used. |
| (b) SAAR-N forms will be submitted to the Government Sponsor or Technical Point of Contact (TPOC) via the contractor's Facility Security Officer (FSO). The designated SAAR-N Government Sponsor or TPCO for contractor employees requiring IT access, [fill-in name] shall be responsible for signing and processing the SAAR-N forms. For those contractors that do not have a FSO, SAAR-N forms shall be submitted directly to the designated SAAR-N Government Sponsor or TPOC. Copies of the approved SAAR-N forms may be obtained through the designated SAAR-N Government Sponsor or TPOC. Requests for access should be routed through the NAVAIR_SAAR.fct@navy.mil mailbox. |
| (c) In order to maintain access to Navy IT resources, the contractor shall ensure completion of initial and annual IA training, monitor expiration of requisite background investigations, and initiate re-investigations as required. If requested, the contractor shall provide to the designated SAAR-N Government Sponsor or TPOC documentation sufficient to prove that it is monitoring/tracking the SAAR-N requirements for its employees who are accessing Navy IT resources. For those contractor personnel not in compliance with the requirements of this clause, access to Navy IT resources will be denied/revoked. |
| (d) The SAAR-N form remains valid throughout contractual performance, inclusive of performance extensions and option exercises where the contract number does not change. Contractor personnel are required to submit a new SAAR-N form only when they begin work on a new or different contract. |
| 5252.211-9502 | GOVERNMENT INSTALLATION WORK SCHEDULE (NAVAIR)(DEC 2014) |
| (a) The Holidays applicable to this contract are: New Year's Day, Martin Luther King's Birthday, Presidents' Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, and Christmas Day. |
| (b) In the event that any of the above holidays occur on a Saturday or Sunday, or alternate Friday, then such holiday shall be observed as they are by the assigned Government employees at the using activity. |
| (c) The Naval Air Warfare Center Weapons Division works a 4/5/9 work schedule. Therefore alternate Fridays are not a part of the normal workweek for work performed on-site at a Naval Air Warfare Center Weapons Division site. The majority of the Government offices are closed on alternate Fridays. |
| (d) No deviation in the normal workweek will be permitted without express advance approval by the designated Contracting Officer with coordination of the using departments. |
| 5252.211- 9510 | CONTRACTOR EMPLOYEES (NAVAIR)(MAY 2011) | |
| (a) In all situations where contractor personnel status is not obvious, all contractor personnel are required to identify themselves to avoid creating an impression to the public, agency officials, or Congress that such contractor personnel are Government officials. This can occur during meeting attendance, through written (letter or email) correspondence or verbal discussions (in person or telephonic), when making presentations, or in other situations where their contractor status is not obvious to third parties. This list is not exhaustive. Therefore, the contractor employee(s) shall: | |
| | (1) Not by word or deed give the impression or appearance of being a Government employee; |
| | (2) Wear appropriate badges visible above the waist that identify them as contractor employees when in Government spaces, at a Government-sponsored event, or an event outside normal work spaces in support of the contract/order; |
| | (3) Clearly identify themselves as contractor employees in telephone conversations and in all formal and informal written and electronic correspondence. Identification shall include the name of the company for whom they work; |
| | (4) Identify themselves by name, their company name, if they are a subcontractor the name of the prime contractor their company is supporting, as well as the Government office they are supporting when participating in meetings, conferences, and other interactions in which all parties are not in daily contact with the individual contractor employee; and |
| | (5) Be able to provide, when asked, the full number of the contract/order under which they are performing, and the name of the Contracting Officer’s Representative. |
| (b) If wearing a badge is a risk to safety and/or security, then an alternative means of identification maybe utilized if endorsed by the Contracting Officer’s Representative and approved by the Contracting Officer. | |
| (c) The Contracting Officer will make final determination of compliance with regulations with regard to proper identification of contractor employees. | |
| 5252.216-9512 | PAPERLESS CONTRACTING (NAVAIR)(JUN 2009) |
| (a) Orders and requests for proposals are hereby authorized to be issued by facsimile or by electronic commerce (including e-mail and paperless methods of delivery). Nothing in this contract should be read to prohibit these types of orders. In the event of a conflict with any other provision of this contract, this clause shall govern. |
| (b) To the extent the terms "written", "mailed", or "physically delivered" appear in other provisions of this contract, these terms are hereby defined to explicitly include electronic commerce, email, or paperless delivery methods. |
| 5252.216-9534 | TASK ORDER PROCEDURES (NAVAIR)(OCT 2005) |
| (a) The following activity (ies) or individual(s) is/are designated as Ordering Officer(s): |
| The above activity (ies) or individual(s) is/are responsible for issuing and administering any orders placed hereunder. Ordering Officers may negotiate revisions/modifications to orders, but only within the scope of this contract. Ordering Officers have no authority to modify any provision of this basic contract. Any deviation from the terms of the basic contract must be submitted to the Procuring Contracting Officer (PCO) for contractual action. Ordering Officers may enter into mutual no cost cancellations of orders under this contract and may reduce the scope of orders/tasks, but a Termination for Convenience or Termination for Default may only be issued by the PCO. | | |
| (b) Task orders. All orders issued hereunder are subject to the terms and conditions of this contract. The contract shall control in the event of conflict with any order. When mailed, an order shall be "issued" for purposes of this contract at the time the Government deposits the order in the mail, or, if transmitted by other means, when physically delivered to the contractor. | | |
| (c) A task order shall be issued for each order. In addition to any other data that may be called for in the contract, the following information shall be specified in each order, as applicable: | | |
| (1) Date of order. | |
| (2) Contract and task order number. | |
| (3) Applicable contract line item number (CLIN). | |
| (4) Description of the task to be performed. | |
| (5) Description of the end item or service. | |
| (6) DD Form 254 (Contract Security Classification). | |
| (7) DD Form 1423 (Contract Data Requirements List). | |
| (8) Exact place of performance. | |
| (9) The inspecting and accepting codes. | |
| (10) Estimated cost and fee and level of effort by labor category (and billing rate if known). | |
| (11) List of Government furnished property and the estimated value of the property. | |
| (12) Invoice and payment provisions to the extent not covered by the contract. | |
| (13) Accounting and appropriation data. | |
| (14) Period of performance. | |
| (15) Organizational Conflict of Interest provisions. | |
| (16) Type of order (e.g., completion, term, FFP) | |
| (d) Negotiated Agreement. For task orders with an estimated value of greater than $1,000,000, the information contained in each task order with respect to labor categories, man-hours and delivery date shall be the result of a negotiated agreement reached by the parties in advance of issuance of the order. | | |
| (1) The Ordering Officer shall furnish the contractor with a written preliminary task order and request for proposal. The request shall include: | |
| | (i) a description of the specified work required, |
| | (ii) the desired delivery schedule, |
| | (iii) the place and manner of inspection and acceptance, and |
| (2) The contractor shall, within the time specified by the preliminary task order, provide the Ordering Officer with a proposal to perform, which shall include: | |
| | (i) the required number of labor hours by labor classification and scheduled billing rates, for each end product or task, |
| | (ii) overtime hours by labor category, |
| | (iii) proposed completion or delivery dates, |
| | (iv) other direct costs (i.e., direct material, travel subsistence, and similar costs) |
| | (v) dollar amount and type of any proposed subcontracts, and |
| | (vi) total estimated cost/price. |
The cost factors utilized in determining the estimated cost/price under any order shall be the rates applicable at time the order is issued.
| (3) Upon receipt of the proposal, the Ordering Officer shall review the estimates therein to ensure acceptability to the Government, enter into such discussions with the contractor as may be necessary to correct and revise any discrepancies in the proposal, and effect whatever internal review procedures are required. Should the Ordering Officer and contractor be unable to reach agreement as to the terms of the order prior to its issuance, the conflict shall be referred to the Contracting Officer. | | |
| (4) For task orders under the dollar amount indicated in paragraph (d), the procedures for reaching agreement are as follows: | | |
| | (i) The Ordering Officer shall issue a fully funded, unilaterally executed task order representing a firm order for the total requirement. | |
| | (ii) In the event the contractor cannot perform in accordance with the terms and conditions and within the estimated cost of the task order, he shall: | |
| | | (A) notify the Ordering Officer immediately, |
| | | (B) submit a proposal for the work requested in the task order, |
| | | (C) not commence performance until such time that differences between the task order and the contractor's proposal are resolved and a modification, if necessary, is issued. |
| (e) Total Estimated Dollar Amount. The total estimated dollar amount of each order constitutes a ceiling price for that order. The requirements for notification set forth in Federal Acquisition Regulation paragraph (c) of FAR Clause 52.232-22, Limitation of Funds are applicable to individual task orders. The ceiling amount for each order may not be exceeded unless authorized by a modification to the order. All revisions providing additional funds to a task order will include fee in the same manner as established in the basic task order. | | | |
| (f) Oral Orders. Oral orders may be placed hereunder only in emergency circumstances. Information described above shall be furnished to the contractor at the time of placing an oral order and shall be confirmed by issuance of a written task order within 30 working days of the oral order. | | | |
| (g) Modifications. Modifications to orders shall be issued using a Standard Form 30 and shall include the information set forth in paragraph (c) above, as applicable. Orders may be modified orally by the Ordering Officer in emergency circumstances. (Oral modifications shall be confirmed by issuance of a written modification on Standard Form 30 within 30 working days from the time of the oral communication amending the order.) | | | |
| 5252.216-9540 | ISSUANCE OF ORDERS USING STREAMLINED PROCEDURES (NAVAIR)(NOV 2003) | | |
| (a) Unless the procedures in paragraphs (b) and (c) are utilized orders will be issued under this contract using the following streamlined procedures: | | |
| | (1) For each proposed order, the contracting officer will provide the contractor with a statement of work (SOW) and an independent Government cost estimate (IGCE). | |
| | (2) Within three (3) working days of receipt of the SOW and IGCE, the contractor will respond with a confirmation letter agreeing to perform the SOW within the IGCE. If the requirement remains valid and the contracting officer determines the IGCE to represent a fair and reasonable price, a fully negotiated, priced order will be issued to the contractor. | |
| | (3) If the contractor does not agree with the SOW and/or IGCE, a proposal will be submitted to the contracting officer within five (5) working days of receipt of the SOW and IGCE, addressing only the specific areas of differences. Once the differences are resolved between the contracting officer and the contractor, and the contracting officer determines that the price is fair and reasonable, a fully negotiated, priced order will be issued to the contractor. | |
| (b) There may be occasions when the Government determines, in circumstances of emergency or exigency, that the need for specific supplies or services is unusually urgent. On such occasions, the Ordering Officer may issue an order based solely on the Government estimate, requiring the contractor to provide the supplies or services specified without having an opportunity to review the Government estimate before the order is issued. This type of order shall be a unilaterally unpriced order. | | |
| | (1) The unilaterally unpriced order shall specify the estimated cost and fee and the desired delivery schedule for the work being ordered. The Government's desired delivery shall apply unless the Ordering Officer receives written notification from the Contractor within fifteen (15) days after receipt of the order that the proposed delivery schedule is not acceptable. Such notification shall propose an alternative delivery schedule. The Contractor shall either provide written acceptance of the order or submit its cost proposal within thirty (30) days after receipt of the order. | |
| | (2) The Government has no obligation to pay for the supplies or services ordered until the actual price and delivery schedule have been negotiated. In no event shall the costs incurred exceed the estimated cost of the order. | |
| | (3) The contractor shall include in its proposal a statement of costs incurred and an estimate of costs expected to complete the work. Data supporting the accuracy and reliability of the cost estimate should also be included. After submission of the contractor's cost proposal and supporting data, the contractor and the Ordering Officer shall negotiate a bilateral modification to the original order finalizing the price and delivery schedule. | |
| | (4) Should the Ordering Officer and the contractor be unable to reach an agreement as to the terms of the order, the conflict shall be referred to the Contracting Officer who shall issue such direction as is required by the circumstances. If a bilateral agreement is not negotiated within sixty (60) days after submission of the contractor's cost proposal, the Contracting Officer will issue a modification to the unilaterally unpriced order that establishes the Government's total estimated cost for the order. This price will remain in effect unless the contractor requests to negotiate the price by submission of a proposal. | |
| | (5) Failure to arrive at an agreement shall be considered a dispute in accordance with the clause entitled "Disputes". | |
| (c) For orders under $100,000, the procedures for reaching agreement are as follows: | | |
| | (1) The Ordering Officer shall issue a fully funded, unilaterally executed order representing a firm order for the total requirement. | |
| | (2) In the event the contractor cannot perform in accordance with the terms and conditions and within the estimated cost of the order, the contractor shall: | |
| | | (i) notify the Ordering Officer with in three working days |
| | | (ii) submit a proposal for the work requested in the order, |
| | | (iii) not commence performance until such time that the differences between the order and contractor's proposal are resolved and a modification, if necessary, is issued. |
| 5252.227-9511 | DISCLOSURE, USE AND PROTECTION OF PROPRIETARY INFORMATION (NAVAIR)(FEB 2009) |
| (a) During the performance of this contract, the Government may use an independent services contractor (ISC), who is neither an agent nor employee of the Government. The ISC may be used to conduct reviews, evaluations, or independent verification and validations of technical documents submitted to the Government during performance. |
| (b) The use of an ISC is solely for the convenience of the Government. The ISC has no obligation to the prime contractor. The prime contractor is required to provide full cooperation, working facilities and access to the ISC for the purposes stated in paragraph (a) above. |
| (c) Since the ISC is neither an employee nor an agent of the Government, any findings, recommendations, analyses, or conclusions of such a contractor are not those of the Government. |
| (d) The prime contractor acknowledges that the Government has the right to use ISCs as stated in paragraph (a) above. It is possible that under such an arrangement the ISC may require access to or the use of information (other than restricted cost or pricing data), which is proprietary to the prime contractor. |
| (e) To protect any such proprietary information from disclosure or use, and to establish the respective rights and duties of both the ISC and prime contractor, the prime contractor agrees to enter into a direct agreement with any ISC as the Government requires. A properly executed copy (per FAR 9.505-4) of the agreement will be provided to the Procuring Contracting Officer. |
| 5252.228-9501 | LIABILITY INSURANCE (NAVAIR) (MAR 1999) |
| The following types of insurance are required in accordance with the clause entitled, 52.228-7,"Insurance--Liability to Third Persons" and shall be maintained in the minimum amounts shown: |
| (a) Comprehensive General Liability: $200,000 per person and $500,000 per accident for bodily injury. |
| (b) Automobile Insurance: $200,000 per person and $500,000 per accident for bodily injury and $500,000 per accident for property damage. |
| (c) Standard Workman's Compensation and Employer's Liability Insurance (or, where maritime employment is involved, Longshoremen's and Harbor Worker's Compensation Insurance) in the minimum amount of $100,000. |
| (d) Aircraft public and passenger liability: $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability; $200,000 per occurrence for property damage. Passenger bodily injury liability limits of $200,000 per passenger, multiplied by the number of seats or number of passengers, whichever is greater. |
| 5252.232-9509 | TRAVEL APPROVAL AND REIMBURSEMENT PROCEDURES (NAVAIR)(OCT 2013) | |
| (a) General. Performance under this contract may require travel by Contractor personnel. If travel, domestic or overseas, is required, the Contractor is responsible for making all necessary arrangements for its personnel. These include but are not limited to: medical examinations, immunizations, passports/visas/etc., and security clearances. | |
| (b) Travel Approval Process. Prior approval is required for all travel under this contract. Travel shall be reviewed and approved/disapproved as follows: | |
| | (1) The Contractor shall provide the [Insert Procuring Contracting Officer (PCO) or Contracting Officer's Representative (COR)] a written request for authorization to travel at least 30 days in advance of the required travel date, when possible. The request should include: purpose of travel, location, travel dates, number of individuals traveling, and all estimated costs associated with the travel (e.g., lodging, meals, transportation costs, incidental expenses, etc.). |
| | (2) The [Insert PCO or COR] will review the travel request and provide, in writing, an approval or disapproval of the travel request to the Contractor [Insert "and the Procuring Contracting Officer." if the COR is reviewing and approving the request.] |
| (c) Travel Policy. | |
| | (1) Travel arrangements shall be planned in accordance with the Federal Travel regulations, prescribed by the General Services Administration for travel in the conterminous 48 United States, (hereinafter the FTR) and the Joint Travel Regulation, Volume 2, DoD Civilian Personnel, Appendix A, prescribed by the Department of Defense (hereinafter the JTR). |
| | (2) The Government will reimburse the Contractor for allowable travel costs incurred by the Contractor in performance of the contract in accordance with FAR Subpart 31.2. |
| | (3) For purposes of reimbursement of travel expenses, the Contractor's official station is defined as within 50 miles of the Contractor's regular work site. (If Contractor has more than one regular work site, the official station is defined as within 50 miles of each of its regular work sites.) |
| | (4) The Contractors documentation for the reimbursement of travel costs (e.g., receipts) shall be governed as set forth in FAR Subpart 31.2, the FTR, and the JTR. |
| | (5) Car Rental for a team on temporary duty (TDY) at one site will be allowed provided that only one car is rented for every four (4) members of the TDY team. In the event that less than four (4) persons comprise the TDY team, car rental will be allowed if necessary to complete the mission required. |
| | (6) Whenever work assignments require TDY aboard a Government ship, the Contractor will be reimbursed at the per diem identified in the JTR. |
| 5252.232-9516 | ALLOTMENT OF FUNDS - INCREMENTALLY FUNDED COST-REIMBURSEMENT CONTRACT OTHER THAN COST-SHARING CONTRACT (NAVAIR)(JUL 1985) - ALT I (OCT 2005) | | | |
| For the purposes of paragraph (b) of the "Limitation of Funds" clause of this contract- | | | |
| (a) The amount available for payment and allotted to this incrementally funded contract is: | | | |
| | Funded Cost | | $ [insert dollar amount or TBD] |
| | Funded Fee | | $ [insert dollar amount or TBD] |
| TOTAL FUNDS | | $ [insert dollar amount or TBD] | |
| (b) This contract is incrementally funded and the amount currently available for payment is limited to $[if contract, enter dollar amount; if solicitation, state "to be determined"] which includes a fixed fee amount of $[if contract, enter dollar amount; if solicitation, state "to be determined"]. Subject to the provisions of the clause entitled "Limitation of Funds" (FAR 52.232-22) of the General Provisions of the Contract, no legal liability on the part of the Government for payment in excess of the revised total shall arise unless additional funds are made available and incorporated in a contract modification. | | | |
| (c) the items covered by such amount are Item(s) [insert CLINs]; and | | | |
| (d) the period of performance for which it is estimated the allotted amount will cover is [insert the period of performance (calendar date)]. | | | |
*This clause will be utilized and completed at the task order level.
| 5252.237-9501 | ADDITION OR SUBSTITUTION OF KEY PERSONNEL (SERVICES) (NAVAIR)(OCT 2005) |
| (a) A requirement of this contract is to maintain stability of personnel proposed in order to provide quality services. The contractor agrees to assign only those key personnel whose resumes were submitted and approved, and who are necessary to fulfill the requirements of the effort. The contractor agrees to assign to any effort requiring non-key personnel only personnel who meet or exceed the applicable labor category descriptions. No substitution or addition of personnel shall be made except in accordance with this clause. |
| (b) If personnel for whatever reason become unavailable for work under the contract for a continuous period exceeding thirty (30) working days, or are expected to devote substantially less effort to the work than indicated in the proposal, the contractor shall propose a substitution to such personnel, in accordance with paragraph (d) below. |
| (c) The contractor agrees that during the term of the contract, no key personnel substitutions or additions will be made unless necessitated by compelling reasons including, but not limited to: an individual's illness, death, termination of employment, declining an offer of employment (for those individuals proposed as contingent hires), or family friendly leave. In such an event, the contractor must promptly provide the information required by paragraph (d) below to the Contracting Officer for approval prior to the substitution or addition of key personnel. |
This is the start of the file's text. The full file is on GovTribe.