STATEMENT OF WORK
REFURBISH TWO BLACK BRUIN HYDRAULIC WHEEL MOTORS
Description: This Statement of Work (SOW) is in support of the Expeditionary Maintenance Center Two (EMC2) located in Gulfport, Mississippi. EMC2 has a requirement for two (2) Black Bruin Hydraulic Motors to be refurbished to the Original Equipment Manufacturer (OEM) specifications.
General Information: EMC2 will provide two assembled Black Bruin Hydraulic Motors (cores) for being refurbished to OEM specifications by a Certified Service Center. The Contractor shall perform necessary cleaning, inspection, repairs, testing and painting to return hydraulic motors to OEM specifications.
Requirements: The Contractor must be a certified ‘Black Bruin Hydraulic Service Center’. Upon award of contract, the Contractor will perform repairs, test and paint two (2) Black Bruin Hydraulic Motors - BBC65-261-1102 motors to OEM Specifications. Serial #15050031 shall be repaired to Tier 2 (One Major Deficiency-replacement of bearing, seals, shaft rings and piston rings); serial #14060026 shall be repaired to Tier 1 (No Major Deficiencies-replacement of bearings, seals, shaft rings and piston rings). An invoice indicating all cost shall be provided at time of Pick-up / Delivery to EMC2.
Government Equipment Furnished: The Government shall provide two (2) Black Bruin Hydraulic Motors - BBC65-261-1102, as Government Equipment Furnished, to the Contractor:
· #15050031
· #14060026
Transportation: The Contractor must be within 150 miles of the Naval Construction Battalion Center Gulfport MS. EMC2 will provide transportation for delivery and pick-up of the hydraulic motors to the Contractor site within a 150-mile radius of Gulfport MS. Upon notification from Contractor that the hydraulic motors are, complete EMC2 has 5 working days to pick-up for completion of contract.
Period of Performance: Upon awarding of the contract, the Contractor has 100 working days to complete work and notify EMC2 for pick-up.
Point of Contact: The EMC2 points of contact for this contract are listed below:
Mr. Bill Richmond (SME) 228-871-3880 william.c.richmond@navy.mil
Mr. Tom Briney 228-871-3176 thomas.briney@navy.mil