SUMMARY
OPERATION ENDURING PROMISE - PUERTO CASTILLA
| BID SCHEDULE SUMMARY | |
| SITES | OM&N |
| Med Site #1 Banana Cruise Port | $ - 0 |
| Med Site #2 Centro de Education Basica Dr. Jesus Augilar Paz. Corocito | $ 1,500.00 |
| Helo Landing Zone (HLZ) #1 | $ - 0 |
| Fleet Landing Zone | $ - 0 |
| ACE Team | $ - 0 |
| Helo Landing Zone (HLZ) #2 | $ - 0 |
| GRAND TOTAL | $ 1,500.00 |
MEDSITE #1
MED SITE #1 BANANA COAST CRUISE PORT
| COMMENTS | ||
| PERIOD | 6 DEC 2018 - 14 DEC 2018 | 06-07 Setup. 08-12 Mission Execute. 13-14 Breakdown. |
| DAYS OF SERVICE | 9 |
| PERSONNEL | |
| MAIN PERSONNEL | 120 |
| TOTAL | 120 |
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS |
| TRANSPORTATION | DAYS | QTY | TOTAL | Not Needed due to Fleet Landing = Med Site | ||
| 2 | 40 Pax Bus w/Driver & Fuel | 0 | 3 | 531.51 | 0 | 12 HOURS/DAY REQUIRED TO TRANSPORT 120 PERSONNEL TO EACH MED SIGHT |
| BOTTLE WATER | DAYS | QTY | TOTAL | |||
| 18 | CASES OF WATER | 9 | 45 | $0.00 | 24-16.9oz per case (45 cases delivered every morning). | |
| ICE | DAYS | QTY | TOTAL | |||
| 20 | ICE (units in quantity are kg) | 9 | 100 | $0.00 | 100kg per day delivered with insulated ice chests provided. | |
| WASTE | DAYS | QTY | TOTAL | |||
| 22 | 55 Gallon Trash Can | 9 | 10 | $0.00 | Emptied 2x daily. | |
| LATRINE/WATER WASTE | DAYS | QTY | TOTAL | |||
| 24 | Portable Latrines (PORTA POTTIES) (3'X3'X7') | 9 | 16 | $0.00 | To include cleaning/restocking four (4) rolls of toilet paper and pumping 2x per day early in the morning and evening. | |
| 25 | Triple-sink Handwashing station 3 faucets, soap & paper dispenser | 9 | 5 | $0.00 | Cleaned, Restocked, and pumped 2x per day, loaded and offloaded from the camp-site by contractor. | |
| VECTOR/GRASS | DAYS | QTY | TOTAL | |||
| 28 | VECTOR CONTROL (spraying) | 1 | EA | $0.00 | Aprrox four (4) acres to be performed on 03 December 2018. | |
| POTABLE WATER | DAYS | QTY | TOTAL | |||
| 30 | Distilled Water (Dental Chairs) | 1 | 150 | $0.00 | Delivered in Distilled five (5) Gal Containers. | |
| FUEL | DAYS | QTY | TOTAL | |||
| 32 | MOGAS (GAL) | 1 | 300 | $0.00 | FPCON FUEL REQUIREMENTS | |
| 33 | DIESEL (GAL) | 1 | 340 | $0.00 | FPCON FUEL REQUIREMENTS | |
| RENTAL EQUIPTMENT | DAYS | QTY | TOTAL | |||
| 34 | Security Barriers, pedestrian, size 5' length | 9 | 675 | $0.00 | Length is in Feet. 5’ length per section, 135 sections, totaling 675’ | |
| 35 | Canopies (15' x 15') free standing | 9 | 1 | $0.00 | ||
| 36 | Chairs , plastic, stacking or folding | 9 | 600 | $0.00 | ||
| 37 | Tables, 6' Folding | 9 | 50 | $0.00 | ||
| 38 | Portable warehouse fan | 9 | 7 | $0.00 | 7,500-10,000 CFM | |
| 39 | Portable Pedastal Oscillating fan | 9 | 40 | $0.00 | 18" oscillating adjustable height floor or pedestal fans or equivalent | |
| 40 | Rental Generators (3kw)/With Fuel | 9 | 11 | $0.00 | NOT TO EXCEED 50 Decibles (DBS) | |
| 41 | Rental Generators (10kw)/With Fuel | 9 | 2 | $0.00 | 120V | |
| 42 | Rental Generators (20kw)/With Fuel | 9 | 1 | $0.00 | 240-120V | |
| 43 | Night Security Lighting gas powered w/fuel | 9 | 15 | $0.00 | 15' high with 12 hours of use. Fueled Daily. | |
| CONSTRUCTION | DAYS | QUANTITY | U/P | OM&N Total | COMMENTS | |
| 54 | Building Cleaning | 1 | 9 | $0.00 | Clean/Sanitize nine (9) rooms throughout four (4) buildings | |
| 55 | Furniture Movement | 1 | 6 | $0.00 | Aprox 5000 lbs six (6) Roooms | |
| 56 | Pavers | 1 | 1 | $0.00 | In accordance with the medical site schematics (attached) Remove and haul away roughly two (2) inches of dirt in the three (3) identified dirt floor buildings. Level and Install approximately 5,000 square feet of pavers (reuse existing pavers as needed) taking care to ensure that the pavers are below the door sills and doors can easily open and close. The pavers are to present a smooth surface for patient movement using something like a wheelchair. | |
| SITE TOTAL | $0.00 |
MEDSITE #2
MED SITE #2 Centro de Education Basica Dr. Jesus Augilar Paz. Corocito, Bonito Oriental, Colon, Honduras
| COMMENTS | ||
| PERIOD | 6 DEC 2018 - 14 DEC 2018 | 06-07 Setup. 08-12 Mission Execute. 13-14 Breakdown. |
| DAYS OF SERVICE | 9 |
| PERSONNEL | |
| MAIN PERSONNEL | 120 |
| TOTAL | 120 |
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS |
| TRANSPORTATION | DAYS | QTY | TOTAL | |||
| 2 | 40 Pax Bus w/Driver & Fuel | 9 | 3 | $0.00 | 12 HOURS PER DAY REQUIRED TO TRANSPORT 120 PERSONNEL TO EACH MED SIGHT | |
| BOTTLE WATER | DAYS | QTY | TOTAL | |||
| 19 | CASES OF WATER | 9 | 45 | $0.00 | 24-16.9oz per case (45 cases delivered every morning) | |
| ICE | DAYS | QTY | TOTAL | |||
| 21 | ICE (units in quantity are kg) | 9 | 100 | $0.00 | 100kg per day delivered with insulated ice chests provided. | |
| WASTE | DAYS | QTY | TOTAL | |||
| 23 | 55 Gallon Trash Can | 9 | 10 | $0.00 | Emptied 2x daily | |
| LATRINE/WATER WASTE | DAYS | QTY | TOTAL | |||
| 26 | Portable Latrines (PORTA POTTIES) (3'X3'X7') | 9 | 16 | $0.00 | To include cleaning/restocking four (4) roles of toilet paper and pumping 2x per day early in the morning and evening. | |
| 27 | Triple-sink Handwashing station 3 faucets, soap & paper dispenser | 9 | 5 | $0.00 | Cleaned, Restocked, and pumped 2x per day loaded and offloaded from the camp-site by contractor. | |
| VECTOR/GRASS | DAYS | QTY | TOTAL | |||
| 29 | VECTOR CONTROL (spraying) | 1 | EA | $0.00 | Aprrox 1 acre to be performed on 03 December 2018 | |
| POTABLE WATER | DAYS | QTY | TOTAL | |||
| 31 | Distilled Water (Dental Chairs) | 1 | 150 | $0.00 | Delivered in Distilled five (5) Gallon containers | |
| RENTAL EQUIPTMENT | DAYS | QTY | TOTAL | |||
| 44 | Security Barriers, pedestrain, size 5' length | 9 | 250 | $0.00 | Length is in Feet. 5’ length per section, 50 sections, totaling 250’ | |
| 45 | Canopies (15' x 15') free standing | 9 | 12 | $0.00 | ||
| 46 | Chairs , plastic, stackable or foldable | 9 | 684 | $0.00 | ||
| 47 | Tables, 6' Folding | 9 | 56 | $0.00 | ||
| 48 | Portable warehouse fan | 9 | 6 | $0.00 | 7,500-10,000 CFM | |
| 49 | Portable Pedastal Oscillating fan | 9 | 32 | $0.00 | 18" oscillating adjustable height floor or pedestal fans or equivalent | |
| 50 | Rental Generators (3kw)/With Fuel | 9 | 16 | $0.00 | NOT TO EXCEED 50 Decibles (DBS) | |
| 51 | Rental Generators (10kw)/With Fuel | 9 | 2 | $0.00 | 120V | |
| 52 | Rental Generators (20kw)/With Fuel | 9 | 1 | $0.00 | 240-120V | |
| 53 | Night Security Lighting gas powered w/fuel | 9 | 16 | $0.00 | 15' high with 12 hours of use. Fueled Daily. |
Elkhay, Heather M CIV NAVSUP FLC Jacksonville, 230: Elkhay, Heather M CIV NAVSUP FLC Jacksonville, 230:
To match PWS
| CONSTRUCTION | DAYS | QUANTITY | U/P | OM&N Total | COMMENTS | |
| 57 | Railing, Temporary | 1 | 1 | $0.00 | Construction of 75 Feet of temporary railing, specified in attached drawings. |
Elkhay, Heather M CIV NAVSUP FLC Jacksonville, 230: Elkhay, Heather M CIV NAVSUP FLC Jacksonville, 230:
To match PWS
| MISCELLANEOUS MATERIALS | DAYS | QUANTITY | U/P | OM&N Total | COMMENTS | |
| 58 | Miscellaneous materials to assist in tasking | 1 | 1 | $1,500.00 | $1,500.00 | NOT TO EXCEED (NTE) $1,500.00 and all and/or any cost must be approved by the COR before proceeding. |
| SITE TOTAL | $1,500.00 |
HLZ #1
HELO LANDING ZONE #1 Aeropuerto de Trujillo
| COMMENTS | ||
| PERIOD | 6 DEC 2018 - 14 DEC 2018 | 06-07 Setup. 08-12 Mission Execute. 13-14 Breakdown. |
| DAYS OF SERVICE | 9 |
| PERSONNEL | |
| MAIN PERSONNEL | 240 |
| TOTAL | 240 |
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS | |
| LINE HAUL | DAYS | QTY | TOTAL | ||||
| 6 | Line Haul from location 3 to location 1 | 2 | 2 | $0.00 | 60' Diesel flatbed trucks to move a variety of TRICON CONTAINERS (8 ft L X 6 ft W X 8 ft, approx. 6,000 lbs each), ISU-90 Containers (88"x108"x90 approx.6,000 lbs each). Shall include driver, fuel, unlimited mileage and associated chains, straps/load securing gear. | Med Site 1 | |
| 7 | 10,000 LB FORKLIFT and W/DRIVER, FUEL, UNLIMITED MILEAGE, 14 hours a day. | 2 | 1 | $0.00 | One (1) All-Terrain Forklift per truck w/operator, fuel, unlimited mileage to load and offload. Forklift shall have adjustable and extended forks. Capable of driving off road. | ||
| 8 | TRUCK TRACTOR W/ 52’SEMITRAILER LOWBED 55 TON W/ DRIVER, FUEL, UNLIMITED MILAGE AND ASSOCIATED STRAPS/LOAD SECURING GEAR 14 hours a day | 2 | 1 | $0.00 | Truck Tractor with an attached 8’ x 52’ LOWBED SEMITRAILER to move one (1) 10k all-terrain forklift with (preferred) hydraulic powered self-contained detachable gooseneck. Shall include chains, straps/securing gear. Truck Tractor provided w/operator, fuel and unlimited mileage to load and transport one (1) 10K Forklift. | ||
| 9 | Line Haul from location 3 to location 2 | 2 | 2 | $0.00 | 60' Diesel flatbed trucks to move a variety of TRICON CONTAINERS (8 ft L X 6 ft W X 8 ft, approx. 6,000 lbs each), ISU-90 Containers (88"x108"x90 approx.6,000 lbs each) Shall include driver, fuel, unlimited milleage and associated chains, straps/load securing gear. | Med Site 2 | |
| 10 | 10,000 LB FORKLIFT and W/DRIVER, FUEL, UNLIMITED MILEAGE, 14 hours a day. | 2 | 1 | $0.00 | 1 All-Terrain Forklift per truck w/operator, fuel, unlimited mileage to load and offload. Forklift shall have adjustable and extended forks. Capable of driving off road. | ||
| 11 | TRUCK TRACTOR W/ 52’SEMITRAILER LOWBED 55 TON W/ DRIVER, FUEL, UNLIMITED MILAGE AND ASSOCIATED STRAPS/LOAD SECURING GEAR 14 hours a day | 2 | 1 | $0.00 | Truck Tractor with an attached 8’ x 52’ LOWBED SEMITRAILER to move one (1) 10k all-terrain forklift with (preferred) hydraulic powered self-contained detachable gooseneck. Shall include chains, straps/securing gear driver, fuel, unlimited milated and associated chains, straps/load securing gear. Truck Tractor provided w/operator, fuel and unlimited mileage to load and transport (1) 10K Forklift. | ||
| 12 | Line Haul from location 1 to location 3 | 2 | 2 | $0.00 | 60' Diesel flatbed trucks to move a variety of TRICON CONTAINERS (8 ft L X 6 ft W X 8 ft, approx. 6,000 lbs each), ISU-90 Containers (88"x108"x90 approx.6,000 lbs each). Shall include driver, fuel, unlimited mileage and associated chains, straps/load securing gear. | Med Site 1 | |
| 13 | 10,000 LB FORKLIFT and W/DRIVER, FUEL, UNLIMITED MILEAGE, 14 hours a day. | 2 | 1 | $0.00 | 1 All-Terrain Forklift per truck w/operator, fuel, unlimited mileage to load and offload. | ||
| 14 | TRUCK TRACTOR W/ 52’SEMITRAILER LOWBED 55 TON W/ DRIVER, FUEL, UNLIMITED MILAGE AND ASSOCIATED STRAPS/LOAD SECURING GEAR 14 hours a day | 2 | 1 | $0.00 | Truck Tractor with an attached 8’ x 52’ LOWBED SEMITRAILER to move one (1) 10k all-terrain forklift with (preferred) hydraulic powered self-contained detachable gooseneck. Shall include chains, straps/securing gear. Truck Tractor provided w/operator, fuel and unlimited mileage to load and transport one (1) 10K Forklift. | ||
| 15 | Line Haul from location 2 to location 3 | 2 | 2 | $0.00 | 60' Diesel flatbed trucks to move a variety of TRICON CONTAINERS (8' L X 6' W X 8' H, approx. 6,000 lbs each), ISU-90 Containers (88"x108"x90 approx.6,000 lbs each). Shall include driver, fuel, unlimited mileage and associated chains, straps/load securing gear. | Med Site 2 | |
| 16 | 10,000 LB FORKLIFT and W/DRIVER, FUEL, UNLIMITED MILEAGE, 14 hours a day. | 2 | 1 | $0.00 | One (1) All-Terrain Forklift per truck w/operator, fuel, unlimited mileage to load and offload. | ||
| 17 | TRUCK TRACTOR W/ 52’SEMITRAILER LOWBED 55 TON W/ DRIVER, FUEL, UNLIMITED MILAGE AND ASSOCIATED STRAPS/LOAD SECURING GEAR 14 hours a day | 2 | 1 | $0.00 | Truck Tractor with an attached 8’ x 52’ LOWBED SEMITRAILER to move one (1) 10k all-terrain forklift with (preferred) hydraulic powered self-contained detachable gooseneck. Shall include chains, straps/securing gear. Truck Tractor provided w/operator, fuel and unlimited mileage to load and transport one (1) Forklift. | ||
| TOTAL | $0.00 |
FLEET LANDING
FLEET LANDING: BANANA COAST CRUISE PORT
| COMMENTS | ||
| PERIOD | 6 DEC 2018 - 14 DEC 2018 | |
| DAYS OF SERVICE | 9 |
| PERSONNEL | |
| MAIN PERSONNEL | 240 |
| TOTAL | 240 |
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS |
| TRANSPORTATION | DAYS | QTY | TOTAL | |||
| 3 | 6-Pax 4x4 SUV 4WD/w DRIVER, UNLIMITED MILEAGE | 9 | 2 | $0.00 | COMMAND ELEMENT 24 HOURS/DAY | |
| COMMUNICATION | DAYS | QTY | TOTAL | |||
| 5 | SMART PHONES WITH SIM CARD | 9 | 20 | $0.00 | HOST NATION CARRIER PROVIDED Unlimited local and international calls and txt, and data | |
| TOTAL | $0.00 |
ACE TEAM
ACE TEAM HONDURAS - Aeropuerto Internacional Ramón Villeda Morales, San Pedro Sula
| COMMENTS | ||||||
| PERIOD | 1 DEC 2018 -14 DEC 2018 | |||||
| DAYS OF SERVICE | 14 | |||||
| PERSONNEL | ||||||
| MAIN PERSONNEL | 5 | DESRON Lead, Medical Planner x2, COR | ||||
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS |
| TRANSPORTATION | TOTAL | |||||
| 1 | 6-Pax 4x4 SUV 4WD/w DRIVER, UNLIMITED MILEAGE | 14 | 2 | $0.00 | 24 HOURS/DAY turned over to base camp upon departure of ACE team. | |
| COMMUNICATION | DAYS | QTY | TOTAL | |||
| 4 | SMART PHONES WITH SIM CARD | 14 | 5 | $0.00 | HOST NATION CARRIER PROVIDED Unlimited international calls, local calls, txt, and data | |
| TOTAL | $0.00 |
HLZ #2 (Back Up)
| HELO LANDING ZONE #2 Base Naval de Puerto Castilla | |||
| Back-Up HLZ | |||
| COMMENTS | |||
| PERIOD | 6 DEC 2018 - 14 DEC 2018 | 06-07 Setup. 08-12 Mission Execute. 13-14 Breakdown. | |
| DAYS OF SERVICE | 9 |
| PERSONNEL | |
| MAIN PERSONNEL | 240 |
| TOTAL | 240 |
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS |
| LINE HAUL | DAYS | QTY | TOTAL | |||
| Line Haul from location 4 to location 2 | 2 | 0 | $469.58 | $0.00 | 60' Diesel flatbed truck to move a variety of TRICON CONTAINERS (8 ft L X 6 ft W X 8 ft, approx. 6,000 lbs each), ISU-90 Containers (88"x108"x90 approx.6,000 lbs each) | |
| 10,000 LB FORKLIFT and W/DRIVER, FUEL, UNLIMITED MILEAGE, 14 hours a day. | 2 | 0 | $861.50 | $0.00 | 1 All-Terrain Forklift per truck w/operator, fuel, unlimited mileage to load and offload. | |
| TRUCK TRACTOR W/ 52’SEMITRAILER LOWBED 55 TON W/ DRIVER, FUEL, UNLIMITED MILAGE AND ASSOCIATED STRAPS/LOAD SECURING GEAR 14 hours a day | 2 | 0 | $800.00 | $0.00 | Truck Tractor with an attached 8’ x 52’ LOWBED SEMITRAILER to move one (1) 10k all-terrain forklift with (preferred) hydraulic powered self-contained detachable gooseneck. Shall include chains, straps/securing gear. Truck Tractor provided w/operator, fuel and unlimited mileage to load and transport (1) Forklift | |
| Line Haul from location 2 to location 4 | 2 | 0 | $469.58 | $0.00 | 60' Diesel flatbed truck to move a variety of TRICON CONTAINERS (8 ft L X 6 ft W X 8 ft, approx. 6,000 lbs each), ISU-90 Containers (88"x108"x90 approx.6,000 lbs each) | |
| 10,000 LB FORKLIFT and W/DRIVER, FUEL, UNLIMITED MILEAGE, 14 hours a day. | 2 | 0 | $861.50 | $0.00 | 1 All-Terrain Forklift per truck w/operator, fuel, unlimited mileage to load and offload. | |
| TRUCK TRACTOR W/ 52’SEMITRAILER LOWBED 55 TON W/ DRIVER, FUEL, UNLIMITED MILAGE AND ASSOCIATED STRAPS/LOAD SECURING GEAR 14 hours a day | 2 | 0 | $800.00 | $0.00 | Truck Tractor with an attached 8’ x 52’ LOWBED SEMITRAILER to move one (1) 10k all-terrain forklift with (preferred) hydraulic powered self-contained detachable gooseneck. Shall include chains, straps/securing gear. Truck Tractor provided w/operator, fuel and unlimited mileage to load and transport (1) Forklift | |
| TOTAL | $0.00 |
MEDSITE #1 ALTERNATE
MED SITE #1 Escuela Guia Tecnica No. 16 Naciones Unidas, Trujillo, Colon
| COMMENTS | ||
| PERIOD | 24 NOV 2018 - 02 DEC 2018 | 24-25 Setup. 26-30 Mission Execute. 01-02 Breakdown. |
| DAYS OF SERVICE | 9 |
| PERSONNEL | |
| MAIN PERSONNEL | 120 |
| TOTAL | 120 |
| ITEM | DESCRIPTION OF SUPPLIES OR SERIVES | DAYS | QTY | UNIT PRICE | OM&N Total | COMMENTS |
| TRANSPORTATION | DAYS | QTY | TOTAL | |||
| 2 | 40 Pax Bus w/Driver & Fuel | 9 | 3 | $531.51 | $14,350.77 | 12 HOURS/DAY REQUIRED TO TRANSPORT 120 PERSONNEL TO EACH MED SIGHT |
| BOTTLE WATER | DAYS | QTY | TOTAL | |||
| 19 | CASES OF WATER | 9 | 45 | $11.67 | $4,726.35 | 24-16.9oz per case (45 cases delivered every morning) |
| ICE | DAYS | QTY | TOTAL | |||
| 21 | ICE (units in quantity are kg) | 9 | 100 | $0.08 | $72.90 | 100kg a day delivered with insulated ice chests provided. |
| WASTE | DAYS | QTY | TOTAL | |||
| 23 | 55 Gallon Trash Can | 9 | 10 | $11.36 | $1,022.40 | Emptied 2x daily |
| LATRINE/WATER WASTE | DAYS | QTY | TOTAL | |||
| 25 | Portable Latrines (PORTA POTTIES) (3'X3'X7') | 9 | 16 | $92.00 | $13,248.00 | To include cleaning/restocking 4 roles of toilet paper/pumping 2x a day early in the morning and evening. |
| 26 | Triple-sink Handwashing station 3 faucets, soap & paper dispenser | 9 | 5 | $134.55 | $6,054.75 | Cleaned, Restocked, and pumped 2x a day loaded and offloaded from the camp-site by contractor. |
| VECTOR/GRASS | DAYS | QTY | TOTAL | |||
| 29 | VECTOR CONTROL (spraying) | 1 | EA | $431.25 | $431.25 | Vector Control on 21 November 2018 |
| POTABLE WATER | DAYS | QTY | TOTAL | |||
| 31 | Distilled Water (Dental Chairs) | 1 | 150 | $0.52 | $78.00 | Delivered in Distilled 5 GL Containers |
| FUEL | DAYS | QTY | TOTAL | |||
| 33 | MOGAS (GAL) | 1 | 400 | $3.42 | $1,368.00 | FPCON FUEL REQUIREMENTS |
| 34 | DIESEL (GAL) | 1 | 420 | $3.42 | $1,436.40 | FPCON FUEL REQUIREMENTS |
| 35 | DIESEL (GAL) | 1 | 10,000 | $3.42 | $34,200.00 | Delivered as directed by the COR. DELIVERIES WILL BE MADE VIA HOSE FROM TRUCK TO FUEL BDAs |
| RENTAL EQUIPTMENT | DAYS | QTY | TOTAL | |||
| 36 | Security Barriers, pedestrain, size 3' length | 9 | 200 | $5.18 | $9,324.00 | Length is in Feet |
| 37 | Canopies (15' x 15') free standing | 9 | 2 | $86.25 | $1,552.50 | |
| 38 | Chairs , plastic, stacking or folding | 9 | 300 | $0.81 | $2,187.00 | |
| 39 | Tables, 6ft Folding | 9 | 60 | $4.03 | $2,176.20 | |
| 40 | Portable warehouse fan | 9 | 4 | $8.51 | $306.36 | 7,500-10,000 CFM |
| 41 | Portable Pedastal Oscillating fan | 9 | 30 | $5.51 | $1,487.70 | |
| 42 | Rental Generators (3kw)/With Fuel | 9 | 6 | $30.25 | $1,633.50 | NOT TO EXCEED 50 DBS |
| 43 | Rental Generators (10kw)/With Fuel | 9 | 2 | $40.25 | $724.50 | 120V |
| 44 | Rental Generators (20kw)/With Fuel | 9 | 1 | $60.25 | $542.25 | 240-120V |
| 45 | Night Security Lighting gas powered w/fuel | 9 | 10 | $120.75 | $10,867.50 | 12 hours of use. Fueled Daily. |
| CONSTRUCTION | DAYS | QUANTITY | U/P | OM&N Total | COMMENTS | |
| 57 | Classroom Cleaning | 1 | 12 | $100.00 | $1,200.00 | Clean/Sanitize Classrooms |
| 58 | Scrap and Level | 1 | 1 | $2,000.00 | $2,000.00 | Aprox 1 acres |
| 59 | Walkway, Temporary | 1 | 1 | $5,000.00 | $5,000.00 | 230 Ft Walkway Setup |
| 60 | Chain Link Fence, Temporary | 1 | 1 | $1,500.00 | $1,500.00 | 100 Ft Temporary Chain Link Fence |
| SITE TOTAL | $117,490.33 |