Attachment 0001 - SOW - Crane Hoist and Conductor Bar Upgrade v5.pdf

PDF 106 KB Posted

Attached to
Crane Hoist and Conductor Bar Upgrade
Solicitation number
N6833527Q1037
Issued by

About this file

This is a Statement of Work (SOW) for a hoist and conductor bar upgrade project at Naval Air Warfare Center Aircraft Division Lakehurst, New Jersey.

The Prototype, Manufacturing, and Test Department (PMTD) requires replacement of an obsolete 3-ton Detroit hoist and 3-wire conductor bar on Crane 148-12 with a new 3-ton wire rope hoist and 4-wire conductor bar system that meets Navy Crane Centers (NCC) latest requirements. The existing underhung bridge crane operates on 240 volts AC with a 5-inch bridge beam and approximately 17 feet of lift. PMTD will retain the current steel runway, bridge, end trucks, and single-motor bridge drive configuration. The 40-year-old hoist is beyond its useful lifespan (NCC standard is 20-30 years), and new tenants require upgraded capabilities for precision work.

Minimum requirements include: procurement and installation of a 3-ton wire rope hoist with mechanical load brake compliant with NAVCRANECEN Instruction 11450.1C; Variable Frequency Drive (VFD) control for hoist, bridge, and trolley; new bridge and/or hoist panel; new pendant control; new bridge and traveling pendant festoons; and 150 feet of new four-bar runway electrification including new collector pole and four double-shoe collectors. The vendor must submit engineering drawings and specifications for approval per CDRL A001, remove and replace existing equipment, provide all NAVFAC P-307 certified personnel, arrange freight and rigging to NAWCADLKE, provide onsite training, deliver two hard copy and one electronic set of maintenance manuals, maintain a continental U.S. parts warehouse with overnight emergency delivery capability, and ensure all employees use required personal protective equipment. Shipments shall be FOB Destination with costs borne by the contractor. Government personnel will perform inspection and 125% load testing before equipment acceptance. Contact information and shipping address are to be provided at award.

View the file

Other files

File Type Posted
Hoist Model and Serial Number.jpg JPG image
Crane Stop 1.jpg JPG image
Hoist Control Panel Inside.jpg JPG image
Trolley Motor Nameplate.jpg JPG image
Bridge Motor Nameplate.jpg JPG image
Bridge Control Panel.jpg JPG image
Overall Crane 1.jpg JPG image
Crane Power Bar.jpg JPG image
Crane Power Supply.jpg JPG image
Hoist Motor Nameplate.jpg JPG image
NCC Crane Alteration Request N3258A-19-008.pdf PDF
Overall Crane 2.jpg JPG image
Crane Bumper.jpg JPG image
Hoist Control Panel Outside.jpg JPG image
Crane Stop 2.jpg JPG image
Crane Hoist Conductor Bar Upgrade CDRL A001 10-7-2026 SIGNED.pdf PDF
Print of Crane.jpg JPG image
Bridge motor gear box and brake setup.jpg JPG image
Shoe.jpg JPG image
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR

Crane 148-12 Hoist and Conductor Bar Upgrade

1.0 Scope

The Prototype, Manufacturing, and Test Department (PMTD) is seeking a hoist and conductor bar upgrade on an existing bridge crane in accordance with the requirements listed below.

The objective for this project is to replace the obsolete 3-ton Detroit hoist and 3-wire conductor bar of crane 148-12 with a new hoist and 4-wire conductor bar meeting the Navy Crane Centers (NCC) latest requirements. The existing crane is an underhung bridge, and underhung hoist/trolley crane running on 240 volts alternating current with a 5” bridge beam. Current hoist has approximately 17’ of lift. PMTD will retain the current steel runway, bridge and end trucks of crane 148-12. PMTD will also retain the current bridge drive configuration of a single motor driving the bridge wheels through a driveshaft setup. The current hoist is over 40 years old and beyond its useful lifespan. The NCC states the useful lifespan of running hoists is 20 to 30 years. There are new tenants in the space covered by this crane. The new tenants need an upgraded hoist for the precision work required by them.

2.0 References

A)NAVFAC P-307: Weight Handling Program Management B)NAVCRANECEN Instruction 11450.1C: Acquisition of Navy Shore Based Weight Handling Equipment C)NAVSEA Publication 0989-030-7000: Lifting Standard D)National Fire Protection Association 70: National Electric Code E)American Society of Mechanical Engineers (ASME) B30.16: Overhead Hoists (Underhung) F)ASME HST-4: Performance Standard for Overhead Electric Wire Rope Hoists G)ASME B30.17: Cranes and Monorails (With Underhung Trolley or Bridge) H)ASME B1.1: Unified Inch Screw Threads (UN and UNR Thread Form) I)NEMA ICS 8: Industrial Control Systems Crane and Hoist Controllers J)ANSI ECMA 15: Cable-less Controls for Electric Overhead Traveling Cranes

3.0 New Hoist General Requirements

Minimum requirements that must be met in all proposals are listed as follows:

1.Procurement and installation of a 3-Ton Wire rope hoist with mechanical load brake, with all features meeting NAVCRANECEN Instruction 11450.1C: Acquisition of Navy Shore Based Weight Handling Equipment 2.Hoist, bridge and trolley will be Variable Frequency Drive (VFD) controlled.

3.New bridge and/or hoist panel.

4.New pendant control.

5.New Bridge and traveling pendant festoons 6.150’ of new four bar runway electrification to include new collector pole and four new double shoe collectors.

4.0 Vendor Provided Services

1. The vendor shall submit drawings and specifications for the crane hoist and electrical components after award, for approval in accordance with CDRL A001. These drawings and specifications shall meet or comply with NAVCRANECEN Instruction 11450.1C: Acquisition of Navy Shore Based Weight Handling Equipment. The vendor shall provide all engineering approval drawings, Bill of Materials, and supporting documentation as required for the facility to generate a Crane Alteration Request for NAVFAC NCC approval.

2. Remove the existing two speed Hoist

3. Provide and install a new VFD equipped 3 Ton Electrical Wire Rope Hoist with motorized trolley. Hoist must meet or comply with the NAVCRANECENINST 11450.2A

4. Remove the existing bridge motor and brake assembly

5. Install a new VFD ready gear-motor and brake assembly that match current ratio and speeds

6. Remove the existing bridge control panel and install a new VFD Control panel that is compliant with the NAVCRANECENIST 11450.2A

7. Remove the existing cross bridge festoon systems

8. Install a new cross bridge power festoon system

9. Remove the existing cross bridge pendant festoon system

10. Provide all NAVFACP307 certified personnel to perform all work 11.The cost of freight to the Naval Air Warfare Center Aircraft Division Lakehurst, NJ (NAWCADLKE) and rigging services for installation shall be included. Vendor shall be responsible for off-loading hoist and equipment from the delivery truck.

12. The vendor will connect electrical power to the hoist. The Government will supply A/C power, up to the runway beam.

6. The vendor shall provide onsite training for Operations, and Maintenance.

7. The vendor shall provide two (2) hard copy sets and one (1) electronic set of maintenance manuals.

8. A parts warehouse must be in the continental United States with typical overnight delivery in an emergency.

9. All labor to remove hoist, festoon, conductor bar, bridge panel, hoist panel and replacing with new. This shall include all rental equipment, materials, labor, and travel.

10. Vendor shall ensure all employees and/or contractors performing work will have and use personal protective equipment for the work, such as hard hats, safety glasses, fall protection, and safety shoes.

5.0 Government Inspection and Acceptance

After installation and system start up, Government personnel shall perform inspection, and 125% load testing before acceptance of the equipment.

6.0 Packaging, Preservation, and Shipping

Shipments shall be packaged and transported (FOB Destination) via safe, secure, reliable, and traceable means of transportation and provide protection from normal climatic/weather conditions;

and incidental mishandling during shipping to prevent any damage or loss during shipment. All shipments under this contract shall be addressed to NAWCADLKE as indicated below. Shipping costs need to be incurred by the contractor who is doing the shipping. All exterior shipping containers/packaging shall at a minimum be marked with the information listed below and the Contract Number.

ATTN: To be provided at award Naval Air Warfare Center, Aircraft Division Highway Route 547 Building 148 Joint Base MDL, New Jersey 08733

7.0 Points of Contact

Acquisition Point of Contact:

To be provided at award Naval Air Warfare Center, Aircraft Division Highway 547, Building 148 Joint Base MDL, NJ 08733 Telephone: To be provided at award E-Mail Address: To be provided at award

Technical Point of Contact:

To be provided at award Naval Air Warfare Center, Aircraft Division Highway 547, Building 148 Joint Base MDL, NJ 08733 Telephone: To be provided at award E-Mail Address: To be provided at award