LHTS__Interim_Payments.doc

DOC document 36 KB Posted

Attached to
Linear Hydraulic Test Stand Federal contract opportunity
Solicitation number
N6833517R0384
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

Contract Financing

View the file

Other files for this federal contract opportunity

Other files attached to Linear Hydraulic Test Stand, newest first.
File Type Posted
Questions_and_Answers_to_N6833517R0384_9-20-17.docx DOCX document
Drawing_19396F.pdf PDF
Reps_and_Certs.doc DOC document
52.212-4_Addendum.docx DOCX document
LHTS_Specification.docx DOCX document
Addendum_to_52.212-1_Instructions_to_offerors.docx DOCX document
Site_Visit_Info_for_Servo_Valve_Test_Stand.docx DOCX document
Drawing_PE_21743F.pdf PDF
Site_Visit_Letterhead_sample_FRCE.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RECOMMENDED PERFORMANCE BASED/COMMERCIAL INTERIM PAYMENTS

FY18 LINEAR HYDRAULIC TEST STAND (UPGRADE)

MILESTONE PAYMENT

DESCRIPTION

ACCOMPLISHMENT

EXPECTED

METHOD OF VERIFICATION
MILESTONE

PAYMENT PERCENTAGE

Post Award Conference/Plan of Actions and Milestones
Completion of PAC (Para.4.1)
Email from COR/TPOC to CO verifying completion
10%
Joint Design Review (JDR)
Completion of JDR (Para.4.4)
Email from COR/TPOC to CO verifying acceptance
10%
Final Acceptance Test Plan (FATP)
Completion of FATP (Para.3.20.13)
Email from COR/TPOC to CO verifying completion
20%
Delivery of Equipment
Delivery of equipment and all associated items.
Email from COR/TPOC to CO verifying completion
20%

SUBTOTAL OF MILESTONE PAYMENTS

60%

BALANCE UPON COMPLETION OF REMAINING DELIVERABLES, INSTALLATION, OPEN ACTION ITEMS, FINAL ACCEPTANCE TEST, & TRAINING OF STAND
LAST DELIVERABLES RECEIVED; INSTALLATION COMPLETED ALL OPEN ACTION ITEMS COMPLETED, FAT & TRAINING COMPLETED
Email from COR/TPOC to CO verifying completion
40%

Special Note: Contract financing payments will be authorized for 60% of the total contract value. The remaining 40% balance of the contract value may be invoiced after completion of all remaining contact requirements including, installation, Final Acceptance Testing, training, submittal of all remaining documentation, and satisfactory completion of all punch list items.