SOW_T-45_SE_Landing_Gear_Components_rev_4_T45_Team_May_5th_(3).pdf
PDF 370 KB Posted
- Attached to
- T-45 Main Landing Gear
- Solicitation number
- N68335-15-T-0013
About this file
SOW and CDRLs
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N68335-15-T-0013_RFP_Amendment.docx | DOCX document | |
| N68335-15-T-0013_RFP.docx | DOCX document | |
| N68335-15-T-0013_Proposal_Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVAL AIR SYSTEMS COMMAND
NAVAL AIR WARFARE CENTER AIRCRAFT DIVISION LAKEHURST
STATEMENT OF WORK
FOR
T-45 Main Landing Gear (MLG)
SE Side Brace Assembly- Part Number: 3568AS260-1 SE Drag Brace Assembly- Part Number: 3568AS280-1
Nose Landing Gear- Part Number: 3568AS118-1
Naval Air Warfare Center Aircraft Division SE and ALRE Department
SE and ALRE Systems Engineering Division Lakehurst, New Jersey 08733-5109
Original
07 April 2015
DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO THE
DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY (CRITICAL
TECHNOLOGY) (SEPTEMBER 2008). OTHER REQUEST SHALL BE REFERRED TO
PROGRAM EXECUTIVE OFFICER TACTICAL (PEO(T)), PMA-251, 47123 BUSE RD.,
RADM WILLIAM A MOFFETT BUILDING, PATUXENT RIVER, MD 20670-1547.
WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS
RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC 2751 ET
SEQ.) OR EXECUTIVE ORDER 12470. VIOLATIONS OF THESE EXPORT LAWS ARE
SUBJECT TO SEVERE CRIMINAL PENALTIES.
DESTRUCTION NOTICE, FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY
ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR
RECONSTRUCTION OF THE DOCUMENT.
Prepared for
Commander, Naval Air Systems Command
AIR 1.3.3.8
Lakehurst, NJ 08733-5000
FOR THE
T-45 MLG SE Side Brace Assembly, Side Brace & Nose Landing Gear
Prepared by:
Ken Nilsson, NAVAIRLKE 4.8.6.4 T-45 Airframes SE Engineer
Reviewed by:
John Reiss, NAVAIRLKE 6.7.6.1.3 T-45 Weapons System Manager
Approved by:
Willie Cusaac, NAVAIRLKE 1.3.3.8 T-45 SE IPT Lead
FOR THE
T-45 MLG SE Side Brace Assembly, Side Brace & Nose Landing Gear
1.0 SCOPE
This Statement of Work (SOW) establishes the specific tasks that must be performed by the contractor in order to fulfill the terms of the government solicitation for the T-45 Aircraft SE Side Brace, Part Number 3568AS260-1, Drag Brace Part Number 3568AS280-1 and Nose Landing Gear , Part Number 3568AS118- 1 hereafter referred to, in this SOW, MLG SE ). The SE gear shall be used in place of the landing gear to hold the aircraft up, and have towing capability which will enable the maintainers to tow the aircraft around the hangar if necessary. This SOW addresses the scope, performance of tasks and delivery of services, technical data, and the following hardware:
1. Side Brace Assemblies- T-45 Main Landing Gear (MLG) SE Side Brace Assembly Part Number 3568AS260-1.
i. One SE Side Brace Assembly shall be built and delivered as a First Article Test (FAT) unit. The government shall use this first article assembly and install on a T-45 aircraft as a fit check to verify three characteristics:
i. The total length of the assembly has been correctly specified pertaining specifically to drawing 3568AS264 for the side brace tubing.
ii. The bolt per drawing 3568AS265 properly interfaces with the aircraft attach points both in terms of outside shaft diameters and bolts overall length.
iii. The bolt per drawing 3568AS266 properly interfaces with the aircraft attach points both in terms of outside shaft diameters and bolts overall length.
ii. Production units shall then be built and delivered IAW post FAT test results:
i. If first article assembly passes FAT, performed by the government, that item becomes the first production unit and the vendor shall then be authorized to manufacture the remaining balance of units.
OR
ii. If discrepancies were found during FAT, the Government will submit revised drawings for all production units.
2. Drag Brace Components- four (4) components of a SE Drag Brace, P/N 3568AS280-1, in addition as delineated below, to be used to convert an existing prototype into a Ready for Issue (RFI) asset. The government requires each of the four components in the following quantities.
i. One (1) bolt – Part Number 3568AS283-1
ii. One (1) bolt – Part Number 3568AS284-1
iii. Two (2) nuts – per Drawing 3568AS280, F/N 7 with Part Number M45913/1-18FS3
iv. Two (2) drag brace end fittings – Part Number 3568AS281-1.
3. Drag Brace Assemblies- P/N 3568AS280-1.
4. Nose Landing Gear Assemblies- P/N 3568AS118-1.
2.0 APPLICABLE DOCUMENTS
The documents listed in this section are specifically invoked throughout this SOW. Unless otherwise noted elsewhere in the document, the version of the listed documents shall apply. When referenced document titles, revision letters, and dates of issue are omitted for brevity of reference, the short form reference shall be understood to be the specific issue identified in this section.
2.1 SPECIFICATIONS/STANDARDS DOCUMENTS
The following government specifications, standards, and handbooks form a part of this document to the extent specified herein.
ANSI/AQC-Q9001, Quality Systems- Model for Quality Assurance in Design, Development, Installation, and Servicing, 1994
AS9100, Quality Management System Standard, Jan 2004
MIL-STD-130N, Identification Marking of US Military Property, 17 Dec 2007
MIL-STD 3046 Configuration Control 6 Mar 2013
2.2 Drawing Package List for SE Side Brace Assembly
i. 3568AS260rAs1 – Top Drawing, referred as the NHA for the next five drawings
ii. 3568AS261rAs1 – Swivel, Outboard
iii. 3568AS262r-s1 – End Fitting, Main Gear
iv. 3568AS263r-s1 – Swivel, Inboard
v. 3568AS264rAs1 – Tubing, Side Brace
vi. 3568AS265rAs1 – Bolt, Side Brace, INBD, Attach, MLG
vii. 3568AS266rAs1 – Bolt, Side Brace, Lower, Attach, MLG
2.3 Drawing Package List for SE Drag Brace Assembly
i. 3568AS280rAs1 – Top Drawing, referred as the NHA for the next four drawings
ii. 3568AS281rAs1 – End Fitting, Drag Brace
iii. 3568AS282r-s1 – Tubing, Drag Brace
iv. 3568AS283r-s1 – Bolt, Drag Link, Strut End
v. 3568AS284rAs1 – Bolt, Drag Link, Trunnion End
2.4 Drawing Package List for Nose Landing Gear
i. 3568AS118r-s4 - Dummy Nose Landing Gear Assembly
ii. 3568AS285r-s6 - Assembly, Upper Dummy Nose Landing Gear
iii. 3568AS286r-s5 - Assembly, Lower Dummy Nose Landing Gear
3.0 MATERIAL PRODUCTION MANUFACTURING AND TEST
3.1 FIRST ARTICLE TEST ASSEMBLY (CDRL A001)
The Contractor shall manufacture and deliver the First Article test Assembly of the SE Side Brace part number 3568AS260-1 in accordance with the drawing Package List delineated in paragraph 2.2 to NAVAIR Lakehurst for inspection, fit check, and approval before proceeding with the production lot. All CDRLs are applicable to the sample and can be found in Appendix A.
3.2 PRODUCTION (CDRL A002, A004 & A006)
The Contractor shall manufacture the SE Side Brace Assemblies as defined in paragraph 1.0 (1)ii, and the six components defined in paragraph 1.0 (2). SE Drag Brace as defined in paragraph 2.0 and Nose Landing
Gear as defined in paragraph 4.0. All CDRLs are applicable to the production units and can be found in Appendix A.
[CDRL A002 Production Units SE Side Brace Assemblies] [CDRL A004 Production Units for SE Drag Brace Assemblies] [CDRL A006 Production Units for Nose Landing Gear]
3.3 PRODUCTION MANUFACTURING TEST
N/A
3.4 PRODUCTION PROGRESS (CDRL B001, B002 & B003)
The contractor shall provide status of the production progress for all hardware configuration items being produced under this contract. Reviews shall be conducted at the contractor facility or via phone with the Navy to report production progress in meeting contractual requirements and identify problems. Program management reporting shall include progress against the production schedule, problem identification, risk/opportunity, and corrective action plans, when required.
[CDRL B001 Production Progress Report for SE Side Brace Assemblies] [CDRL B002 Production Progress Report for SE Drag Brace Assemblies] [CDRL B003 Production Progress Report for Nose Landing Gear]
3.4.1 MEETING SUPPORT
The Contractor shall support programmatic and technical meetings as required.
3.5 QUALITY ASSURANCE (QA) MANAGEMENT
3.5.1 QA PROGRAM
The Contractor shall develop and maintain a quality system that meets the requirements of ISO 9001-2008 of ANSI/AQC-Q9001 or current highest level requirement.
3.5.2 QUALITY PROGRAM
The Contractor shall implement a quality program for the timely investigation and correction of quality deficiencies. The Contractor shall investigate all quality deficiency reports and system discrepancy reports, and all other relevant non-conformance indications and take appropriate corrective action. The Contractor shall support Government surveys, audits, and surveillance of Contractor facilities to determine capability to comply, and to verify continuing compliance, with the requirements of this contract.
3.5.3 CERTIFICATE OF QUALITY COMPLIANCE (CDRL A008, A009 & A010)
The Contractor shall prepare and furnish a Certificate of Quality Compliance (COQC) and Acceptance Test Report for all supplies delivered under this contract IAW A008, A009 & A010).
[CDRL A008 Certificate of Quality Compliance SE Side Brace Assemblies] [CDRL A009 Certificate of Quality Compliance for SE Drag Brace Assemblies] [CDRL A010 Certificate of Quality Compliance t for Nose Landing Gear]
3.5.4 MANUFACTURING QUALITY (CDRL A003, A005 & A007)
Contractor shall submit Non-Conforming requests using the Request for Deviation DD Form 1694, MIL- STD-3046 for all major and critical non-conformances for NAVAIR approval. In order to minimize any potential production delays. NAVAIR will dispositio003n all Request for Deviation within 10 working days of submittal from contractor. Contractor shall provide Request for Deviation and product baseline changes summaries IAW CDRL A003. All minor deviations will be available for review at the Government’s request.
[CDRL A003: Request for Deviation -SE Side Brace] [CDRL A005: Request for Deviation- SE Drag Brace] [CDRL A007: Request for Deviation- Nose Landing Gear]
3.6 PACKAGING AND PRESERVATION
Packaging, Preservation and Shipping shall be in accordance with best commercial practices available and shall provide protection from normal climatic / weather conditions and incidental mishandling during shipping. The Side Braces shall be shipped Freight On Board (FOB) Destination. The planned delivery locations is for JBMDL, Lakehurst NJ, however deliveries could be requested for direct shipment to Naval Air Station (NAS) Patuxent River, MD, NAS Meridian MS, NAS Pensacola FL, or NAS Kingsville, TX.
3.7 HAZARDOUS MATERIALS MANAGEMENT AND ENVIRONMENTAL
COMPLIANCE
The contractor (and its sub-contractors) shall comply with all federal, state and local environmental laws, regulations and policies for all activities defined in this contract whether conducted at government or contractor owned or managed facilities. The contractor shall be solely responsible for the management, cleanup, protection, and disposal of any and all emissions, effluents, wastes and hazardous materials used in, generated by, or associated with the actions required by this contract.
5.0 LIST OF ACRONYMS AND ABBREVIATIONS
CDRL Contract Data Requirements List DCMA Defense Contract Management Agency IMS Integrated Master Schedule IPT Integrated Product Team ISO International Organization of Standardization LDY Lead Design Yard MLG Main Landing Gear NLG Nose Landing Gear PMA Program Manager Air QA Quality Assurance SDR Supplier Deficiency Report SE Support Equipment SOW Statement of Work WAWF Wide Area Work Flow
APPENDIX A
A CONTRACT DATA REQUIREMENTS LIST FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
A
C. CATEGORY:
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Side Brace Assembly – 1st Article Unit
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Certificate of Quality Compliance
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81356A
5. CONTRACT REFERENCE
SOW Para 3.1
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10 & 12: One time only and should be delivered 10 days after acceptance testing of 1st article unit. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
Lakehurst NJ 08733 willie.cusaac@navy.mil
CODE 1.3.3.8 1 0
CODE 4.8.8.8 0 1
DCMA QAR 0 1
CODE 4.8.6.4 0 1
15. TOTAL
1 3
G. PREPARED BY
J. Reiss
H. DATE
I. APPROVED BY
W. Cusaac
J. DATE
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Side Brace Assembly – Production Units
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A008
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.5.3
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10 & 12: Shall be delivered per unit 5 days prior to delivery of each Production Unit SE Side Brace Assembly. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Side Brace Assemblies
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A003
2. TITLE OF DATA ITEM
Request for Deviation
DI-CMAN-80640C
5. CONTRACT REFERENCE
SOW Para 3.5.4
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10: One per deviation as required.
Block 12 & 13: Shall be delivered per unit 5 days after discovery of the nonconformance. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Side Brace Assemblies
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
B001
2. TITLE OF DATA ITEM
Production Progress Report
DI-MGMT-80034
5. CONTRACT REFERENCE
SOW Para 3.4 & 3.4.1
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
LT
9. DIST STATEMENT
See Block 16
10. FREQUENCY
MTHLY
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
See Block 16
Draft Final
Reg Repr
16. REMARKS
Block 5: Contractor shall submit a monthly progress report describing the contractor’s current progress including progress against the production schedule, problem identification, risk/opportunity, and corrective action plans, wen required.
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 12: 15 days after contract award. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
Lakehurst NJ 08733 willie.cusaac@navy.mil
Block 13: Subsequent reports to be submitted no later than the 5th day of the month (for the month proceeding). Local DCMA verification required on all status reports.
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Drag Brace Assembly – Production Units
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A009
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.5.3
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10 & 12: Shall be delivered per unit 5 days prior to delivery of each Production Unit SE Side Brace Assembly. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Drag Brace Assemblies
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A005
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.5.4
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10: One per deviation as required.
Block 12 & 13: Shall be delivered per unit 5 days after discovery of the nonconformance. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
SE Drag Brace Assemblies
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
B002
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.4 & 3.4.1
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
LT
9. DIST STATEMENT
See Block 16
10. FREQUENCY
MTHLY
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
See Block 16
Draft Final
Reg Repr
16. REMARKS
Block 5: Contractor shall submit a monthly progress report describing the contractor’s current progress including progress against the production schedule, problem identification, risk/opportunity, and corrective action plans, wen required.
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 12: 15 days after contract award. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
Lakehurst NJ 08733 willie.cusaac@navy.mil
Block 13: Subsequent reports to be submitted no later than the 5th day of the
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
Nose Landing Gear – Production Units
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A010
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.5.3
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10 & 12: Shall be delivered per unit 5 days prior to delivery of each Production Unit SE Side Brace Assembly. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
Nose Landing Gear
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A007
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.5.4
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
SS
9. DIST STATEMENT
See Block 16
10. FREQUENCY
See Block 16
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft Final
Reg Repr
16. REMARKS
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 10: One per deviation as required.
Block 12 & 13: Shall be delivered per unit 5 days after discovery of the nonconformance. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
DCMA QAR 0 1
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202- 4302, and to the Office Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Office for the Contract/PR No. listed in Block E.
TDP_______ TM_______ OTHER
D. SYSTEM ITEM
Nose Landing Gear
E. CONTRACTOR/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
B003
2. TITLE OF DATA ITEM
5. CONTRACT REFERENCE
SOW Para 3.4 & 3.4.1
6. REQUIRING OFFICE
NAVAIRLKE Code 1.3.3.8
7. DD 250 REQ
LT
9. DIST STATEMENT
See Block 16
10. FREQUENCY
MTHLY
12. DATE OF FIRST
SUBMISSION
See Block 16
14. DISTRIBUTION
a. ADDRESSEE b. COPIES
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
See Block 16
Draft Final
Reg Repr
16. REMARKS
Block 5: Contractor shall submit a monthly progress report describing the contractor’s current progress including progress against the production schedule, problem identification, risk/opportunity, and corrective action plans, wen required.
Block 9: Distribution Statement: Authorized to U.S. Government Agencies and their contractors, administration/operational use. Other requests for this document shall be referred to Commanding Officer, Naval Air Warfare Center, Aircraft Division, Lakehurst, NJ 08733-5000.
Block 12: 15 days after contract award. Report shall be submitted to:
NAVAIRWARCENACDIVLKE
Attention Willie Cusaac, Code 1.3.3.8 Bldg 562-1
HWY 547
Lakehurst NJ 08733 willie.cusaac@navy.mil
Block 13: Subsequent reports to be submitted no later than the 5th day of the
DCMA QAR 0 1
Appendix B Technical Data Requirement (TDR)
REVISION rAs1 Drawing 3568AS260 is the NHA for the SE Side Brace Assembly and adequately provides all information for production using drawings called out in BOM. All physical characteristics are dimensioned and QA inspection shall verify individual components comply with stated tolerances.
REVISION rAs1 Drawing 3568AS280 is the NHA for the SE Drag Brace Assembly and adequately provides all information for production using drawings called out in BOM. All physical characteristics are dimensioned and QA inspection shall verify individual components comply with stated tolerances.
REVISION rAs1 Drawing 3568AS118 is the NHA for the Nose Landing Gear and adequately provides all information for production using drawings called out in BOM. All physical characteristics are dimensioned and QA inspection shall verify individual components comply with stated tolerance.
| & Nose Landing Gear |
| 1.0 SCOPE |
| 2.0 APPLICABLE DOCUMENTS |
| 2.1 SPECIFICATIONS/STANDARDS DOCUMENTS |
| MIL-STD 3046 Configuration Control 6 Mar 2013 |
| 2.2 Drawing Package List for SE Side Brace Assembly |
| 2.3 Drawing Package List for SE Drag Brace Assembly |
| 2.4 Drawing Package List for Nose Landing Gear |
| 3.0 MATERIAL PRODUCTION MANUFACTURING AND TEST |
| 3.1 FIRST ARTICLE TEST ASSEMBLY (CDRL A001) |
| 3.2 PRODUCTION (CDRL A002, A004 & A006) |
| 3.4.1 MEETING SUPPORT |
| 3.5 QUALITY ASSURANCE (QA) MANAGEMENT |
| 3.5.1 QA PROGRAM |
| 3.5.2 QUALITY PROGRAM |
| 3.5.4 MANUFACTURING QUALITY (CDRL A003, A005 & A007) |
| 3.6 PACKAGING AND PRESERVATION |
| 3.7 HAZARDOUS MATERIALS MANAGEMENT AND ENVIRONMENTAL COMPLIANCE |
| 2015-08-17T11:46:04-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:47:19-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:48:22-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:48:50-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:49:29-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:50:11-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:50:34-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:50:56-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:51:22-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
| 2015-08-17T11:51:48-0400 | |
| CUSAAC.WILLIE.J.1229002305 |
File details come from the government source that posted it. Updated .