N6660424Q0314 Amendment_0002.pdf

PDF 403 KB Posted

Attached to
Construction - B104 Emergency Generator Project Federal contract opportunity
Solicitation number
N6660424Q0314
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document is an amendment to Solicitation N6660424Q0314 for the Construction - B104 Emergency Generator Project for the Naval Undersea Warfare Center Division, Newport (NUWCDIVNPT). The amendment extends the proposal due date from April 23, 2024 to May 3, 2024, provides answers to previous requests for information, and replaces the Davis Bacon Wage Determination with a newer version. The solicitation is a 100% small business set-aside with a magnitude between $100,000 and $250,000, using the NAICS code 236220. The project involves replacing an emergency generator and automatic transfer switch at the B104 facility. Key details include the required site visit, technical submission requirements, and instructions for bid submission and acknowledgment of the amendment. The method of payment will be through Wide Area Workflow (WAWF).

View the file

Other files for this federal contract opportunity

Other files attached to Construction - B104 Emergency Generator Project, newest first.
File Type Posted
N6660424Q0314 Amendment_0001.pdf PDF
Attachment_2_Davis Bacon Wage Determination (8MAR24 Pgs15).pdf PDF
N6660424Q0314.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1301144332

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See section A.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Apr-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6660424Q0314

X 9B. DATED (SEE ITEM 11)

21-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Apr-2024

CODE

NAVAL UNDERSEA WARFARE CENTER

JAY PARKER, CODE 0221

CONTRACTS DEPARTMENT

1176 HOWELL STREET

NEWPORT RI 02841

N66604 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6660424Q0314

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 23-Apr-2024 12:00 AM to 03-May-2024 02:00 PM.

The required performance has changed from PROJECT TITLE AND DESCRIPTION: B104 Emergency Generator ProjectProposal Due: April 23, 2024 at 2:00PM EST, Email to Michael.N.Ouellette.civ@us.navy.mil and jay.a.parker2.civ@us.navy.mil NOTE: Offeror MUST be registered in the System for Award Management (SAM) to be considered for award. Bid Guarantee is also required to be considered for award.Magnitude per FAR 36.204:

Between $100,000 and $250,000.Method of Payment: Electronic Payment through Wide Area Workflow (WAWF) will be used.This requirement is 100% small business set aside, NAICS 236220; $45 millionSITE VISIT DATE and TIME: April 09, 2024 at 10:00AM EST, Meet at Building 80 NUWC Division New port. Please allow for sufficient time to process site visit request. See Section A for complete details.IMPORTANT: PLEASE NOTE THAT TECHNICAL INFORMATION IS REQUIRED WITH SUBMISSION OF OFFER. PLEASE SEE SECTIONS L

AND M FOR SPECIFIC REQUIRMENTS. OFFERORS NOT SUBMITTING THIS INFORMATION RISK

BEING EXCLUDED FROM CONSIDERATION FOR AWARD. to PROJECT TITLE AND DESCRIPTION:

B104 Emergency Generator ProjectProposal Due: May 3, 2024 at 2:00PM EST, Email to Michael.N.Ouellette.civ@us.navy.mil and jay.a.parker2.civ@us.navy.mil NOTE: Offeror MUST be registered in the System for Award Management (SAM) to be considered for award. Bid Guarantee is also required to be considered for award.Magnitude per FAR 36.204: Between $100,000 and $250,000.Method of Payment: Electronic Payment through Wide Area Workflow (WAWF) will be used.This requirement is 100% small business set aside, NAICS 236220; $45 millionSITE VISIT DATE and TIME: April 09, 2024 at 10:00AM EST, Meet at Building 80 NUWC Division New port. Please allow for sufficient time to process site visit request. See Section A for complete details.IMPORTANT: PLEASE NOTE THAT TECHNICAL INFORMATION IS REQUIRED WITH SUBMISSION OF OFFER. PLEASE SEE SECTIONS L AND M FOR SPECIFIC REQUIRMENTS. OFFERORS

NOT SUBMITTING THIS INFORMATION RISK BEING EXCLUDED FROM CONSIDERATION FOR

AWARD..

The following have been modified:

GENERAL INFORMATION

Distribution: To be provided at award NUWCDIVNPT PR number: To be provided at award

NUWCDIVNPT PID: N66604-24-SIMACQ-NPT-10-0212

NUWCDIVNPT Point of Contact: Jay Parker, jay.a.parker2.civ@us.navy.mil and Michael Ouellette Michael.N.Ouellette.civ@us.navy.mil

AMENDMENT 0002:

The purpose of this amendment it to:

1. Extend the solicitation due date from 23 April 2024 to 3 May 2024 @ 1400 EST.

2. Provide answers to RFI 0001 as seen below.

3. Remove Attachment 2 Davis Bacon Wage Determination dated 08-Mar-2024 and replace with Davis Bacon Wage Determination RI20240001 dated 05-Apr-2024.

4. Attachment 3 has been added (revised drawings 24-009A).

ALL OTHER SOLICITAITON TERMS AND CONDITIONS REMAIN UNCHANGED.

RFI 0001

1. Please provide existing Operations and Maintenance manuals for the existing equipment to be replaced during the B104 Emergency Generator project.

Response: The existing generator is a Kohler model 300REOZV, and the existing automatic transfer switch is a Kohler model KDT-AMTA-0600S. The existing generator and automatic transfer switch will be returned to the Government as indicated in the Revision 1 Drawing Set, so the information requested is no longer needed by the Contractor.

2. Please provide a “one-line” power diagram for the B104 Generator Project.

Response: A “one-line” power diagram is included in the Revision 1 Drawing Set.

3. Would the government provide any and/or all information on the existing generator i.e., model#, approximate age and number of hours, if possible, and any maintenance records that might be available?

Response: See Government response to question #1.

4. If the generator is not currently in use, are we re-using existing cabling or providing new? The Existing and New drawings show the same Keynotes Response: The existing cabling will remain in place and be connected to the new generator and automatic transfer switch (extend if required).

5. Where will the temporary soil stockpile area be located at the job site for the excess excavated material generated from the excavation of the generator pad extension? This soil will remain on-site until the soil can be tested, landfill approval received and then scheduled to be removed and properly disposed of at the landfill facility.

Response: The Contractor shall propose a temporary soil stockpile laydown area prior to the start of the project, for approval by the Project Engineer. The laydown area shall be clear of the roadway, and not interfere with traffic.

6. During the generator replacement period will a temporary generator be needed?

Response: A temporary generator will not be required during the generator replacement period.

7. How long can building be without emergency and normal power? If no, does a temporary generator need to be connected to panel P.P.1?

Response: The Contractor shall ensure minimum downtime to Data Center operations to the greatest extent possible. The Contractor shall gain Government approval for any interruption to Data Center operations two weeks in advance of the requested shutdown date, and complete all work requiring a shutdown during weekend hours, from 1800 on Friday to 0600 on Monday.

8. Can outages occur on Saturday and Sunday (48 hours)?

Response: See Government response to question #7.

9. Is there a remote annunciator and where is it located?

Response: There is not a remote annunciator.

10. Is the generator connected to Fire Alarm system? If so, what indications are required?

Response: The generator is not connected to the fire alarm system.

The following have been deleted:

SITE VISIT INSTRUCTIONS

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications and

Drawings

173 22-FEB-2024

Attachment 2 Davis Bacon Wage Determination

15 08-MAR-2024

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications and

Drawings

173 22-FEB-2024

Attachment 3 Davis Bacon Wage Determination

RI20240001

15 05-APR-2024

Attachment 4 Revised Drawings 22-APR-2024

(End of Summary of Changes)