1300914630 W2018-194-02

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Section A - General Information: Provide Question & Answ ers #1-19.

Section I: Add clause 52.204-2 Alt II Security Requirements (incorporated by reference).

Section J:

Provide updated Wage Determination RI20220001 Mod 4 dated 1 Apr 2022. See J-1.

Provide revised Specification dated 18 Mar 2022. See J-2.

Provide revised Draw ing Set 20-006A Rev 1 dated 22 Mar 2022. See J-3.

Provide updated Project Submittal Register. See J-4.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Apr-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6660422R0230

X 9B. DATED (SEE ITEM 11)

25-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Apr-2022

CODE

NAVAL UNDERSEA WARFARE CENTER

JOSEPH SCARPA, CODE 0222, 401-832-1499,

CONTRACTS DEPARTMENT

1176 HOWELL STREET, BLDG. 1258

NEWPORT RI 02841-1708

N66604 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6660422R0230

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been added by full text:

GENERAL INFO - AMENDMENT 0001

*** Due Date is not extended; proposals remain due 2:00 PM ET Tuesday 26 Apr 2022***

Questions and Answers (Q&A)

Question #1: Is there a designated laydown area? May Contractor store new materials, tools, and lifts in Room 119B/C? Is Government providing a space for dumpsters?

Answer #1: Construction Site Plan article in Specification Section 01 50 00 requires Contractor to submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area, et cetera. We will discuss Contractor’s proposed laydown area at the preconstruction meeting consistent with the Preconstruction Meeting article in Section 01 30 00 and the Preconstruction Meeting subparagraph in Section 01 35 26. The general outside area and parking lot behind the building is a candidate for a laydown area, as are Rooms 119B and 119C.

Question #2: Is Contractor permitted to use Government restrooms?

Answer #2: Government restrooms will not be available for Contractor use. In accordance with the Sanitation paragraph in Specification Section 01 50 00, Contractor is required to provide and maintain within the construction area minimum field-type sanitary facilities in accordance with U.S. Army Corps of Engineers Engineering Manual EM 385-1-1 Section 02.

Question #3: Is Contractor required to remove expanded metal from all locations? Is Contractor required to remove all the expanded metal on the outside of the existing cage? Does the Navy want to save it for future use? If remaining in place, selected areas will have to be cut to accommodate plywood beans.

Answer #3: The expanded metal may remain. Contractor should address areas to be cut in its Deconstruction Plan, pursuant to Specification Section 02 41 00.

Question #4: If Contractor is removing the expanded metal, is the Contractor to provide a separate dumpster for recycling metal?

Answer #4: Miscellaneous Metal paragraph in Specification Section 02 41 00 requires Contractor to provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the [Contractor] Waste Management Plan, pursuant to Section 01 74 19.

Question #5: Will storage shelves be removed, relocated, and replaced by the Government?

Answer #5: Yes, the Government will remove the storage shelves prior to start of Work and the Government will replace the shelves after final acceptance of the Work or upon beneficial occupancy.

Question #6: The 2x4 by overhead door is damaged. Is that scheduled to be replaced?

Answer #6: Contractor shall replace the damaged 2x4.

Question #7: Drawings do not seem to indicate all areas/walls for sheetrock. Please confirm.

Answer #7: Your observation is correct. The drawings indicate the appropriate areas to be finished with sheetrock.

Question #8: Drawing Sheet 4 Detail for swing door / overhead door section doesn't match the wall thickness. In fact, all details on this page show 3-1/2” but the wall thickness should be 7”+.

Answer #8: See revised drawings in Section J provided with this Amendment 0001.

Question #9: Where is panel P1? (Electrical panel that feeds P000).

Answer #9: Panel P1 is located in the same bay of the building, approximately 100 feet northwest of panel P000.

Question #10: 2x8 sill plate not indicated as PT, but should be if in contact with concrete.

Answer #10: Contractor shall ensure the sill plate is preservative treated.

Question #11: Will Rooms 119A/B/C be emptied and turned over at same time to Contractor before commencement of Work?

Answer #11: Room 119A will remain in use with Government inventory. The Government and Contractor will coordinate clearing of pathways as needed. Government will clear Rooms 119B and 119C prior to start of Work.

Question #12: Is there a fork truck available to move the lifts of sheetrock and plywood? Or should one be rented?

Answer #12: Contractor shall provide its own or rented equipment, including forklifts, aerial lifts, etc.

Question #13: Are any of the new finishes required to be painted? E.g., Drawing #20-006A sheet 4 of 8, Door Schedule calls for factory pre-finish for doors and frames. Can Contractor provide a factory primed door and frame with field painting to be done after install so as to minimize damage to finish?

Answer #13: The new doors are scheduled to be painted. The plywood and gypsum walls are not scheduled to be painted. Contractor may provide a factory-primed door and frame and apply painting finish in the field.

Question #14: Is the north side of Room 119A going to have the expanded metal removed and receive the 3/4-inch fire rated plywood also?

Answer #14: No.

Question #15: On the top connection picture of the vertical beams, the right pic shows 4x3x1/4 angle and the left shows 3x3x3/16 angle?

Answer #15: This question seems to revolve about the meaning or intent of the weld symbol. The angles are 4”x3”x1/4” and they are attached to the existing steel with 3/16”x3” fillet welds.

Question #16: Is there only one sheetrock control joint in 119B/C?

Answer #16: Two control joints are required. One between the new gypsum and the existing gypsum and one halfway between that joint and the corner of the room.

Question #17: Plywood beam to sill plate nail size says 10D, it shows 1-1/2-inch length which is 4D nail size?

Answer #17: The 1-1/2” long nails should be labeled as 1-1/2” x 0.148”.

Question #18: Do all plywood ends need vertical blocking or only in between the built up vertical beams?

Answer #18: All plywood ends need blocking.

Question #19: What size is the ledger board? 2 x 4?

Answer #19: Yes, ledger board size is 2 x 4.

(End of Q&A)

Submit questions to joseph.scarpa6.civ@us.navy.mil or (401) 832-1499 with copy to michael.h.broomfield.civ@us.navy.mil or (401) 832-8469.

If you cannot participate in this contract opportunity, please email a brief explanation such that we can continuously improve our contracting processes.

SECTION I - CONTRACT CLAUSES

The following have been added by reference:

52.204-2 Alt II Security Requirements (MAR 2021) - Alternate II APR 1984

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Wage Determination

RI20220001 Mod 3

13 25-FEB-2022

Attachment 10 DoD Guidance for COVID-19 Vaccination

28 20-DEC-2021

Attachment 11 DD Form 3150 Certification of Vaccination

Attachment 12 COVID-19 Screening Questionnaire

1 10-FEB-2022

Attachment 13 Past Performance Questionnaire (PPQ) - Fill-in by Offeror

Attachment 14 Indication of Interest - Optional

Attachment 2 Specification B47 R119 211 10-MAR-2021 Attachment 3 Drawing Set 20-006A

B47 R119

8 12-MAR-2021

Attachment 4 Submittal Register 4 10-MAR-2021

Attachment 5 List of Key Personnel (Fill-in by Offeror)

Attachment 6 Visitor Request Instructions and Information Needed

Attachment 7 SECNAV Form 5512 Base Access Pass Information

Attachment 8 Use of Masks and Other Public Health Measures

2 04-FEB-2021

Attachment 9 Mask Guidance for all DoD Installations

1 28-JUL-2021

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Wage Determination

RI20220001 Mod 4

13 01-APR-2022

Attachment 10 DoD Guidance for COVID-19 Vaccination

28 20-DEC-2021

Attachment 11 DD Form 3150 Certification of Vaccination

Attachment 12 COVID-19 Screening Questionnaire

1 10-FEB-2022

Attachment 13 Past Performance Questionnaire (PPQ) - Fill-in by Offeror

Attachment 14 Indication of Interest - Optional

Attachment 2 Specification B47 R119 180 28-MAR-2022 Attachment 3 Drawing Set 20-006A

Rev 1 - B47 R119

8 22-MAR-2022

Attachment 4 Submittal Register 28-MAR-2022 Attachment 5 List of Key Personnel

(Fill-in by Offeror)

Attachment 6 Visitor Request Instructions and Information Needed

Attachment 7 SECNAV Form 5512 Base Access Pass Information

Attachment 8 Use of Masks and Other Public Health Measures

2 04-FEB-2021

Attachment 9 Mask Guidance for all DoD Installations

1 28-JUL-2021

(End of Summary of Changes)