2_-_1300619477_DT-100_Staves_SOW_06FEB17.docx_draft.pdf
PDF 43 KB Posted
- Attached to
- DT-100 Staves
- Solicitation number
- N66604-17-R-1497
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6660418R0049U0001.pdf | ||
| cdrls_11_17_2017_16_32_49.pdf | ||
| 25_-_1300619477_DT-100_STAVES_DD-254_16MAY17_(3).pdf | ||
| N6660418R0049.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR DT-100 STAVE PRODUCTION
1.0 BACKGROUND
The Fleet Sensors & Cables Engineering Branch (Code 1535) of the Sensors and Arrays Division (Code
153) of the Naval Undersea Warfare Center Division Newport serves as the Navy's Technical Design Agent (TDA), In-Service Engineering Agent (ISEA), and assists with Acquisition Engineering Agent (AEA) activities for surface ship and submarine transducers, hydrophones and projectors. Code 1535 maintains the Navy's transducer, hydrophone and projector inventory establishing contract vehicles to procure transducers, hydrophones, and projectors which are delivered to both the stock system to support emergent fleet needs and new construction shipyards for initial outfitting.
2.0 SCOPE
This SOW reflects a build-to-print requirement. The contractor shall manufacture, test, package, and deliver DT-100 Staves which meet the requirements of the DT-100 Staves drawing packages listed in Section 3.0.
2.1 APPLICABLE SYSTEMS
The DT-100 Staves are used within the DT-100 High Frequency Receive Modules used for under-ice operations, mine detection and close contact avoidance systems. The DT-100 High Frequency Receive Modules are integral to systems on SSN688I, SSN774, and SSN21 platforms.
2.2 APPLICABLE SPONSORS
IWS 5, Undersea Systems FMS, Foreign Military Sales Office PMS 401, Submarine Acoustic Systems PMS 450, VIRGINIA Class
2.3 APPLICABLE NUWCDIVNPT DEPARTMENTS
Code 15 will utilize the resulting DT-100 Stave production contract to procure DT-100 Staves.
2.4 FUNDING TYPES
Other Procurement, Navy (OPN) Shipbuilding and Conversion, Navy (SCN) Operation & Maintenance, Navy (O&MN) Research, Development, Test & Evaluation, Navy (RDT&EN) Foreign Military Sales (FMS)
3.0 APPLICABLE DOCUMENTS
The following documents, of the issue in effect on the date of request for proposal, form a part of the SOW for this procurement to the extent stated herein.
3.1 NAVSEA Drawing
No. 53711- 8192886-2
Transducer, Hydrophone Stave
3.2 NUWC Drawing
50225-00267RDA
Configuration Management Engineering Drawing Requirements
3.3 NUWC Drawing
50225-00266MN
Configuration Management Engineering Change Document Manual
4.0 REQUIREMENTS
The contractor shall manufacture, inspect, package, and deliver DT-100 Staves which meet the requirements of the applicable document defined in Section 3.0. Table 1 defines the requirements for this procurement.
The following terms apply throughout this requirements section:
Configuration Item The configuration items (CIs) for this contract is the DT-100
Stave
Product Baseline The Product Baseline is established at contract award and is defined in applicable document 3.1.
Table 1. Requirements
Requirement Description Contract Timeframe Applicable CDRLs
4.1 GENERAL
4.1.1 Contract
Kick-Off Meeting
The contractor shall host a Contract Kick-Off meeting at its facility. The contractor shall present the Program Objectives and Milestone Schedule (POAMS) for production to include:
- tasks and major milestones
- CDRL submittals
- production schedule
Within 45 days after contract award
A001 - Agenda
A002 - Meeting Minutes
4.1.2 Progress
Reports
The contractor shall prepare and submit Progress Reports using Government Furnished Information (GFI) item 5.1.
Over the life of the contract
A003 - Production Progress Report
4.1.3 Failure
Reports
The contractor shall establish a system to handle all non-conforming material and to handle any case when a DT-100 Stave fails a Production Acceptance test.
The contractor shall submit Failure Summary and Analysis reports which identify the nature of the failure, and identify remedial and corrective action for preventing future occurrences.
Establish system at the beginning of the contract which is in effect for the life of the contract
A004 - Failure Summary and Analysis Report
4.2.
PRODUCTION
PHASE
4.2.1 Production
Hardware
The contractor shall manufacture, test, package and deliver production DT-100 Staves. The contractor shall manufacture the DT-100 Staves to meet the requirements of applicable document 3.1.
N/A N/A
4.2.2 Serial
Numbers
The contractor shall assign a unique serial number to each DT-100 Stave sequentially beginning with T0001.
N/A N/A
4.2.3 Production
Test and Inspection Procedures
The contractor shall develop Production Acceptance Test and Inspection Procedures. The contractor shall perform final acceptance inspection/testing of all production DT-100 Staves prior to delivery to the Government. Through inspection and acceptance testing, the contractor shall ensure that all DT-100 Staves meet the requirements of applicable documents 3.1.
During active production
A005 - Production Acceptance Test Procedures
4.2.4 Production
Acceptance Test and Inspection Reports
The contractor shall record actual inspection/test results for each production unit by serial number including date of acceptance by the Government. In the Production Acceptance and Inspection Reports, the contractor shall identify units that failed Production Acceptance Tests or were otherwise accepted only after rework and retest and shall explain the circumstances and corrective actions taken where rework occurred.
During active production activity
A006 - Production and Acceptance Test and Inspection Data
4.2.5 Transducer/
Hydrophone Certification Card
The contractor shall complete a Certification Card for each DT-100 Stave to be delivered using GFI item 5.2.
This certification card states that the DT-100 Staves have been constructed in accordance with the approved Product Baseline, and have passed all production inspection/testing.
During active production activity
A007 - Transducer/Hydrophone Certification Card
4.2.6 Production
Program Reviews
The contractor shall host Production Program Reviews semi-annually (maximum). The purpose of the PPRs is to review programmatic and technical issues.
During active production activity
A001 - Agenda
A002 - Meeting Minutes
4.2.7 Engineering
Changes
The contractor shall prepare the Engineering Change Proposals (ECPs) and Requests for Deviation (RFDs) in accordance with applicable document 3.3.
As required during production
A008 - Engineering Change Proposal (ECP)
A009 - Request for
Deviation (RFD)
5.0 Government Furnished Information (GFI):
5.1 DD Form 375 Production Progress Report Form
5.2 Certification Card Template The Government will provide the contractor the certification card template at contract award. The contractor shall complete a certification card for each production dome and submit in accordance with CDRL A007.