Statement of Work
Requirement: Fiber Optic Connectivity
Period of Performance: 30 days ARO
Location: Naval Station Norfolk
1. Complete install of 24-strand, tight buffered single mode fiber-optic cable between Building LF18, NE exterior corner and building N26, Frame Room.
2. Install approximately 550 feet of 3/4" Galvanized Rigid Conduit (GRC) from Building LF18 LF9b to NE exterior corner, and reroute cable with installation of pull rope from manhole LF8 to LF9B.
3. Contractor to remove fiber cable (720’) from interior wall pull box on SE exterior wall of Building LF18, and reroute through manhole LF8, LF9, and LF9B to exterior pull box on NW wall of Building LF18
4. On building LF18 NW wall install 3/4" Galvanized Rigid Conduit (GRC) from LF9B wall pull box to a rooftop pull box per path identified.
5. On building LF18 roof install GRC from the Rooftop pull box and along the rooftop as shown in the “Roof Conduit” to a rooftop pull box as identified in the NE roof area at the top of the N wall.
6. On building LF18 N wall install 3/4" GRC from rooftop pull box to equipment pad at base NE corner of LF18. Conduit would continue from pull box, and down the wall and be landed in a fiber terminal box on the NE corner of the building.
7. The newly integrated fiber optic cable shall be landed and terminated in government approved patch panels using T-SC connectors
8. End-to-end fiber continuity of the installed cable shall be verified and test results shall be provided and approved by the government
9. Drawings documenting the cable run including the cable pathways shall be provided
Notes:
• Attached photo of Building LF18 shows building, manholes and conduit path, and termination at NE corner.
kolste Stamp kolste Line
Blank Page