Plastic Waste Processing Equipment Questions and Answers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N65540-15-R-5163_Amendment_3.pdf | ||
| N65540-15-r-5163_Amendment_2.pdf | ||
| Attachment_2_CMU_Test_Procedures.docx | DOCX document | |
| Attachment_3_AU_Test_Procedures.docx | DOCX document | |
| Exhibit_A_CDRLS.pdf | ||
| Attachment_1_Drawings_of_Record.xlsx | XLSX spreadsheet | |
| N65540-15-R-5163.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
See continuation page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 90
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Dec-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N65540-15-R-5163
X 9B. DATED (SEE ITEM 11)
02-Dec-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Dec-2015
CODE
NAVAL SURFACE WARFARE CENTER PHILA
CODE 02311, KAREN JOHNSON
215-897-7062, KAREN.JOHNSON2@NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
N64498 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N65540-15-R-5163
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT
The Point of Contact for this Amendment is Karen Johnson, Karen.Johnson2@navy.mil
The purpose of the amendment is to (1) add clause 52.232-28, additional drawings and documents Exhibit A, Attachment 1, 2 and 3 (2) respond to questions regarding additional drawings and (3) extend the closing date for the
Solicitation from 15 January 2016 to 20 January 2016. A copy of the additional drawings will be posted in https://www.fbo.gov/ .
Question 1. “We respectfully request the government consider changing the nomenclature for the First
Article(s) to Preproduction Unit and add Clause 52-232-16 Progress Payments for small business.”
Answer 1. The Solicitation is clear on its face. Please refer to Section I Clause 52.232-28 Invitation to
Propose Performance Based Payments of the Solicitation.
Question 2. “Drawing 7556811 Pc 40, refers to Dwg 2, Pc 29. Drawing 7556812, Pc 4, refers to Dwg 1, Pc 65. Drawing 7556812 Pc 17, refers to Dwg 1, Pc 33. We have not located Drawings 1 and 2 in the
TDP. Please provide these drawings, or advise where we can find them.”
Answer 2. See Section J attached.
Question 3. “Page 32 of the solicitation lists under (b) (iv), Drawing 7556871, Pc 8, 9, 20 and 21. We do not find drawing 7556871 listed in the executive summary or in the TDP. Please provide this drawing if it is needed for this solicitation, or advise where we can locate it in the TDP provided. We request an extension of two weeks to submit the proposal after receipt of the government's response.”
Answer 3. See Section J attached.
All other terms and conditions remain unchanged.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 15-Jan-2016 04:00 PM to 20-Jan-2016 04:00 PM.
SECTION I - CONTRACT CLAUSES
The following have been added by reference:
52.232-28 Invitation to Propose Performance-Based Payments MAR 2000 mailto:Karen.Johnson2@navy.mil https://www.fbo.gov/
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been added by full text:
ADDITIONAL DRAWINGS
ATTACHMENT 1
This list summarizes the major changes made to each MOD 1 PWP drawing after 06 August 2014. It is not intended to be a detailed explanation of the revision. Refer to the drawing revision block for the specific details. If there is a conflict between this list and the drawing revision block, the drawing revision block takes precedence.
DWG NO. REV TITLE REMARKS
7556801 C PWP Mod. 1 - Interface Control
Drawing No change
7556802 C PWP Mod. 1 - Electrical Schematic
No change
7556803 A PWP Mod. 1 - Pneumatic Schematic
No change
7556804 - PWP Mod. 1 - CMU Daily Cleaning Placard
No change
7556805 A PWP Mod. 1 - Electrical Enclosure Mounting Adapter
No change
7556806 - PWP Mod. 1 - Auxiliary Unit Grating Assembly and Details
No change
7556807 D PWP Mod. 1 - Cooling Hoses No change 7556808 B PWP Mod. 1 - Disk Storage Bin
Assembly and Details No change
7556810 - PWP Mod. 1 - System Assembly No change 7556811 K PWP Mod. 1 - CMU Assembly No change
7556812 E PWP Mod. 1 - CMU Door Assembly
No change
7556813 D PWP Mod. 1 - CMU Lower Frame Weldment and Machining
No change
7556814 A PWP Mod. 1 - CMU Lower Frame Casting/Weldment
No change
7556815 A PWP Mod. 1 - CMU Upper Frame Assemblies
No change
7556816 E PWP Mod. 1 - CMU Upper Frame Top Plate
No change
7556817 E PWP Mod. 1 - CMU Door Casting and Machining
No change
7556818 D PWP Mod. 1 - CMU Ram Casting and Machining
No change
7556819 C PWP Mod. 1 - CMU Ram & Door Cooling Coil and Heating Elements
No change
7556820 - PWP Mod. 1 - CMU Ram Adapter Weldment and Machining
No change
7556821 B PWP Mod. 1 - CMU Ram Adapter Casting and Machining
No change
7556822 C PWP Mod. 1 - CMU Chamber No change 7556823 - PWP Mod. 1 - CMU Cooling
Water Manifold No change
7556824 A PWP Mod. 1 - CMU Guard Weldment and Assembly
No change
7556825 B PWP Mod. 1 - CMU Shock Mount Casting and Machining
No change
7556826 A PWP Mod. 1 - CMU Washdown Manifold
No change
7556827 D PWP Mod. 1 - CMU Miscellaneous Details and Weldments
No change
7556828 - PWP Mod. 1 - CMU Door Jam Breaker Bar Assembly and Details
No change
7556829 - PWP Mod. 1 - Safety Cover Bracket
No change
7556830 C PWP Mod. 1 - CMU Door Jam Breaker Bar Casting and Machining
No change
7556831 - PWP Mod. 1 - CMU Safety Cover Bracket Modification
No change
7556832 - PWP Mod. 1 - CMU Hinge Bracket Mocification
No change
7556833 D PWP Mod. 1 - CMU & AU Label Plates
Added nameplates and labels for the Mini-Aux controller and the consolidated shredder.
7556834 A PWP Mod. 1 - CMU Safety Cover Modification and Assemby
No change
7556835 - PWP Mod 1 - CMU Safety Cover Assembly and Details
No change
7556836 A PWP Mod 1 - CMU Hinge Bracket No change 7556837 - PWP Mod 1 CMU Hinge Bracket
Weldment and Machining No change
7556840 F PWP Mod. 1 - CMU Rear Electrical Enclosure Conversion
No change
7556841 A PWP Mod. 1 - CMU Pendant Assembly and Details
No change
7556842 B PWP Mod. 1 - CMU Door and Ram Wiring Assembly
No change
7556843 E PWP Mod. 1 - CMU Cable Assemblies
No change
7556844 B PWP Mod 1 - 2-PC Thermostat Assembly and Details
No change
7556845 H PWP Mod. 1 - CMU Rear Electrical Enclosure Assembly and Details
No change
7556846 B PWP Mod 1 - Washdown Controller, Assembly, Details, and Schematic
No change
7556850 E PWP Mod. 1 - Auxiliary Unit Assembly
No change
7556851 A PWP Mod. 1 - AU Frame Assembly
No change
7556852 C PWP Mod. 1 - AU Cooling Water Supply Pipe Assembly
No change
7556853 B PWP Mod. 1 - AU Cooling Water Return Pipe Assembly
No change
7556854 E PWP Mod. 1 - AU Cooling Valve Assembly
No change
7556855 C PWP Mod. 1 - AU Miscellaneous Details
No change
7556856 - PWP Mod 1 - Mini-Aux Controller System Arrangement
No change
7556857 - PWP Mod 1 - Mini-Aux Controller Assembly and Details
No change
7556858 A PWP Mod 1 - Mini-Aux Controller Cooling Valve and Coalescing Filter Assemblies
No change
7556859 - PWP Mod 1 - Interface Drawing with Mini-Aux Controller
No change
7556860 C PWP Mod. 1 - AU Junction Enclosure Assembly and Details
No change
7556861 B PWP Mod. 1 - Auxiliary Unit Control Devices
BASELINE PWP DRAWINGS USED IN MOD 1
FABRICATION
6961210 H Platics Processor - Door Assembly and Details
No change
6961213 C Platics Processor - Hinge Bracket Casting and Machining
No change
6961243 P Platics Processor - Miscellaneous Details
No change
6961248 E Plastics Processor - Exhaust Duct Details
No change
6961250 F Platics Processor - Safety Cover Assembly and Details
No change
6961251 D Platics Processor - Safety Cover Bracket Detail Weldment
6961335 L Platics Processor - Mk II Rear Electrical Enclosure Assembly and Details
MINI AUXILIARY
UNIT
7556856 - Mini-Controller System Arrangment
7556857 - Mini-Aux Controller Assembly and Details
7556858 A Mini-Aux Controller Cooling Valve and Coalescing Filter Assemblies
7556859 - PWP Mod 1 Interface Frawing with Mini-Aux Controller
ICDS
7556801 C PWP Mod 1 Interface Drawing 7556802 B PWP Mod 1 Electrical Schematic 7556856 - Mini-Aux Controller System
Arrangement
7556859 - PWP Mod 1 Interface Drawing with Mini-Aux Controller
7556810 - PWP Mod 1 System Assembly
ATTACHMENT 2
PWP Mod. 1 - CMU and AU Test & Inspection Procedures, Rev 6 References:
(l) 593-7556811, PWP Mod. 1, CMU Assembly
(2) 593-7556812, PWP Mod. 1, CMU Door Assembly
(3) 593-7556834, PWP Mod. 1, CMU Safety Cover Modification and Assembly
(4) 593-7556840, PWP Mod. 1, CMU Rear Electrical Enclosure Conversion
(5) 593-7556850, PWP Mod. 1, Auxiliary Unit Assembly
1.0 VISUAL INSPECTION. Complete the following inspections prior to applying power to the CMU or the rear enclosure. Remove the CMU side and front guards to aid in visual inspection. Record the results of this inspection in the data sheet. If item is satisfactory without adjustment or repair, check the SAT box on the data sheet; if repair or adjustment is required, check the “SAT w/Repair” box on the data sheet.
1.1 CMU. Note: Part numbers given without accompanying reference drawing are from reference (1)
a. Verify that the safety cover assembly (pc 48) sits entirely within the 25.50/25.44 width of the upper frame top plate (pc 59). Recycled safety covers shall be allowed to extend beyond the top plate by no more than
.125-inch.
b. Open the safety cover. Verify the following items:
Verify visually that both gas springs (pc 70) are installed.
Verify that the plastic retainer caps are installed on each end of each gas spring.
Verify visually that the ball studs (pc 61) on the safety cover are installed in the holes closest to the front of the safety cover.
Verify that the gas springs are charged. Fully raise the safety cover and release it; the safety cover should remain in the open position when released.
Verify that both bumpers (ref. 3, pc 5) are installed.
Verify that the bumpers are screwed as far into the safety cover as possible.
c. Close the safety cover and latch the toggle latch (pc 73). Verify the following items:
The latch should toggle and snap into the locked position.
The catch should engage. The toggle should not be able to be released unless the catch lever is released first.
The gap between the bottom of the safety cover and the upper frame should be less than 0.09 inch on average.
d. Verify that the cables and hoses on top of the door are properly routed and secured as shown on reference
(1), section 52-A. Verify the following:
Verify visually that the cable loop clamp (pc 78) is installed on the hinge bracket (ref. 2, pc 12).
Verify that the door power cable W102 (pc 6) is routed in a loop as shown on ref. (l) and is secured in the cable loop clamp.
Verify that air hose H103 (pc 31) and air hose H102 (pc 32) are secured to the power cable.
Verify that the door thermostat TS1 (pc 3 & 161) and the door overtemp switch TS4 (pc 2 & 163) are tied to the cable and hose bundle with slack in the orange silicon leads.
Verify that the orange silicon leads of the door thermostat TS1 (pc 161) and the door overtemp switch TS4 (pc 163) are tied under the hose bundle.
Verify that the cable and hose bundle is secured approximately every 6 inches with blue high temperature wire ties (pc 150).
Verify that the cable from limit switch LS1, W110 (pc 8), is NOT secured to the cable and hose bundle from the door. Cable W110 should run independently of the remainder of the cable and hose bundle.
e. Visually that the door water hoses are correctly routed as shown on reference (1), section 52-A. Verify the following:
Verify that the door water hose labels have been installed and marked with the pressure tested date and the hose description and part number.
Verify that the lower hose (pc 28) is secured to the door with a cable loop clamp (pc 78).
Verify that the upper hose (pc 29) is securely tied to the lower hose with blue high temperature ties
(pc 150).
f. Verify visually that in the unlocked position, the door pneumatic cylinder (ref. 2, pc 24) is bottomed in the extended direction. That is, the cylinder bottoms to stop the unlocking motion rather than some other piece of the door assembly contacting a stationary piece of the CMU assembly
g. Verify that the spherical rod end bearing (ref. 2, pc 25) on the pneumatic cylinder rod is tightly jammed against the rod shoulder.
h. Cycle the door manually from unlocked to locked to unlocked as many times as required to observe the hoses and cables on top of the door to assure freedom of motion. Verify the following:
The orange leads from the thermostats TS1 and TS4 (pcs 3 and 2, respectively) have slack in them and neither is binding, kinking, or pulling.
The stainless steel water hoses (pcs 28 and 29) are sliding freely in the slot in the upper frame top plate and are not pulling or kinking.
i. Lock the door manually. Verify that the trailing edges of the door pivot lugs (ref. 2, pc 17) are flush with the leading edges of the stationary locking lugs (pc 40) within -0/+.25 inch. Note: The door pivot lugs may be flush with the locking lugs or sticking out up to .25 inch. They may not be under the locking lugs.
j. With the door still locked, verify that all four pivot lugs are making contact with the locking lugs. Each lug location should preclude a 0.002-inch feeler gauge over at least half of the lug contact area.
k. Verify that the locked door fully contacts the top of the chamber (pc 13). The door/chamber interface should preclude a 0.005-inch feeler gauge everywhere.
l. Manually unlock the door. Verify that both detent rods (ref. 2, pc 7) disengage and reengage the hinge pin brackets (ref. 2, pc 4) when the latch handle (ref. 2, pc 15) is operated.
m. Verify that the jam nuts on the detent mechanism (ref. 2, pc 46) are tightly jammed against the turnbuckle nuts (ref. 2, pc 23).
n. Verify visually that the clevis pins (ref. 2, pc 30) do not hang up on the hinge bracket (ref. 2, pc 12) when the detent mechanism is operated.
o. Verify visually that the cotter pins and washers (ref. 2, pcs 32 and 48) are installed correctly; that is, to the outside of the crank arm (ref. 2, pc 6).
p. Open the door to the 45° position and verify that both detent rods reengage the holes in the hinge pin brackets and hold the door in the open position when the latch handle is released.
q. Verify that the door assembly does not hit the safety cover in the open position.
r. Cycle the door one or more times from open to close to open. Observe the hoses and wires on top of the door to assure there is no kinking or pulling.
s. Verify visually that the cables and hoses under the ram are properly routed and secured as shown on reference (1), section 46-A. Verify the following:
Verify that the ram power cable W 103 (pc 7) and the two stainless steel water hoses (pc 30) are routed on one side of the cable carrier (pc 65) divider.
Verify that the ram water hose labels have been installed and marked with the pressure tested date and the hose description and part number
Verify that the TS2 and TSS thermostat cables, Wll5 and Wll8, respectively, (pcs 5 and 4) are routed on the other side of the cable carrier divider.
Verify that the thermostat cables are secured by two cable-loop clamps (pc 77). Where the orange silicon wire leads pass thru the first loop clamp, all four leads should be inside the clamp. Where the cable jackets pass thru the second loop clamp, only one cable jacket is inside the clamp and the other cable is attached to the first with blue high-temperature wire ties (pc 150).
Verify that the thermostat cables have slack in the orange silicon lead wires.
Verify that the thermostat cables are routed around the ram adapter (pc 44) so as not to be damaged should the ram be lifted off the adapter.
Verify that the stainless steel water hoses are routed around the ram adapter so as not to be damaged should the ram be lifted off the adapter.
Verify that 45-degree fitting on the ram power cable directs the cable horizontally in the direction of the water hoses.
Verify that the ram power cable is routed with and secured to the stainless steel water hoses.
Verify that all hoses and cables are secured to the entrance of the cable carrier track (pc 65) with blue high-temperature wire ties (pc 150).
Verify that all hoses and cables are secured to the exit of the cable carrier track with white wire ties (pc
151).
t. Verify that all limit switch covers are properly oriented and tight. Verify that all limit switch stuffing tubes are tight.
u. Verify that the door and ram power cable connectors are screwed tightly to their respective receptacle connectors.
v. Verify that the hazard placard (pc 154), warning placard (pc 153), side guard (pc 155), MacLube labels, and CMU nameplate (pc 152) are installed as shown on reference (1), Detail3l-A.
w. Verify that the unit serial number has been stamped on the nameplate.
x. Verify that the four cleaning nozzles (pc 140) on the outside of the chamber are of the 90-degree head type. Verify that the nozzle outlets are pointing inward toward the chamber.
y. Verify that the four cleaning nozzles (pc 139) on the inside of the chamber are of the 45-degree deflected spray type. Verify that the supporting setscrews (pc 108) are light and that the nozzles are pointing outward toward the chamber.
z. Verify that the cleaning nozzle (pc 138) in the rear of the CMU is aimed down toward the cable carrier.
aa. Verify that all nozzles have been plumbed to the washdown manifold (pc 60) at the front of the CMU.
Nozzles should be plumbed with white .38 OD teflon tubing (pcs 35, 36, 37, and 38).
bb. Verify that there is a pipe plug (pc 143) in the end of the washdown manifold.
cc. Verify that there is a hose washer in the garden hose fitting (pc 132) attached to the bottom of the washdown manifold.
dd. Verify that air hoses (pcs 31, 32, 33, and 34) are properly marked and attached to the proper devices.
Verify markings and devices per the following table.
Hose
N o.
Attached to Cylinder End
Designation
Free End
Designa tion
H102 Door Cylinder Rear H102 DR REAR H102 DV
P2
H103 Door Cylinder Front H103 DR FRT H103 DV
P4
H106 Ram Cylinder
Bottom
H106 RAM BOT H106 RV
P2
H107 Ram Cylinder Top H107 RAM TOP H107 RV
P4
ee. Verify that cables W110- WJI8 (pcs 1 thru 11) are attached to the correct devices as shown in the following table.
Cable
No.
Designation Attached to
Wl10 LS1 Door Closed Limit Switch
W111 LS2 Safety Cover Closed Limit
Wl12 LS3 Door Locked Limit Switch
W113 LS4 Ram Retracted Limit
Switch
W114 TS1 Door Thermostat
W115 TS2 Ram Thermostat
W116 TS3 Chamber Thermostat
W117 TS4 Door Overtemp Switch
W1l8 TS5 Ram Overtemp Switch
ff. Verify that the TS3 shield (pc 159) is installed on the chamber.
1.2 REAR ELECTRICAL ENCLOSURE, Note: Part numbers given without accompanying reference drawing are from reference (4).
a. Verify that the electrical hazard placard (pc 108), the nameplate (pc 112), and the instruction plate (pc
113) are installed as shown in reference (4), detail 19-A.
b. Verify that the unit serial number has been stamped on the nameplate.
c. Verify that fuses are installed in the fuse holders in accordance with the following table.
d. Verify that relay 1R2 (pc 67) is set for 30-second delay (50% of 1-minute scale).
e. Verify that relay 1R3 (pc 68) is set for 3-minute delay (30% of 10-minute scale).
f. Verify that the display unit cable assembly (pc 5) end connectors are screwed firmly to the PLC and the display unit.
g. Verify that the cable bundle between the enclosure and the door passes thru the cable loop clamp (pc
20).
h. Verify that the devices on the panel and the receptacles on the bottom of the enclosure are labeled in accordance with note 4.2 on reference (4).
i. Verify that a watertight cap (pc 6) is installed on connector 1J7 on the bottom of the electrical enclosure.
j. Verify that a watertight cap (pc 6) is installed on connector lJ8 on the bottom of the electrical enclosure
k. Verify that a watertight cap (pc 7) is installed on connector 1J1 on the bottom of the electrical
l. Verify that the large stuffing tube (pc 33) has a packing assembly installed.
m. Verify that the small stuffing tubes (pc 32) have plugs installed.
n. Verify that the Hubbell Junior stuffing tubes (pc 31) have packing assemblies installed. Verify that the caps are snug (so they don't fall off during shipping and handling).
o. Verify that the wire label tags that will be placed on the field wires at installation are inside the
2.0 WATER AND AIR TIGHTNESS TESTS
Prior to beginning the water and air tightness test, verify that the following conditions are met. The CMU is connected to 450 +/-· 10 VAC power; the AU is connected to low-pressure air at 120 to 125 psi
Fuse
Designation
Ref (4) Pc No Rating P/N
F1 thru F6 Pc 53 600 V, 20A, fast acting KLK20, ATM 20
F7 & F8 Pc 51 600 V, 0.3 A, class CC KLDR.3
F9 Pc 52 250 V, l A, time delay FLM1
F10 Pc 50 250 V, Y ½ A, time delay FLM.5
2.1 Hydrostatic Test. The CMU cooling loop must be hydrostatically tested to 275 psi to assure there are no leaks
Record the results of this test in data sheet. Note any leaks repaired
a. Connect a water pressure source capable of 275 psi to the inlet fitting (the -12 size fitting on the outboard side of the water manifold) at the rear of the CMU.
b. Turn on the water at low pressure and allow the CMU to fill until water runs freely from the water outlet fitting (the -12 size fitting on the inboard side of the water manifold) at the rear of the CMU.
c. Cap the outlet fitting.
d. Bleed the CMU of air by cracking the hose fittings on top of the CMU door. Allow air to bleed and retighten hose fittings.
e. Pressurize the CMU water loop to 275 psi and hold for 15 minutes. Visually inspect all fittings and hoses for leaks. All leaks must be repaired and the CMU must be held at 275 psi for 15 minutes after the last repair to assure all joints are tight.
f. Vent all pressure from the CMU water loop.
2.2 Air Tightness Test The CMU air system must be tested to 120 psi to assure there are no leaks. Record the results of these tests in the data sheet. Note any leaks repaired.
a. The safety cover should be open and the CMU door closed.
b. Connect a shop air source capable of 120 psi to hose H103. Tum on air pressure and the door will lock.
c. Use soap solution on the door air cylinder rod end fittings center section with piston extended and rod seals to detect leaks. All leaks must be repaired and H103 must be held at 120 psi for 5 minutes after
d. Vent pressure from H103.
e. Connect a shop air source capable of 120 psi to hose H102. Turn on air pressure and the door will unlock.
f. Use soap solution on the door air cylinder blind end fittings to detect leaks. All leaks must be repaired and H102 must be held at 120 psi for 5 minutes after the last repair to assure all joints are tight.
g. Vent pressure from H102.
h. Open the CMU door.
i. Connect a shop air source capable of 120 psi to hose HI06. Turn on air pressure and the ram will extend.
j. Use soap solution on the ram air cylinder blind end fittings to detect leaks. All leaks must be repaired and H106 must be held at 120 psi for 5 minutes after the last repair to assure all joints are tight.
k. Vent pressure from H106.
l. Connect a shop air source capable of 120 psi to hose H107. Turn on air pressure and the ram will retract.
m. Use soap solution on the ram air cylinder rod end and rod seals to detect leaks. All leaks must be repaired and H107 must be held at 120 psi for 5 minutes after the last repair to assure all joints are
n. Vent pressure from H107.
3.0 SWITCH ADJUSTMENT CHECKS
Prior to beginning the switch adjustment checks, verify that the following conditions are met. TEST
CONDITIONS. The CMU is connected to 450 +1/- 10 VAC power; the AU is connected to shop air at l20 to
125 psi;
3.1 Pre-Startup. This section requires the CMU to be connected to a rear electrical enclosure, an Auxiliary Unit, and a pendant electrical controller. The AU should have passed all tests and inspections in the latest version of
AU-TEST Procedure prior to being used in the following series of tests.
a. Connect the cabling W110 thru W118 between the CMU and the rear electrical enclosure as shown in
Section 15-B on drawing 7556810.
b. Connect cable W l 09 between the CMU rear electrical enclosure (plug P2) and the Auxiliary unit electrical enclosure.
c. Connect the pendant controller cable W108 to the rear electrical enclosure at plug P9.
d. Connect the CMU Rear Electrical Enclosure to a 450 +1- 10 VAC power supply. Connect as shown in
Detail 16-E on 7556810. Do not turn on power to the CMU at this time.
Note: The following steps assume that the “A” side of the auxiliary unit (AU) is being used for testing.
If the “B” side is used, substitute “B” valve designations (XXB) for the “A” valve designations
(XXA) used below. See Figure 1 for plumbing described below.
e. Connect hose H102 from the CMU to port 2 on the door control valve DVA on the AU. Connect hose
H103 from the CMU to port 4 on the door control valve DVA on the AU.
f. Connect hose Hl 06 from the CMU to port 2 on the ram control valve RV A on the AU. Connect hose
H107 from the CMU to port4 on the ram control valve RVA on the AU.
g. Close manually operated air isolation valves AVA and AVB on the Auxiliary Unit.
h. Connect a low pressure air source (100 to 125 psi) to the Auxiliary Unit air inlet fitting. Leave manually operated air isolation valves AVA and AVB on the AU closed at this time.
WARNING: In steps “h” and “i” below, do not tighten the compression fittings when connecting the 3/8 OD tubing or the ferrules will be permanently attached to the tubing.
i. Connect a length of 3/8-inch OD teflon tubing between the exhaust port elbow on the CMU and the pressure port on the air flow switch FSA on the AU. Note that the pressure port is on the rear (side where the mounting bracket is located) of the air flow switch. Do not tighten the compression fittings when making these connections; simply insert the hose.
j. Connect a length of 3/8-inch OD teflon tubing between the exhaust duct connector on the CMU and the vacuum port on the air flow switch FSA on the AU. Note that the vacuum port is on the front (side where the electrical junction box is located) of the air flow switch. Do not tighten the compression fittings when making these connections; simply insert the hose.
k. Connect a 4-inch diameter flexible exhaust duct to the exhaust duct connector on the rear of the CMU.
The exhaust system shall have a fan calibrated to 100 +1- 10 CFM of air flow out of the CMU. Leave the fan off at this time.
l. Interconnect between the CMU and the AU with %-inch nominal ID hose with female -12 size SAE
37° flare swivel ends. Interconnect as shown in figure l.
m. Connect the inlet (lower) flange on the Auxiliary Unit to a cooling water source capable of flowing 10 to 30 GPM of cold fresh water. This water source shall have a shutoff valve in the line. Do not tum on the cooling water at this time.
n. Connect the outlet (upper) flange on the Auxiliary Unit to a drain.
Figure 1. CMU to AU connection
o. Loosen the display unit cover on the CMU rear electrical enclosure so the function keypad can be accessed.
p. Loosen the clamps that secure the door on the REE so that the internal components can be accessed and inspected during the following procedures.
q. Open the CMU safety cover. The CMU door should be unlocked and closed.
3.2 Startup. The door control valve on the AU may be shifted to either the lock or unlock position on initial power
up. The current position must be determined and the valve shifted to the unlock position
a. Push in the emergency stop pushbutton on the CMU control pendant
b. Turn on 450 VAC power to the CMU rear electrical enclosure, CAUTION
The current PLC program version is and the current display unit program version is. If program versions other than these are installed, stop and install the current program versions.
c. Note CMU and CDU program versions at startup: PLC: _____ ,Display: ____ _
d. The following message should be displayed after PLC startup: 08) PULL OUT E-STOP THEN PRESS
RESET,
e. Pull out the Emergency Stop pushbutton on the CMU pendant controller, The following message should be displayed: 02) MACHINE SHUTDOWN PRESS RESET,
f. Open manually operated air isolation valve AVA on the AU,
g. Note whether the CMU door remains unlocked or if it locks, If the door locks, manually over-ride solenoid 12 on the door control valve DVA on the AU to cause the door to unlock,
h. Open the door.
i. Press the RESET pushbutton,
j. The ram should fully retract,
k. Tum on cooling water flow at the AU inlet piping assembly,
l. Tum on the CMU exhaust system fan.
3.3 AIR FLOW SWITCH ADJUSTMENT
3.3.1 Air Flow Switch FSA. See reference (5) for location of FSA
a. Remove the cover from FSA electrical junction box,
b. Use a nut driver to loosen the adjusting nut until there is no tension on the spring, PLC slot I, light A5 should be lit
c. Tighten the adjusting nut until PLC slot l, light A5 goes out
d. Loosen the adjusting nut just until PLC slot 1, light A5 comes back on,
e. Loosen the adjusting nut an additional ½ tum,
f. Tum the exhaust fan off, Verify the PLC slot l, light A5 goes out,
g. Tum the exhaust fan back on, Verify that PLC slot 1, light A5 lights up,
h. If the conditions from steps “e” and “f” are met, adjustment is complete, Replace the cover on the junction box, If these conditions are not met, repeat steps “b” through “g” until satisfactory adjustment is achieved,
3.3.2 Air Flow Switch FSB. See reference (5) for location of FSB
a. Press in the E-STOP pushbutton.
b. Turn off 450 VAC power to the CMU.
c. Turn off the exhaust fan.
d. Move the AU cable W109 from the “A” side electrical enclosure to the “B” side electrical enclosure.
e. Connect the vent lines from the CMU to the pressure and vacuum ports on FSB. Do not tighten the compression fittings.
f. Turn on 450 VAC power to the CMU.
g. Pull out the E-STOP pushbutton.
h. Press the RESET pushbutton.
i. Turn on the exhaust fan.
j. Remove the cover from FSB electrical junction box.
k. Use a nut driver to loosen the adjusting nut until there is no tension on the spring. PLC slot 1, light A5 should be lit.
l. Tighten the adjusting nut until PLC slot 1, light A5 goes out.
m. Loosen the adjusting nut just until PLC slot l, light A5 comes back on.
n. Loosen the adjusting nut an additional ½ turn.
o. Tum the exhaust fan off. Verify that PLC slot l, light A5 goes out.
p. Tum the exhaust fan back on. Verify that PLC slot l, light A5 lights up.
q. If the conditions from steps “e” and “T” are met, adjustment is complete. Replace the cover on the junction box. If these conditions are not met, repeat steps “k” through “p” until satisfactory adjustment is achieved.
r. Turn off the exhaust fan.
s. Press the E-STOP pushbutton.
t. Turn off 450 VAC power to the CMU.
u. Move the AU cable W109 from the “B” side electrical enclosure to the “A” side electrical enclosure.
v. Connect the vent lines from the CMU to the pressure and vacuum ports on FSA. Do not tighten the
w. Turn on 450 VAC power to the CMU.
x. Pull out the E-STOP pushbutton.
y. Press the RESET pushbutton
3.4 LIMIT SWITCH ADJUSTMENT.
3.4.1 Door Closed Limit Switch LS l Adjustment. See ref. (1), Sections 52-A and 55-E for location of LS1.
LS1should have been adjusted when it was installed on the CMU. Complete the check in step “a” below. If adjustment is correct, skip to section 3.4.2. If adjustment is incorrect, complete the rest of this procedure.
a. Open the safety cover and door. Slowly close the door and note the position where LS1 energizes (PLC slot1, light A6 lights). LS1 should energize when the bottom of the door is 1.00 to 3.00 inches from the top of the chamber at the front. Record the value: ___________ inches.
b. Open the door.
c. Verify visually that the roller arm on LSI is oriented upward at approximately a 15° angle. (Note:
When the arm is rotated counterclockwise, the switch should energize when the arm is parallel to the top plate.)
d. Close the CMU door until the bottom of the door is approximately 2 inches above the top of the chamber
e. Loosen the jam nut on the flag bolt and adjust the bolt up or down until LS1 energizes (PLC slot 1, light 6 lights).
f. Retighten the jam nut.
g. Open the door to the 45 degree position
h. Slowly close the door and note the position where L1I energizes (slot 1, light A6 lights). LSI should energize when the bottom of the door is 1.00 to 3.00 inches from the top of the chamber at the front.
Record the value: _______________ inches.
i. If adjustment is not correct, repeat steps “b” through “g” until correct adjustments have been achieved.
Press the RESET pushbutton
3.4.2 Safety Cover Closed Limit Switch LS2 Adjustment. See ref (1) Section 52-A and Detail 50-E for location of
LS2. LS2 should have been adjusted when it was installed on the CMU. Complete the check in step “a” below. If adjustment is incorrect, complete the rest of this procedure.
a. Unlatch and raise the safety cover. Slowly close the safety cover and verify that the switch activates
(PLC slot2, light A7 lights) when the safety cover is closed (0.5-inch or less from the top plate).
Record the distance between the bottom of the safety cover and the top when LS2 activates:
b. Adjust the LS2 flag bracket (ref. l, pc 23) so that the threaded rod (ref. l, pc 109) is centered in the hole in the safety cover bracket.
c. Adjust the threaded rod so that it protrudes 0.31 - 0.38-inch beyond the back of the safety cover bracket when the safety cover is closed and pinned shut. See ref. (l), Detail 50-E.
d. Close the safety cover and latch it shut.
e. Loosen the limit switch lever arm cap screw so that lever arm is free to rotate on the limit switch shaft.
f. Hold the lever arm roller in contact with the threaded rod.
g. Rotate the switch shaft counterclockwise with a screwdriver until the switch activates (PLC slot 2, light A7 lights).
h. Retighten the lever arm cap screw.
i. Unlatch and raise the safety cover. Slowly close the safety cover and verify that the switch activates
(PLC slot2, light A7 lights) when the safety cover is fully closed (0.5-inch or less from the top plate).
Record the distance between the bottom of the safety cover and the top plate when LS2 activates:
j. If adjustment is not correct, repeat steps “b” through “i” until proper adjustment is achieved.
3.4.3 Door Locked Limit Switch LS3 Adjustment. See ref (l), Section 52-A and Detail52-E for location of LS3.
LS3 should have been adjusted when it was installed on the CMU. Complete steps “a” thru “e” below to check for correct adjustment. If adjustment is correct, skip to section 3.4.4; if incorrect, complete the rest of this procedure.
a. Lock the CMU door by pressing function key F10 on the display unit keypad.
b. Mark the location of the door pivot lug (ref. 2, pc 17) relative to the leading edge of the fixed locking lug (ref. l, pc 40) with a washable or water-soluble marker. See Figure 2.
c. Unlock the door by pressing function key F11 on the display unit keypad.
d. Measure 0.38 inch to the left of the mark made in step “b” above and make another mark. Measure
0.88 inch to the left of the mark made in step “b” above and make another mark. See Figure 2.
e. Bleed air pressure from the door lock cylinder and manually rotate the door to the locked position. The door locked limit switch LS3 should activate (FLC slot l, light A8 lights) when the door has rotated so the leading edge of the fixed locking lug is between the two marks made in step “d” above. If adjustment is correct, skip to section 3.8; if not, continue with this procedure.
f. Unlock the door. Remove the air cylinder and the shock absorber from the door
g. Manually rotate the door to position the leading edge of the locking Jug midway between the marks made in step “-d” above.
h. Loosen the limit switch lever arm cap screw so that lever arm is free to rotate on the limit switch shaft.
i. Hold the lever arm roller in contact with the door locked switch flag (ref. 2, pc 10).
j. Rotate the switch shaft counterclockwise with a screwdriver until the switch activates (FLC slot l, lightA8 lights).
k. Retighten the lever arm cap screw.
l. Manually rotate the door unlocked. Slowly rotate the door locked and verify that LS3 activates when the leading edge of the locking lug is between the marks made in step “d” above.
m. If adjustment is correct, rotate the door to the unlocked position and re-install the air cylinder and the shock absorber. If adjustment is not correct, repeat steps “g” through “l” until satisfactory adjustment
n. Leave the door unlocked.
Figure 2. Door Locked Limit Switch Adjustment Check
3.4.4 Ram Retract Limit Switch LS4 Adjustment. See ref. (1), Section 42-A for location of LS4. LS4 should have been adjusted when it was installed on the CMU. Complete steps “a” thru “d” below to check for correct adjustment. If adjustment is correct, skip to section 4.0; if incorrect, complete the rest of this procedure.
a. Open the door.
b. Pull out the E-stop pushbutton and press the reset pushbutton.
c. PLC slot l, light B l should be lit.
d. Press function key F6 to extend ram. As soon as the ram rises from the bottom, PLC slot l, light B 1 should go out.
e. Press function key F7 to retract ram. When the ram reaches the bottom of travel, PLC slot l, light B1 should light.
f. Leave the ram in the fully retracted position.
g. Loosen the limit switch lever arm cap screw so that the lever arm is free to rotate on the limit switch shaft.
h. Hold the lever arm roller in contact with the bottom of the ram skirt.
i. Rotate the switch shaft counterclockwise with a screwdriver until the switch activates (PLC slot I, light
B1lights).
j. Retighten the lever arm cap screw.
k. Press function key F6 to extend ram. As soon as the ram rises from the bottom, PLC slot l, light should go out.
l. Press function key F7 to retract ram. When the ram reaches the bottom of travel, PLC slot l, light B1 should light.
m. If the requirements of steps adjustment is achieved.
4.0 FUNCTIONAL TEST
4.1 PRE-START-UP. Prior to beginning the functional test, verify that the following conditions are met. TEST
CONDITIONS The CMU is connected to 450 +/- 10 VAC power; the AU is connected to shop air at 120 to
125 psi and to cooling water as noted.
a. The PLC PROM and the display unit PROM are the latest revision.
b. The CMU and rear electrical enclosure have passed visual inspection per section 1.0 of this procedure.
c. The CMU cooling water loop has passed hydrostatic testing per section 2.1 of this procedure.
d. The CMU air system has passed air tightness testing per section 2.2 of this procedure.
e. Air flow switches FSA and FSB have been adjusted per section 3.3 of this procedure.
f. Limit switches LSI through LS4 have been adjusted per section 3.4 of this procedure.
g. Shop air at 120 to 125 psi is turned on to the AU. Manual isolation valve AVA on the AU has been opened.
h. Cooling water capable of flowing 10 to 30 GPM is turned on to the inlet flange of the AU.
i. The CMU is connected to 450 +/- 10 VAC power.
j. The CMU rear electrical enclosure door is open to permit viewing of the PLC module indicator lights.
k. The display unit cover is loose to permit access to the function keypad.
l. The CMU side and front guards are off. Loosen the limit
4.2 PLC INITIALIZATION.
a. Close the CMU door if it is open. Close the safety cover if it is open.
b. If the CMU is energized, turn off 450 VAC power to the CMU.
c. Press the EMERGENCY STOP push-button on the pendant controller.
d. Turn on 450 VAC power to the CMU.
e. Record the PLC and Display Unit program version number as displayed on the startup screen on the display unit (DU1).
PLC: PCMU ____________ DISPLAY: PCDU __________
f. Verify that the red PROBLEM INDICATED and white POWER ON indicators on the rear electrical enclosure are lit.
g. Verify the display unit message is: 08) PULL OUT E-STOP THEN Press RESET.
h. Verify that the PLC PWR, OK, and RUN indicators are lit. Verify that the BATT light is off.
i. Measure the voltage at the CMU transformer primary terminals H1 to H4. The voltage should be between 440 and 460 VAC. Record this reading: ____________ VAC.
j. Measure the voltage at the CMU transformer secondary terminals X1 to X2. The voltage should be between 110 and 120 VAC. Record this reading: ____________ VAC.
k. Pull out the EMERGENCY STOP push-button on the CMU pendant controller. Verify that the red
PROBLEM INDICATED indicator goes out and the white POWER ON indicator remains lit.
l. Verify the display unit message is: 02) MACHINE SHUTDOWN, PRESS RESET.
4.3 PLC I/O CHECK
4.3.1 RESET Pushbutton
a. Press the RESET pushbutton.
b. Verify that PLC slot l, light A2 lights while the RESET pushbutton is held.
c. Verify that the master control relay (1R1) has energized (PLC slot 1, light A1 lights).
d. Verify that the air blocking valve solenoid has energized (PLC slot 3, light A5 lights)
Note: If the ram is not fully retracted, it will retract. If the door is locked, it will unlock.
e. Verify the display unit message is E) OPEN COVER
f. Press and hold the RESET pushbutton. Verify the message 05) ALREADY RESET is displayed while the RESET pushbutton is held.
g. Verify the message E) OPEN COVER
4.3.2 PROCESS Pushbutton
a. Open the safety cover. Verify message F) OPEN DOOR TO LOAD
b. Open the door. Verify the message G) PREP. CHAMBER, LOAD & CLOSE DOOR
c. Press the PROCESS pushbutton.
d. Verify that PLC slot 1, light A3 lights while the PROCESS pushbutton is held.
e. Verify that the following message is displayed while the PROCESS pushbutton is held: 14) CLOSE
DOOR TO PROCESS.
f. Close the door. Verify message H) CLOSE COVER.
g. Press the PROCESS pushbutton.
h. Verify the following message is displayed while the PROCESS pushbutton is held: l3) CLOSE
COVER to PROCESS.
4.3.3 EJECT Pushbutton
a. Close the safety cover. Door will lock.
b. Push the EJECT pushbutton. Verify the ram does not move. Verify the following message is displayed while the EJECT button is pushed: “10) OPEN COVER TO EJECT.”
c. Press the RESET pushbutton. The door will unlock. Verify message E) OPEN COVER is displayed.
d. Open the safety cover. Verify the following message is displayed: F) OPEN DOOR TO LOAD.
If the ram moves when the EJECT pushbutton is pushed in the next step, immediately push in the EMERGENCY STOP pushbutton and troubleshoot. If the ram is allowed to move against the unlocked door, damage to the CMU is likely.
e. Leave the door closed and again push the EJECT pushbutton. Verify the ram does not move. Verify the following message is displayed while the EJECT button is pushed: “09) OPEN DOOR TO
EJECT.”
f. Open the door. Verify the following message is displayed: G) PREP. CHAMBER, LOAD & CLOSE
DOOR.
g. Press the EJECT pushbutton.
h. Verify that PLC slot l, light A4 lights while the EJECT pushbutton is held.
i. Verify that the ram extend solenoid energizes (PLC slot 3, light A3 lights) when the EJECT pushbutton is pressed.
j. Verify that the ram moves up in the chamber.
k. Verify that LS4 de-energizes as the ram moves from the fully retracted position (PLC slot l, light B l goes out).
l. Verify that the ram extend solenoid de-energizes (PLC slot 3, light A3 goes out) after approx. 5 seconds.
m. Verify the following message is displayed: A) READY to RESET
4.3.4 Ventilation Flow Switch
a. Verify that PLC slot 1, light A5 is off.
b. Turn on the exhaust ventilation fan to the CMU. Verify that PLC slot1, light A5 lights.
c. Turn ventilation off. Verify that PLC slot 1, light A5 goes out.
4.3.5 Retract Ram. Press function key F7 (RETRACT RAM) on the display unit. Verify that PLC slot3, light A4 lights while function key F7 is held.
a. Verify that the display unit message is F7) RAM RETRACTING while the function key is held.
b. Verify that the ram moves down in the chamber.
c. When the ram is fully retracted, verify that LS4 activates (PLC slot I, light B l lights).
d. Verify the following message is displayed: G) PREP CHAMBER, LOAD, & CLOSE DOOR.
4.3.6 Extend Ram. Press function key F6 (EXTEND RAM) on the display unit.
a. Verify that PLC slot 3, light A3 lights while function key F6 is held.
b. Verify that the display unit message is F6) RAM EXTENDING while function key F6 is held.
c. Verify that the ram moves up in the chamber.
d. Verify the following message is displayed: A) READY to RESET Turn
4.3.7 Blocking Valve
a. Press function keys F6 and F7 simultaneously. Verify that the blocking valve solenoid de-energizes
(PLC slot 3, light A5 goes out).
b. Verify the following message is displayed: F6/F7) BLK VALVE CLOSED- RESET or F11.
c. Press function key F7 for 1 to 2 seconds and release. The ram should move down while the function key is held and stop when the function key is released.
d. Press and hold function key F7 until the ram is fully retracted (PLC slot l, light B l lights).
e. Press function key F6 for l to 2 seconds and release. The ram should move up while the function key is held and stop when the function key is released.
f. Press function key F8 on the display unit. Verify that the blocking valve solenoid energizes (PLC slot
3, light A5 lights). The ram will move up to the eject position.
g. Verify the following message is displayed: F8) BLOCKING VALVE OPEN. After a few second delay, the following message will appear: A) READY TO RESET.
h. Press F6 and F7 simultaneously. Verify message F61F7: BLK VALVE CLOSED- RESET or F8.
i. Press the RESET pushbutton. Verify that the ram fully retracts and the following message is displayed:
G) PREP CHAMBER, LOAD, & CLOSE DOOR.
4.3.8 Door Closed Limit Switch LS1
a. Close the door slowly chamber, limit switch LSI energizes (PLC slot 1, light A6 lights).
b. Fully close the door.
c. Verify the following message is displayed: H) CLOSE COVER.
4.3.9 Safety Cover Closed Limit Switch LS2
a. Close the safety cover slowly. Verify that when the safety cover is fully closed, limit switch LS2 energizes (PLC slot l, light A7 lights).
b. After LS2 energizes, the door lock solenoid is automatically energized. Verify that PLC slot 2, A6 lights.
c. Verify the following message is displayed while the door is locking: I) DOOR LOCKING. (Note: This event may occur too fast for message “T” to be displayed.)
d. Verify slot 1, light A8 is lit (door locked).
e. Verify the following message is displayed when the door is locked: J) READY TO PROCESS, RESET
OR SHUTDOWN.
f. Open the safety cover.
Note: Step “g” must be performed within 20 seconds of step “f” or the CMU will go into problem shutdown mode.
g. Verify that the alarm horn sounds for 2 seconds and the following message is displayed: 27) CLOSE
COVER WHILE DOOR IS LOCKED.
h. Close the safety cover.
4.3.10 Door Unlock.
a. Press function key F9 (DOOR UNLOCK) on the display unit keypad.
b. Verify that the door unlock solenoid energizes (PLC slot 2, light A71ights).
c. Verify the following message is displayed while the function key is held: F9) FORCE DOOR TO
UNLOCK.
d. As the door rotates to unlock, verify that limit switch LS3 de-energizes (PLC slot 1, light A8 goes out).
e. Verify the following message is displayed after the door is unlocked: E) OPEN COVER.
f. Open the safety cover.
g. Verify the following message is displayed: F) OPEN OOOR TO LOAD.
4.3.11 Door Heaters.
a. Open the door.
b. Press and hold function key F2 (ACTIVATE DOOR HEATERS) on the display unit.
c. Verify that PLC slot 3, light A1 lights.
d. Verify that the display unit message is F2) DOOR HEATER ON.
e. Verify that the door surface begins to warm.
WARNING
Working on energized electrical equipment could lead to death or injury from electrical shock.
f. Using a clamp on ammeter, measure the current in the door heater leads 1KD-L1, lKD-L2, and 1KD-
L3. The current value should be between 13.5 and 15.5 amps. Record current readings:
DOOR HEATER: L1 __________ Amps, L2 __________ Amps, L3 __________ Amps
4.3.12 Ram Heaters.
a. Press and hold function key F3 (ACTIVATE RAM HEATERS) on the display unit
b. Verify that PLC slot 3, light A2 lights.
c. Verify that the display unit message is F3) RAM HEATER ON.
d. Verify that the ram surface begins to warm.
Working on energized electrical equipment could lead to death or…