Statement_of_Work_EQT_Draft.docx
DOCX document 92 KB Posted
- Attached to
- PD-33-0143; Env Qual Testing
- Solicitation number
- N64498-26-RFPREQ-PD-33-0143
About this file
This is a Statement of Work (SOW) for Environmental Qualification Testing (EQT) Services for the Naval Surface Warfare Center Philadelphia Division (NSWCPD), a Department of Defense research, development, and test organization supporting Navy ships, submarines, and unmanned vehicles.
NSWCPD Code 333 requires contractor support to develop and deliver comprehensive environmental qualification testing for Hull, Mechanical, and Electrical (HM&E) equipment. The primary scope includes: developing detailed EQT plans and test procedures; designing, engineering, and fabricating standard and non-standard structural test fixtures; transporting, mounting, and instrumenting equipment under test (EUTs); conducting test events at designated facilities; operating data acquisition systems; and analyzing test data to produce final qualification reports. Testing covers high-impact mechanical shock (lightweight, medium-weight, and heavyweight shock machines), shipboard mechanical vibration, climatic/thermal exposure, and electromagnetic environmental effects per MIL-DTL-901E, MIL-STD-167-1A, MIL-STD-461F, and MIL-STD-461H standards. Contractor personnel must be U.S. citizens and include qualified engineers, technicians, and machining staff. Key personnel include one EQT Coordinator (seven years' EQT experience, three years' project management experience) and supporting mechanical engineers, electrical engineers, drafters, and technicians at various experience levels. The contract requires submission of multiple Contract Data Requirements Lists (CDRLs) including monthly status reports, test plans/procedures, fixture design packages with CAD drawings and finite element analyses, test reports with raw data and compliance matrices, and periodic government property inventory reports. The work is estimated at 95% contractor facility-based performance with travel to Philadelphia and Washington, D.C. All personnel require security training and clearances up to SECRET level, with specific requirements for Navy Nuclear Propulsion Program (NNPP) work including Confidential clearances and U.S. citizenship. The contract involves handling Controlled Unclassified Information (CUI) and Navy-sensitive technical data with strict operational security requirements. This SOW is associated with a pre-solicitation (Sources Sought) notice issued for market research purposes with responses due by December 15, 2026, to jenny.e.tomeo.civ@us.navy.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought_EQT_Nov2026.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) for Environmental Qualification Testing Services
1.0 INTRODUCTION
1.0.1 The Naval Surface Warfare Center Philadelphia Division (NSWCPD) is a Department of Defense entity responsible for research and development, test and evaluation, engineering and fleet support organization for the Navy’s ships, submarines, military watercraft and unmanned vehicles. This requirement is for NSWCPD Code 333, which has the responsibility of providing environmental qualification testing services for a wide array of Hull, Mechanical, and Electrical (HM&E) equipment that is used, modernized, upgraded, maintained, and/or sustained by any of the NSWC Technical Departments.
1.0.2 This contract is for non-personal services. It does not create employment rights with the U.S. Government whether actual, inherent, or implied
1.0.3 Government/Contractor Relationship
1.0.3.1 The services to be delivered under this Contract/Task Order are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the Contract/Task Order between the Government and the Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.
1.0.3.2 The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence.
1.0.3.3 Contractor personnel under this Contract/Task Order shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.
1.0.4 Employee Relationship:
1.0.4.1 The services to be performed under this Contract/Task Order do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.
1.0.4.2 Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.
1.0.4.3 Inapplicability of Employee Benefits: This Contract/Task Order does not create an employer-employee relationship. Accordingly, entitlements and benefits applicable to such relationships do not apply.
1.0.4.4 It is the Contractor's, as well as the Government's, responsibility to monitor Contract/Task Order activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.
1.0.4.4.1 The Contractor shall notify the Contracting Officer in writing via letter or email within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the Contractor's estimated date when, absent a response, cost, schedule or performance will be impacted.
1.0.4.4.2 The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:
i. Confirm the conduct is in violation and when necessary direct the mode of further performance,
ii. Countermand any communication regarded as a violation,
iii. Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or
iv. In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.
1.1 BACKGROUND
Naval Surface Warfare Center, Philadelphia Division (NSWCPD) provides direct naval engineering, test, and evaluation services to validate that machinery, control systems, electrical distribution components, and auxiliary hardware can withstand the severe physical and climatic operating conditions encountered aboard U.S. Navy surface ships and submarines. To verify shipboard survivability and operational readiness, equipment items (Equipment Under Test (EUTs)) must undergo comprehensive Environmental Qualification Testing (EQT). These tests include, but are not limited to, high-impact (HI) mechanical shock, shipboard mechanical vibration, climatic/thermal exposure, and electromagnetic environmental effects (E3). NSWCPD Code 333 is the In-Service Engineering Agent (ISEA) for surface ship and submarine HI Shock, Shipboard Vibration, and Electromagnetic Compatibility (EMC)/Electromagnetic Interference (EMI) EQT, and overall ship hardening of HM&E systems. As the ISEA, Code 333 utilizes Objective Quality Evidence (OQE), such as the results of laboratory tests conducted in accordance with governing standards, to determine a basis for equipment qualification.
1.2 SCOPE OF WORK
To ensure rigorous and repeatable testing, the Government requires professional contractor support to develop and deliver tailored test plans and procedures, design and fabricate standard and non-standard test fixtures, configure instrumentation and data acquisition systems, conduct test events, analyze high-fidelity physical and electrical data, and develop and deliver final qualification test reports.
The Contractor shall provide qualified engineering, technical, machining, and testing personnel to execute environmental qualification testing requirements for NSWCPD. The Contractor's primary tasking includes:
1. Developing comprehensive, detailed EQT Plans and Test Procedures.
2. Designing, engineering, stress-analyzing, and fabricating standard and non-standard structural test fixtures and interface adapters.
3. Transporting, mounting, instrumenting, setting up, and safely executing environmental qualification test events at designated Government or commercial test facilities.
4. Operating data acquisition (DAQ) systems, sensors, and instrumentation to acquire, record, validate, and analyze test event data.
2.0 APPLICABLE DOCUMENTS
1.1 MIL-DTL-901E, Shock Tests, H.I. (High Impact) Shipboard Machinery, Equipment, and Systems, Requirements for (20 June 2017)
2.1.1 MIL-S-901D, Shock Tests, H.I. (High Impact) Shipboard Machinery, Equipment, and Systems, Requirements for (17 Mar 1989)
2.1.2 MIL-S-901C, Shock Tests, H.I. (High Impact) Shipboard Machinery, Equipment, and Systems, Requirements for (5 Sept 1963)
1.2 MIL-STD-167-1A, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II – Internally Excited) (02 November 2005)
1.3 MIL-STD-461F, Requirements for the Control of Electromagnetic Interference Characteristics of Subsystems and Equipment (10 Dec 2007)
1.4 MIL-STD-461H, Requirements for the Control of Electromagnetic Interference Characteristics of Subsystems and Equipment (17 APR 2026)
1.5 ISO/IEC 17025:2017, General Requirements for the Competence of Testing and Calibration Laboratories
1.6 ANSI/ASQ/ISO 9001:2015: Quality Management Systems - Requirements
Documents in 2.1 thru 2.11 can be found on the following site: https://quicksearch.dla.mil/qsSearch.aspx.
3.0 REQUIREMENTS
The contractor shall develop test plans and procedures, fabricate standard and non-standard test fixtures, set up and conduct environmental qualification tests; acquire and analyze data from test events; and write and provide final test reports following the test event for each test completed.
3.1 EQT Coordinator Responsibilities
3.1.1 The contractor shall provide technical status reports, travel reports for any trips conducted, a personnel roster, and a periodic Government Property Inventory Report on a monthly basis, in accordance with CDRLs A001, A002, A003, and A009 respectively. A Small Business Utilization Report and a Systems Security Plan shall also be delivered in accordance with CDRLs A014 and A015.
3.1.2 Near the conclusion of every Task Order, the contractor shall provide a final Government Property Inventory Report in accordance with CDRL A010.
3.1.3 The contractor shall design and execute tests in strict compliance with MIL-DTL-901E, MIL-STD-167-1A, MIL-STD-461F, MIL-STD-461G, and MIL-STD-461H.
3.1.4 The contractor shall outline specific test profiles, success/failure thresholds, and instrumentation setups prior to testing, in accordance with test planning and test procedure CDRLs.
3.1.5 The contract shall provide formal documentation of the testing results, containing raw sensor data, failure analysis (if applicable), and compliance matrices, in accordance with test reporting CDRLs.
3.1.6 The contractor shall review, design, or source custom shock/vibration/EMI/EMC fixtures.
3.1.7 The contractor shall ensure that any analytical test results and raw data used for calculations must be managed electronically, to ensure results can be independently reproduced or verified
3.2 EQT Test Plans and Test Procedures
3.2.1 The Contractor shall review Government-provided equipment performance specifications, Interface Control Documents (ICDs), drawings, operating manuals, and target military standards (e.g., MIL-DTL-901E, MIL-STD-167-1, MIL-STD-810H) to identify all required qualification parameters, tolerances, and acceptance criteria.
3.1 3.2
3.2.2 The Contractor shall develop an Environmental Qualification Test Plan and procedures for each test campaign in accordance with the applicable Contract Data Requirements List (CDRL) identifier listed in Section 4 of this SOW; either A004, A005, or A012. The plan and procedures shall detail:
3.2.2.1 Identification and operational configuration of the Equipment Under Test (EUT).
3.2.2.2 Applicable test series, profiles, sequences, levels, durations, and tolerances (e.g., shock grade/classification, vibration frequency sweeps and dwell points, thermal cycle extremes, humidity schedules).
3.2.2.3 Required laboratory facilities, test machines or vehicles, environmental chambers, shakers, or drop machines.
3.2.2.4 Instrumentation and sensor allocation matrix (accelerometers, strain gauges, thermocouples, load cells, pressure transducers, voltage/current probes).
3.2.2.5 Definition of operational monitoring during test events (functional checks, continuous operational parameter logging).
3.2.2.6 Formal pass/fail criteria, including physical structural integrity, electrical operational parameters, and post-test operational capability.
3.2.2.7 Pre-test inspection, calibration verification, and baseline functional checkout.
3.2.2.8 Rigging, mounting, bolt torque specifications, and electrical/fluid interconnect installation.
3.2.2.9 Exact test apparatus operating instructions and environmental run sequences.
3.2.2.10 Real-time data logging requirements and data sheet check-off tables.
3.2.2.11 Pre-defined abort criteria, safety precautions, emergency shutdown protocols, and test anomaly response steps.
3.2.3 The Contractor shall submit all Test Plans and Procedures to the NSWCPD Technical Point of Contact (TPOC) and COR for review and formal Government approval prior to commencing fixture fabrication or executing test events.
3.3 Design and Fabrication of Standard and Non-Standard Test Fixtures
3.3.1 The Contractor shall use standard structural test fixtures or design non-standard structural test fixtures, mounting adapter plates, and transit frames necessary to dynamically and mechanically interface EUTs with specified test machines (e.g., lightweight or medium weight shock machines; heavyweight shock test vehicle; electrodynamic/hydraulic vibration tables; centrifuge arms; environmental chamber carts). The Contractor shall utilize Computer Aided Design (CAD) programs and drawing control, Finite Element (FE) modeling programs to provide static strength, dynamic strength and structural modal analyses IAW Navy Dynamic Design Analysis Method (DDAM).
3.3.2 The Contractor shall perform structural dynamic and Finite Element Analysis (FEA) on fixture designs to verify that:
3.3.2.1 Fixture natural resonant frequencies fall outside the specified test frequency bandwidth, avoiding fixture-induced resonances during vibration testing, or match specified shipboard stiffness characteristics as required by MIL-DTL-901 / MIL-STD-167.
3.3.2.2 Fixtures withstand peak dynamic loads, shock accelerations, and thermal stress without plastic deformation, weld failure, or structural yielding.
3.3.3 The Contractor shall submit Fixture Design and Inspection Packages to NSWCPD, including 3D CAD models, 2D fabrication drawings, structural/FEA analysis reports, center-of-gravity calculations, and fastener torque ratings; in accordance with CDRL A006. The Contractor shall also provide shock analysis (CDRL A007) and dynamic analysis reports (CDRL A008).
3.3.4 Upon Government approval of the fixture design package, the Contractor shall fabricate, machine, weld, assemble, and inspect standard and non-standard fixtures. All welding shall be performed by certified welders in compliance with applicable military and industry standards.
3.3.5 The Contractor shall perform dimensional verification and non-destructive examination (NDE) of fabricated fixtures, certify interface tolerances, and provide objective quality evidence (OQE) and material test reports (MTRs) for raw materials and structural hardware.
3.3.6 The Contractor shall deliver the design of the fixtures in accordance with conceptual drawings (CDRL A006), and shall also deliver final CAD drawings of fixtures in accordance with CAD drawings (CDRL A006). Additionally, the contractor shall perform fabrication of test fixtures, including but not limited to metal cutting, forming, welding, lifting and shall assemble equipment to produce, at a minimum, all LWSM, MWSM and HW test fixtures, as detailed in applicable documents in SOW Section 2.0.
3.3.7 Specific shock tests that are expected to require fixturing are:
3.3.7.1 All tests on LWSM and MWSM shall be standard or non-standard
3.3.8 All tests on DSSM and heavyweight barge shall be non-standard.
Fixtures shall be either of a non-standard, or novel, type developed by NSWCPD or by the contractor; or shall be of standard type. Standard and non-standard fixtures for shock testing are as defined by MIL-DTL-901E. For vibration and EMI or EMC EQT, all fixtures will be considered non-standard. The test fixtures shall be provided to the test site location as identified in the applicable Task Order.
3.4 Test Setup, Instrumentation, and Execution
3.4.1 The Contractor shall coordinate test schedules, facility access, and facility preparations with the designated Government or commercial test facility.
3.4.2 The Contractor shall transport, handle, uncrate, and inspect EUTs and test fixtures in accordance with applicable handling procedures to prevent pre-test damage.
3.4.3 The Contractor shall rig, align, and mechanically mount fixtures and EUTs to the test equipment utilizing calibrated torque wrenches, certified rigging gear, and specified Grade 5/Grade 8 or Mil-Spec fasteners.
3.4.4 The Contractor shall install, wire, and calibrate all instrumentation, sensors, and data cabling. Sensor placement shall strictly align with the approved Test Plan and Procedure. The Contractor shall ensure that all transducers and measurement equipment hold active, NIST-traceable calibration certifications.
3.4.5 The Contractor shall establish and verify functional interfaces, including power, cooling water, pneumatic lines, and load banks required to energize and operate the EUT during testing.
3.4.6 The Contractor shall conduct or facilitate pre-test operational baselines to verify sensor channel functionality, signal-to-noise ratios, and baseline equipment performance.
3.4.7 The Contractor shall conduct environmental qualification test events strictly adhering to the approved Test Procedures.
3.4.8 The Contractor shall immediately halt testing and notify the Government TPOC and COR upon the occurrence of any unexpected EUT operational failure, structural anomaly, test equipment abort, safety incident, or violation of test requirements described in applicable documents referenced in SOW Section 2.0.
3.4.9 Shock Testing – specific requirements
3.4.9.1 The Contractor shall perform shock EQT testing, including lightweight, medium weight, and heavy weight high-impact shock tests on various HM&E equipment under test (EUTs), for all equipment classes (Class I, Class II, and Class I/II) as defined by MIL-DTL-901E Section 1.2.4.
3.4.9.2 The Government will identify the specific shock test and related EUT at the Task Order level. All EUT shall be provided as Government Furnished Property (GFP) within 60 days of Task Order award. All testing shall be performed IAW Sections 1.2 and 3.1 of MIL-DTL-901E, or IAW Sections 1.2 and 3.1 of MIL-S-901D, or the applicable submarine-class specification. The Government will specify which specification should be followed in each Task Order issued.
3.4.9.2.1 Light Weight Shock Test: perform Grade A and Grade B lightweight shock testing on a Lightweight Shock Test Machine (LWSM).
3.4.9.2.2 Medium Weight Shock Test: perform Grade A and Grade B medium weight shock testing on a Medium Weight Shock Test Machine (MWSM).
3.4.9.2.3 Medium Weight Deck Simulating: perform Grade A and Grade B medium weight shock testing on a Deck Simulating Shock Machine (DSSM).
3.4.9.2.4 Heavy Weight Shock Test: perform Grade A and Grade B heavyweight shock testing on either a Floating Shock Platform (FSP), an extended Floating Shock Platform (EFSP), or an intermediate Floating Shock Platform (IFSP).
3.4.10 Vibration Testing – specific requirements
3.4.10.1 The Contractor shall perform Vibration Testing on an EUT weighing up to 100 lbs. Type I Environmental vibration testing on a small-scale test machine, IAW Section 5.1 of MIL-STD-167-1A.
3.4.10.2 The Contractor shall perform Vibration Testing on an EUT between 101 lbs. and 75,000 lbs. Type I Environmental vibration testing on a large-scale test machine (mechanical, electromagnetic, servo hydraulic or other type), IAW Section 5.1 of MIL-STD-167-1A.
3.4.11 EMI & EMC – specific requirements
3.4.11.1 The Contractor shall test to MIL-STD-461H (see SOW Section 2), Table IV Emission and susceptibility requirements, including: CE101, CE102, CE106, CS101, CS103, CS104, CS105, CS109, CS114, CS115, CS116, CS117, CS118, RE101, RE102, RE103, RS101, RS103, and RS105.
3.4.11.1.1 The Contractor shall perform tests identified in MIL-STD-461H on both large-scale and small-scale EUTs. A small-scale EUT is defined as any item no larger than a 24” by 24” by 12” footprint. A large-scale EUT is defined as any item that is larger than a 24” by 24” by 12” footprint but no larger than a 50’ by 50’ by 60’ footprint.
3.4.11.1.2 All testing shall be conducted IAW the procedures, equipment, and setup as specified in the applicable paragraph of MIL-STD-461H section 5.0.
3.4.11.2 The Contractor shall test to MIL-STD-461F (see SOW Section 2), Table IV Emission and susceptibility requirements, including: CE101, CE102, CE106, CS101, CS103, CS104, CS105, CS106, CS109, CS114, CS115, CS116, RE101, RE102, RE103, RS101, RS103, and RS105.
3.4.11.2.1 The Contractor shall perform tests identified in MIL-STD-461F on both large-scale and small-scale EUTs. A small-scale EUT and a large-scale EUT are defined as above in Section 3.1.1.1.
3.4.11.2.2 All testing shall be conducted IAW the procedures, equipment, and setup as specified in the applicable paragraph of MIL-STD-461F.
3.4.11.3 The Contractor shall test both small-scale and large-scale EUTs to above-deck levels (200 V/m), specifically to the MIL-STD-461H CS114 susceptibility requirement and the MIL-STD-461H RS103 susceptibility requirement. The contractor shall provide all data acquisition equipment and ancillary equipment that is needed to set up the test for above-deck levels which would not be needed for an EUT tested at below-deck levels.
3.5 Data Acquisition and Data Analysis
3.5.1 The Contractor shall operate automated, multichannel high-speed Data Acquisition (DAQ) systems to continuously capture dynamic, electrical, thermal, and mechanical sensor responses as required during each test run.
3.5.2 The Contractor shall record test parameters at sample rates sufficient to prevent aliasing and capture peak transient events (e.g., minimum 100 kHz sample rate per channel for shock events; appropriate filtering and sample rates for vibration and thermal logging).
3.5.3 The Contractor shall acquire, process, and analyze collected raw test data. Analysis tasks shall be dependent on the type of EQT conducted and may include:
3.5.3.1 Application of calibration offsets, gains, and unit conversions.
3.5.3.2 Time-domain processing (e.g. peak accelerations, velocities, displacements, rise times, pulse durations).
3.5.3.3 Frequency-domain analysis (Fast Fourier Transforms [FFT], Power Spectral Density [PSD], Shock Response Spectra [SRS], transmissibility plots, resonance identification).
3.5.3.4 Comparison of recorded test profiles against specification tolerance bands and baseline measurements.
3.5.4 The Contractor shall evaluate physical and functional data against the pass/fail criteria established in the test procedure to determine whether the EUT successfully met qualification requirements.
3.5.5 The Contractor shall provide test data electronically if requested by Code 333 or the Equipment Authority.
3.6 Post-Test Inspections and Final Test Reports
3.6.1 Following completion of each test event, the Contractor shall perform or facilitate a comprehensive post-test visual, mechanical, and electrical inspection of the EUT and fixture. This includes checking for physical distortion, fastener loosening, cracking, fluid leakage, insulation degradation, and electronic component displacement.
3.6.2 If requested by the Government, the Contractor shall support root-cause failure analysis (RCFA) for any failure or performance degradation observed during testing.
3.6.3 The Contractor shall write and provide a comprehensive Test Report for each completed test event, regardless of equipment performance (i.e. pass or fail), in accordance with the applicable CDRL in Section 4 of this SOW; either CDRL A011, A012, or A013. The Final Test Report shall include, but is not limited to:
3.6.3.1 Executive summary with unambiguous statement of qualification pass/fail status.
3.6.3.2 Identification of EUT serial numbers, part numbers, configuration, and fixture details.
3.6.3.3 Chronological narrative of test events, including environmental profiles applied, run logs, and environmental chamber charts.
3.6.3.4 Calibration data sheets showing model numbers, serial numbers, and NIST calibration expiration dates for all measurement equipment used.
3.6.3.5 High-resolution pre-test, during-test, and post-test photographs showing setup, sensor locations, and post-test condition.
3.6.3.6 Complete reduced and analyzed data plots (acceleration time histories, SRS curves, vibration transmissibility, thermal plots, electrical load logs).
3.6.3.7 Detailed documentation of any test anomalies, test halts, corrective actions taken, and engineering evaluations.
3.6.3.8 Conclusions and formal recommendations.
3.6.4 The Contractor shall submit draft test reports within fifteen (15) business days following completion of each test event and provide final reports within ten (10) business days following receipt of Government comments.
3.7 Emergent Testing Requirements
3.7.1 Shock Testing
3.7.1.1 The Contractor shall reference MIL-DTL-901E Section 3.1.11, which addresses resolution of shock test failures and retest requirements. The Contractor shall immediately halt testing and notify the Government TPOC and COR upon the occurrence of any unexpected EUT operational failure, structural anomaly, test equipment abort, safety incident, or violation of test requirements described in applicable documents referenced in SOW Section 2.0. The contractor shall make recommendations for any re-test event they deem necessary or beneficial, in its own experience or expertise, towards qualifying the EUT for its intended purpose.
3.7.2 Vibration Testing and EMI / EMC Testing
3.7.2.1 The Contractor shall immediately halt testing and notify the Government TPOC and COR upon the occurrence of any unexpected EUT operational failure, structural anomaly, test equipment abort, safety incident, or violation of test requirements described in applicable documents referenced in SOW Section 2.0. Government TPOC and COR will provide approval of any potential resolution of major EMI test failures or retest requests. The contractor shall make recommendations for any re-test event they deem necessary or beneficial, in its own experience or expertise, towards qualifying the EUT for its intended purpose.
3.8 Manufacturing Phase-Out or Discontinuation of Production, Diminishing Sources, and Obsolete Materials or Components
3.8.1 The contractor shall notify the contracting officer immediately upon determining the unavailability of obsolete materials or components. The contractor may recommend a solution to include the impact on the contract price and delivery. The contractor shall not initiate any item redesign or incur any additional costs without the express, written authorization of the contracting officer.
4 DATA REQUIREMENTS
4.1 CDRL A001: Contract Status Report (Monthly)
4.2 CDRL A002: Travel Report
4.3 CDRL A003: Contractor's Personnel Roster
4.4 CDRL A004: Electromagnetic Interference Test Procedures
4.5 CDRL A005: High-Impact Shock Test Procedures
4.6 CDRL A006: Test Fixture Design and Inspection Packages (Drawings, FEA, NDE)
4.7 CDRL A007: Shock Data Analysis
4.8 CDRL A008: Shock FEA Model Analysis
4.9 CDRL A009: Government Property Inventory Report (Periodic)
4.10 CDRL A010: Government Property Inventory Report (Final)
4.11 CDRL A011: Vibration Test Plan and Report
4.12 CDRL A012: Shock Test Report
4.13 CDRL A013: Electromagnetic Interference Test Report
4.14 CDRL A014: Small Business Utilization Report
4.15 CDRL A015: System Security Plan (SSP)
5.0 SECURITY REQUIREMENTS
5.1 SECURITY TRAINING. The Contractor is responsible for completing all required Government mandated training to maintain security and network access to government sites and IT systems to include but not limited to: Antiterrorism Level 1 Awareness; Records Management in the DON: Everyone's Responsibility; Training and Readiness: The Active Shooter; NAVSEA Introduction to Controlled Unclassified Information; Operations Security (OPSEC); NAVSEA Counterintelligence Training; Privacy and Personally Identifiable Information (PII) Awareness Training; NAVSEA Physical Security training and Cybersecurity 101 Training. Certificates of successful completion shall be sent to the COR and as otherwise specified in the contract.
5.1.1 In accordance with the National Industrial Security Program Operating Manual (NISPOM) (37 CFR Part 117), Contractor personnel that require access to Department of Navy (DON) information systems and/or work on-site require an open investigation or favorable adjudicated Tier 3 investigation. An interim clearance is granted by DCSA and recorded in the Defense Information System for Security (DISS). Must have a favorable fingerprint an open or closed investigation with a favorable adjudication in DISS is required prior to issuance of a badge providing access to NSWCPD buildings. Furthermore, if the Navy Central Adjudication Facility has made an unfavorable determination, access will be denied. For Common Access Card (CAC) you must have an open investigation and/or a favorably adjudicated investigation. Interim security clearance is acceptable for a CAC.
Access will be denied for anyone that has eligibility pending in DISS. Vetting through the National Crime Information Center, Sex Offender Registry, and the Terrorist screening database shall be process for a contractor that does not have a favorable adjudicated investigation.
5.1.2 Within 30 days after contract award, the contractor shall submit a list of all contractor personnel, including subcontractor employees, who will have access to DON information systems and/or work on-site at one of the NSWCPD sites to the appointed Contracting Officer Representative (COR) via email. The contractor shall provide each employee's first name, last name, contract number, the NSWCPD technical code, work location, whether or not the employee has a CAC and or Standard Access Control Badge (SACB), the systems the employee can access (i.e., NMCI, RDT&E), and the name of the Contractor's local point of contact, phone number and email address. Throughout the period of performance of the contract, the Contractor shall immediately provide any updated information to the COR when any Contractor personnel changes occur including substitutions or departures.
5.2 ON SITE WORK. Contractor personnel that require a badge to work on-site at one of the NSWCPD sites must provide an I-9 form to verify proof of citizenship. The I-9 form should be signed by the company Facility Security Officer or the company Human Resource Department. In addition to the I-9 form, Contractors shall also bring their birth certificate, current United States Passport or naturalization certificate and state issued REAL ID to the NSWCPD Security Officer at the time of badge request to verify citizenship. Any contractor that has unfavorable information that has not been favorably adjudicated, by Department of Defense Central Adjudication Facility (DOD CAF) will not be issued a badge. Finally, contractors shall supply a copy of their OPSEC Training Certificate or other proof that the training has been completed.
5.2.1 RESERVED
5.3 DD254 REQUIREMENT. This effort requires access to classified information up to the SECRET level. The Contractor is required to have and maintain a SECRET clearance. The requirements of the attached DD Form 254 apply.
5.3.1 The contractor is required to maintain a Facility Security Clearance (FCL) in accordance with the DD254 to perform certain work under the contract. The FCL shall be in place prior to base contract award. Otherwise, the government will have no obligation to continue ordering work under the contract and may not exercise any of the available options.
5.3.2 The Contractor shall appoint a Facility Security Officer (FSO), who shall (1) be responsible for all security aspects of the work performed under this contract, (2) assure compliance with the National Industrial Security Program Operating Manual (NISPOM) (32 CFR Part 117), and (3) assure compliance with any written instructions from the NSWCPD, Security Office Code 105.
5.3.3 Contractor must submit a flow down request for sharing of classified and other sensitive information between prime and subcontracts in writing to the COR and Security Contracting Officer (SCO), louise.r.brunson.civ@us.navy.mil. Each request must reference a contract number identifying the specific information for which approval is sought, a justification for needing to share the information, the contractor’s name and its contract number under which the requested information will be shared.
5.3.4 The contractor shall forward signed copies of DD254s provided to subcontractors to the Naval Surface Warfare Center Philadelphia Division (NSWCPD), ATTN: Security.
5.3.5 The contractor shall direct the subcontractor to obtain approval, through the prime Contractor, for the public release of information received or generated by the sub through the prime Contractor.
5.3.6 The contractor shall submit the subcontractor request for public release through the technical point of contact identified on the DD 254.
Additional information related to the facility clearance process can be obtained by visiting www.dss.mil or http://www.dss.mil/isec/pcl_index.htm.
5.4 OPERATIONS SECURITY (OPSEC)
5.4.1 The Contractor shall protect critical information associated with this contract to prevent unauthorized disclosure. The NSWC Philadelphia Division's (NSWCPD) Critical Information List (CIL)/ CIIL (Critical Indicators and information list) will be provided on site, if warranted. Performance under this contract requires the contractor to adhere to OPSEC requirements, which may include the NSWCPD Contractor OPSEC Plan. When the NSWCPD Contractor OPSEC Plan is required, the contractor shall return acknowledgment of the plan within 15 days of receipt. During the period of this contract, the Contractor may be exposed to, use, or produce, NSWCPD Critical Information (CI) and/or observables and indicators which may lead to discovery of CI. NSWCPD's CI will not be distributed to unauthorized third parties, including foreign governments, or companies under Foreign Ownership, Control, or Influence (FOCI) unless such FOCI has been appropriately mitigated through measures approved by the Defense Counterintelligence and Security Agency. Questions concerning these requirements shall be directed to the PCO.
5.4.2 CUI correspondence transmitted internally on the contractor's unclassified networks or information systems, and externally, shall be protected per NIST SP-800-171, Protecting Controlled Unclassified Information (CUI) in Non-federal Systems and Organizations.
Assembled large components/systems being transported to and from testing areas, other production or government facilities (whether or not on public roadways) shall be in an enclosed van trailer or covered flatbed trailer. Component/System outside storage, staging, and test areas shall be shielded/obscured from public view wherever physically possible.
5.4.3 NSWCPD's CI shall not be publicized in corporate wide newsletters, trade magazines, displays, intranet pages or public facing websites. Media requests related to this project shall be directed to the PCO, and the COR who will forward the required to the NSWCPD Public Release Authority for review.
5.4.4 Any attempt by unauthorized third parties to solicit, obtain, photograph, or record, or; incidents of loss/compromise of government Classified or CI, Business Sensitive, Company Proprietary information related to this or other program must be immediately reported to the contractor's Facility Security Officer and Cognizant Security Office and/or the Naval Criminal Investigative Service, and the NSWC PD Security Division (Code 105).
5.4.5 This SOW has been reviewed against the requirements of SECNAVINST 4200.35. SAIRC controls are not required
5.5 RECEIPT, STORAGE, AND GENERATION OF CONTROLLED UNCLASSIFIED INFORMATION (CUI) All Controlled Unclassified Information (CUI) associated with this contract must follow the minimum marking requirements of DoDI 5200.48, Section 3, paragraph 3.4.a, and include the acronym "CUI" in the banner and footer of the document. In accordance with DoDI 5200.48, CUI must be safeguarded to prevent Unauthorized Disclosure (UD). CUI export controlled technical information or other scientific, technical, and engineering information must be marked with an export control warning as directed in DoDI 5230.24, DoDD 5230.25, and Part 250 of Title 32, CFR. Nonfederal information systems storing and processing CUI shall be protected per NIST SP-800-171, or subsequent revisions. All transmissions to personal email accounts (AOL, Yahoo, Hotmail, Comcast, etc.) and posting on social media websites (Facebook, Instagram, Twitter, LinkedIn, etc.) are prohibited. Destroy CUI associated with this contract by any of the following approved methods: A cross-cut shredder listed on the “NSA/CSS Evaluated Products List for High Security Crosscut Paper shredders”; a certified commercial destruction vendor; a central destruction facility; incineration; chemical decomposition; pulverizing, disintegration; or methods approved for classified destruction.
5.6 PLANNING, PROGRAMMING, BUDGETING AND EXECUTION (PPBE) DATA.
When contractor employees, in the performance of their duties, are exposed to Planning, Programming, Budgeting and Execution (PPBE) data, a Non-Disclosure Agreement (NDA) with all affected contactor personnel must be executed in coordination with the COR and PCO to ensure safeguarding disclosure of this data.
5.7 U-NNPI SECURITY REQUIREMENTS
5.7.1 Security Classification Guidance is as follows of portions of the tasking on this contract when invoked in the task order statement of work:
5.7.1.1 Contractor requires access to information and equipment classified at the Confidential National Security Information (NSI) level in order to provide industrial support services within facilities that actively supports the Navy Nuclear Propulsion Program (NNPP).
5.7.1.2 All contractor personnel accessing classified information or classified material associated with the performance of work related to the resultant contract must be United States citizens, and shall have and maintain at a minimum Confidential security clearance.
5.7.1.3 The Contractor is responsible for completing all required government mandated training to maintain security and network access to government sites and IT systems, as necessary to support.
5.8 U-NNPI
5.8.1 Purpose The Contractor hereby agrees that when provided documents (specifications, drawings, etc.) that are marked as containing NOFORN sensitive information that must be controlled pursuant to Federal law, the information contained therein and generated as part of the inquiry shall be used only for the purpose stated in the contract and shall in no case be transmitted outside the company (unless such transmittals comply with the detailed guidance of the contract) or to any foreign national within the company. While in use, the documents shall be protected from unauthorized observation and shall be kept secure so as to preclude access by anyone not having a legitimate need to view them. The documents shall not be copied unless done in conformance with the detailed guidance of the contract. All the documents shall be promptly returned in their entirety, unless authorized for proper disposal or retention, following completion of the contract.
5.8.2 Specific Requirements for Protecting U-NNPI
a) Only U.S. citizens who have a need to know required to execute the contract shall be allowed access to U-NNPI.
b) When not in direct control of an authorized individual, U-NNPI must be secured in a locked container (e.g., file cabinet, desk, safe). Access to the container must be such that only authorized persons can access it, and compromise of the container would be obvious at sight. Containers should have no labels that indicate the contents. If removed from the site, U-NNPI must remain in the personal possession of the individual. At no time should U-NNPI be left unsecured (e.g., in a home or automobile, or unattended in a motel room or sent with baggage).
c) U-NNPI documents will have the word NOFORN at the top and bottom of each page. The cover sheet will have the warning statement shown below. Documents originated in the course of work that reproduce, expand or modify marked information shall be marked and controlled in the same way as the original. Media such as video tapes, disks, etc., must be marked and controlled similar to the markings on the original information.
d) U-NNPI may not be processed on networked computers with outside access unless approved by CNO (N00N). If desired, the company may submit a proposal for processing NNPI on company computer systems. Personally owned computing systems, such as personal computers, laptops, personal digital assistants, and other portable electronic devices are not authorized for processing NNPI. Exceptions require the specific approval of the cognizant DAA and CNO (N00N).
e) U-NNPI may be faxed within the continental United States and Hawaii provided there is an authorized individual waiting to receive the document and properly control it. U-NNPI may not be faxed to facilities outside the continental United States, including military installations, unless encrypted by means approved by CNO (N00N).
f) U-NNPI may be sent within the continental United States and Hawaii via first class mail in a single opaque envelope that has no markings indicating the nature of the contents.
g) Documents containing U-NNPI shall be disposed of as classified material.
h) Report any attempts to elicit U-NNPI by unauthorized persons to the appropriate security personnel.
i) Report any compromises of U-NNPI to the appropriate security personnel. This includes intentional or unintentional public release via such methods as theft, improper disposal (e.g., material not shredded, disks lost), placement on Web site, transmission via email, or violation of the information system containing U-NNPI.
j) The only approved storage for U-NNPI is CDMS NOFORN.
6.0 PLACE OF PERFORMANCE
6.1 The contractor's primary place of performance shall be at contractor facilities. It is estimated that 95% of the work will occur at the contractor’s facility(ies).
7.0 TRAVEL
7.1 The Contractor may be required to travel from the primary performance location when supporting this requirement. The contractor shall be required to travel CONUS (any state in USA) to accomplish the tasks contained in this contract. Travel in support of this requirement is anticipated to include, but may not be limited to, the following alternate performance locations on an annual basis:
| CONUS/OCONUS |
| ORIGIN: |
| DESTINATION: |
| Number of Days Per Trip |
| Number of Trips |
| Number of People |
| CONUS |
| Contractor location |
| Philadelphia, PA |
| 3 |
| 4 |
| 2 |
| CONUS |
| Contractor location |
| Washinton, DC |
| 3 |
| 2 |
| 2 |
8.0 GOVERNMENT FURNISHED PROPERTY
Government-Furnished Property (GFP) means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes Contractor-Acquired Property (CAP).
All Government Property is property of the U.S. Government and shall not be transferred to any individual or agency, public or private, without the express written approval of the originating Contracting Officer. Accountability for Government Property under this contract/order shall be managed in accordance with FAR Part 45, DFARS Part 245, and the Government Property clauses included within the Solicitation and Contract.
GFP is required for completion of task(s) under this SOW. See GFP attachment for detailed information. All GFP will be identified at the Task Order level during contract performance.
The Contractor shall notify the COR via email, with the TPOC and PCO Cc’d, within seven (7) business days of physical receipt of any GFP received in error or not on an approved GFP Attachment.
8.1 Reporting Requirements.
The Contractor shall follow all reporting requirements to accurately account for GFP.
8.1.1 PIEE Shipment Reporting.
Contractor Receipt Reporting: Clause 252.245-7005 “Management and Reporting of Government Property” requires the Contractor to report receipt of all GFP using the PIEE GFP Module, regardless of whether the Government has submitted a PIEE electronic shipment.
Contractor Shipment Reporting: Clause 52.245-1 “Government Property” (including Alternates 1 & 2) requires the Contractor to report to the Government when GFP is returned. Clause 252.245-7005 requires this notification to be an electronic shipment through the PIEE GFP Module.
A DD Form 1149 shall accompany all government property shipped between the Government and the Contractor using a third party, such as UPS, FedEx, or USPS. The DD 1149 does not take the place of the PIEE shipment. It is a requirement in addition to the PIEE shipment
8.1.2 Inventory Reporting
The Contractor shall submit a Government Property Inventory Report (Periodic) in accordance with CDRL A002. The CDRL identifies all reporting requirements. The Contractor shall continue to submit an inventory report IAW the CDRL even if all GFP has been returned to the Government. The Contractor shall also submit a Government Property Inventory Report (Final) in accordance with CDRL A003. When the Contractor has never received any GFP, the Contractor shall annually certify to the Procuring Contracting Officer (PCO) via email, with the Contracting Officer’s Representative (COR) and Technical Point of Contact (TPOC) Cc’d, that it does not have any GFP.
The Contractor shall also provide support within a reasonable timeframe after any Government request (to include by DoD support agencies such as DCMA) to support any Government audit in which GFP, or its related documentation, is requested as part of normal audit processes.
8.1.3 Lost, Damaged or Stolen GFP Reporting.
Clause 52.245-1 (including Alternates 1& 2) requires the Contractor to investigate and report to the Government (to the COR via email, with the TPOC and PCO Cc’d) all incidents of lost or damaged Government property as soon as the discovery is made. Clause 252.245-7005 requires the Contractor to report loss of Government property by using the Property Loss functionality within the PIEE GFP Module. The Contractor shall support the Government’s process to assign liability and document the loss in support of lost, damaged or stolen GFP.
8.1.4 Excess Property Reporting.
In accordance with Clause 52.245-1 paragraph (f)(viii)(A), the Contractor shall promptly disclose to the COR via email, with the TPOC and PCO Cc’d, Government property in its possession that is excess to contract performance. This reporting requirement also applies to excessive CAP, which must also be disclosed as soon as the material is identified as excessive.
8.2 Loss of Government Property.
Lost, Damaged or Stolen GFP shall be processed in accordance with the processes in Clause 52.245-1.
8.3 Property Management and Use.
The Contractor shall perform property management in accordance with Clause 52.245-1.
8.4 Subcontractor Requirements.
In accordance with Clause 52.245-1, the Contractor shall award subcontracts that clearly identify Government property that will be provided and the extent of any restrictions or limitations on their use. The Contractor shall also ensure appropriate flow down of contract terms, conditions and all relevant contractual information to all subcontractors who will use GFP. This includes dissemination of all information necessary for the subcontractor to properly track GFP in their property management system, such as the contract/order number, the serial management requirements and unit acquisition cost(s). It is the Contractor’s responsibility to assure that subcontracts are properly administered and periodically reviewed for compliance.
8.5 Contractor Acquired Property (CAP).
All CAP is titled to the Government and shall be treated to the same standard as GFP. CAP may be bought back by the Contractor in accordance with Clause 52.245-1. All CAP not bought back by the Contractor shall be processed following PCO or Property Administrator (PA) (if assigned) instructions in the PIEE GFP Module.
8.6 Property Disposition.
All GFP shall be dispositioned to the Government as soon as it becomes excessive to contract performance unless otherwise directed in writing by the PCO or Property Administrator. GFP may be dispositioned by being returned to the Government, or having custodianship transferred to another contract. Regardless of the method, all Government Property shall be processed by the end of contract PoP. The specific method of dispositioning will be specified by the Government within each individual Task Order SOW that requires GFP.
Disposition shall be processed as instructed by the PCO, COR (if delegated), PA (if assigned), and Plant Clearance Officer (PLCO) (if assigned) following the guidance provided in accordance with Clause 52.245-1 paragraph (j) (including Alternates 1 & 2) and Clause 252.245-7005.
8.6.1 Property Disposition Instructions.
Unless noted otherwise in a Task Order SOW, all GFP shall be returned to the Government in accordance with Clause 52.245-1, Clause 252.245-7005, as well as PCO instructions, and contract mod directions.
All GFP shall be returned to the following address:
NWSC Philadelphia Division 1601 Langley Ave, Building 542, POC: Dan Provenzano, Code 333 Philadelphia, PA 19112
Transfer to Another Contract: If instructed by the PCO, the Contractor shall transfer the property to another Government contract in accordance with Clause 252.245-7005. The Contractor shall coordinate the transfer with the gaining contractor and provide all necessary documentation.
8.7 Property Tagging.
The Contractor can either tag issued equipment or use the provided NSWCPD Plant property barcodes, or NMCI asset tags. If the contractor chooses to use their own tag, it shall not cover the NSWCPD barcode, or NMCI asset tag. The NSWCPD barcode, and/or NMCI asset tag number, when provided, shall be used on GFP inventory reports per DI-MGMT-80441D.
8.8 Property Closeout.
The Contractor shall aid the PCO and Property Administrator (if assigned) in contract closeout by promptly performing and reporting any issue that may prevent contract property closeout in accordance with Clause 52.245-1paragraph (f)(X) (including Alternates 1 & 2). This includes reporting, investigating and securing closure of all loss of Government property cases; physically inventorying all property upon termination or completion of this Contract/TO; and disposing of items at the time they are determined to be excess to contractual needs, per PCO/PA instructions.
8.9 Transportation of GFP
Per FAR 45.201, when Government property is offered for…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .