AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to:
1.Provide Questions and Answ ers.
2.The follow ing sections have been updated in the Statement of Work (SOW):
-Section 2.0 to include the Attachment (1)- Unit T-41 Pictures -Add Sections 3.1-“The Government requires a Trane certified personnel to perform the w ork herein. The contractor shall provide evidence of this w ith their proposal submission. Failure to provide this evidence may deem your proposal unacceptable”.
-Sections 3.2-3.9 have been updated accordingly.
3.Add Section J- Attachment (1) - Trane Unit T-41 Pictures.
4.Update CLIN 0001 to include Section 3.1 of the SOW.
5.Extend the closing date from 20 November 2019 to 29 November 2019.
6.No additional questions w ill be accepted.
7.All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 13
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Nov-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6449820Q5015
X 9B. DATED (SEE ITEM 11)
30-Oct-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Nov-2019
CODE
NAVAL SURFACE WARFARE CENTER PHILA
CODE 0223, KARETTE ARMSTRONG
KARETTE.ARMSTRONG@NAVY.MIL
5001 SOUTH BROAD STREET, BUILDING 4
PHILADELPHIA PA 19112
N64498 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6449820Q5015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 20-Nov-2019 05:00 PM to 29-Nov-2019 05:00 PM.
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description has changed from:
The Contractor is required to provide 25/50 Ton Climate Changer Replacement in accordance with section C Statement of Work.
Please Note:The Contractor shall complete the replacement of Trane Performance Climate Changer (CSAA) (Model # CSAA040UA). No deviations or substitute will be accepted.
To:
The Contractor is required to provide 25/50 Ton Climate Changer Replacement in accordance with section C Statement of Work.
Please Note:The Contractor shall complete the replacement of Trane Performance Climate Changer (CSAA) (Model # CSAA040UA). No deviations or substitute will be accepted.
Per Section 3.1 of the SOW: The Government requires a Trane certified personnel to perform the work herein. The contractor shall provide of this with their proposal submission. Failure to provide this evidence may deem your proposal unacceptable.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been added by full text:
QUESTIONS AND ANSWERS
1. The Scope of Work states to remove existing Trane Climate Changer, and replace with a New Unit (not part of a unit). Additionally, the Model # is provided; however, my local Trane Equipment sales person needs the Serial # from the Existing unit to properly Price the New Unit. Can you please clarify, the Scope of Work correctly, the Contract Specialist stated it is for a "Part Replacement", however the Contractor reads the scope as removing & replacing the
Unit No. T-41
Serial No. K5F292452 This requirement is for a remove and replace rather than a part replacement.
2. If site visit is unavailable, provide pictures of existing unit including - Serial # as the equipment salesperson requires this to properly price the new unit and insure it matches existing.
Pictures of the unit are attached herein as Attachment (1): Trane Unit T-41 Pictures.
3. Provide picture of existing site conditions, access for the removal & installation of unit.
Pictures of the site will also be included in Attachment (1): Trane Unit T-41 Pictures.
4. Is the unit on a housekeeping Pad? On Steel?
The unit is located at 1701 Kitty Hawk Avenue, Philadelphia, PA 19112 on the top of a concrete roof.
5. Is their external vibration Isolation required with new equipment? Or internal isolation on Fans?
Per the customer’s POC, this would be a good idea but he does not know if this would be required.
6. Is the electrical service disconnect box located next to the unit?
No, the electrical service disconnect box is located at 1701 Kitty Hawk Avenue, Philadelphia, PA 19112 on the first floor inside the pump room.
7. What control vendor is connected into the Unit / Building?
The control vendor is a relay with a start stop switch.
8. Provide picture of existing damper in the electrical room so it can be matched.
Pictures of the unit will be provided and called Attachment (1) Trane Unit T-41 Pictures.
9. Is there a requirement for Pre & Final Balancing reading?
No
10. Is there a requirement for the new unit to have a factory test and Owner witness?
In the RFQ under Section-E provides information on the Inspection and Acceptance terms of this requirement.
11. Does the unit have Electric Heat or Hot Water Coil & Piping including Size?
12. Does the unit have chilled water coil/Piping including size or a DX coil?
13. Does the existing unit have a humidification unit?
14. Is their Insulation on the Existing Ductwork? Supply and return duct flex transition pieces, are these to be insulated?
15. Overhead crane is to be provided to assist in removal & installation of unit, please provide pictures on the access/loading dock area into the building to the overhead crane.
The unit is accessible via a provided overhead crane. Please see the pictures of the unit in Attachment (1):
Trane Unit T-41 Pictures.
16. Under Requirements Section 3.1: “the contractor shall disconnect and safe power off the current equipment” - How far is the disconnect located from the equipment location, and are there any hard to reach places?
17. For Requirement Section 3.2: How old is the existing unit? Can you please provide the serial number, model number, and photos of existing conditions? *As per our Authorized Trane Distributor, the serial number of the existing unit will provide us the necessary information for the replacement unit.*
Unit No. T-41, Circa 1984 Serial No. K5F292452 This requirement is for a remove and replace rather than a part replacement.
18. Under the Requirement Sections, Sub-Sections 3.3 and 3.5 are not indicated in the SOW – Is this intentional?
These sections were not indicated for additional changes to the requirements
19. As per our Authorized Trane Distributor: Can you kindly provide drawings so we can see what required sections will be needed?
Pictures of the site and performance climate changer are available not drawings
20. Under Requirements Section 3.4: “the replacement unit shall adhere to the same form, fit, and function as the prior equipment” – Can you kindly advise on the form, fit, and function of the existing equipment?
The Air handler will be servicing the capacitor room adjacent to induction furnaces. The replacement unit must be capable of providing form, fit, and function. We anticipated the new unit being dropped in, wired up and begin running.
21. Can you kindly advise on the sizes and specifications for the transition pieces and flex connectors required to tie into the existing ductwork (photos will be helpful), and how many such connections will be required?
Transition – Flex off of the air handler was 48” x 48” transitioned to ducting 60” x 36”.
22. Under Requirement Section 3.7: Please advise on the size of the wall damper required, and is this through a fire rated wall?
No fire rated wall and the size is approximately 48” x 20”.
23. Kindly advise on the specifications of the wiring required to reconnect the new unit to the existing power supply. Can you also advise on the location and specification of the existing power supply panel and how far is it from the equipment location (photos will be helpful)?
From the disconnect located on lower level to air handler on room roof, the conduit run is approximately 60’. 240- 3 phase power. New install will require disconnect within sight of air handler equipment for lock out purposes.
24. Under Requirement Section 3.10: Is the overhead crane already existing in the NFPC warehouse? If so, where are we supplying the new equipment to (location on site), and where are we picking up the old equipment from? Is this overhead crane already existing inside and enclosed warehouse, or will this equipment be installed elsewhere? Can you please provide this information with photographs?
Naval Foundry and Propeller Center (NFPC) has an existing bridge crane located within the warehouse. New equipment shall be trucked into facility footprint following security vetting to either roll up door on south side of designated building. New equipment requires offloading via facility provided fork truck or picked with overhead bridge crane. The old equipment will be disconnected and removed from atop interior room roof and set outside building to designated area via facility fork truck. Facility is responsible for cataloging and discarding old equipment unit. I will get the remaining information to you as soon as possible.
25. Are there any other Technical or Pricing Proposal Specific Requirements in addition to what can be found in Sections L-212-W001 and L-212-W002 of the SOW?
The Government requires Trane certified personnel to perform the work. The contractor shall provide evidence of this with their proposal submission. Failure to provide this evidence may deem your proposal technically unacceptable, sections L&M have been updated accordingly.
The following have been modified:
STATEMENT OF WORK
Statement of Work (SOW) for 25/50 Ton Climate Changer Replacement
Naval Foundry and Propeller Center (NFPC)
1.0 INTRODUCTION
1.0.1 The Naval Surface Warfare Center Philadelphia Division (NSWCPD) is a Department of Defense entity responsible for research and development, test and evaluation, engineering and fleet support organization for the Navy’s ships, submarines, military watercraft and unmanned vehicles. This requirement is for Naval Foundry and Propeller Center (NFPC) who is responsible for the design, manufacture, and repair propellers for the US Navy.
1.0.2 This contract is for non-personal services. It does not create employment rights with the U.S. Government whether actual, inherent, or implied.
1.0.3 Government / Contractor Relationship
(a) The services to be delivered under this Contract are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the Contract between the Government and the Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.
(b) The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence
(c) Contractor personnel under this Contract shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.
(d) Employee Relationship:
1) The services to be performed under this Contract do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.
2) Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation.
This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.
(e) Inapplicability of Employee Benefits: This Contract does not create an employer-employee relationship. Accordingly, entitlements and benefits applicable to such relationships do not apply.
(f) Notice. It is the Contractor's, as well as the Government's, responsibility to monitor Contract activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.
1) The Contractor should notify the Contracting Officer in writing within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the estimate in time by which the Government must respond to this notice to minimize cost, delay, or disruption of performance.
2) The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:
(i) Confirm the conduct is in violation and when necessary direct the mode of further performance,
(ii) Countermand any communication regarded as a violation,
(iii) Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or
(iv) In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.
1.1 BACKGROUND
NFPC currently owns a 25/50 Ton Furnace. NFPC requires this furnace to be fully functional.
The capacitor room associated with these furnaces is in need of a Trane Performance Climate Changer replacement.
1.2 SCOPE OF WORK
The Contractor shall complete the replacement of Trane Performance Climate Changer (CSAA) (Unit Number T-4) (Serial Number K5F292452) (Model # CSAA040UA). No deviations or substitute will be accepted. NFPC requires an authorized Trane distributor to complete this work.
The contractor shall adhere to all the requirements listed in section 3.0.
2.0 APPLICABLE DOCUMENTS
Attachment (1) - Trane Unit T-41 Pictures
3.0. REQUIREMENTS
3.1. The Government requires Trane certified personnel to perform the work. The contractor shall provide evidence of this with their proposal submission. Failure to provide this evidence may deem your proposal technically unacceptable.
3.2. The contractor shall disconnect and safe power off the current equipment.
3.3. The contractor shall demo existing unit and dispose offsite in an Environmental Protection Agency (EPA) approved matter.
3.4. The contractor shall provide, deliver, and install replacement unit. The replacement unit shall adhere to the same form, fit, and function as the prior equipment.
3.5. The contractor shall tie the unit into existing ductwork with new flex connectors and transition pieces.
3.6. The contractor shall replace wall dampers in the electrical room located below the unit.
3.7. The contractor shall reconnect the unit to the existing power supply.
3.8. The contractor shall startup the unit and test for proper operation. Any failures in the test shall be remedied at no additional cost to the Government.
3.9. NFPC shall be responsible in providing an overhead crane to assist the contractor in the replace and installation of the new unit.
4.0 DATA REQUIREMENTS
N/A
5.0 Security
5.1 The contractor shall be escorted onto the site, observed while they perform the work, and escorted off the site.
5.2 Escorted visit. Escorted visits are required for any person who is not assigned to NNSY/NFPC and/or does not have a valid security clearance. Visitors will be escorted at all time by an NFPC employee and no exposure to any classified open storage areas or material. Requests for escorted access must be submitted 5 working days prior to arrival. If it is service or maintenance that needs to be done or an emergency the request needs to be submitted immediately in order to allow for ample time for proper vetting of individual/individuals requesting access.
The requesting NFPC code/shop will coordinate the visit and verify two forms of government issued identification. The responsible code shall provide escort during the contractor’s visit.
Acceptable documents include:
1. US Birth Certificate (original)
2. US Voters registration
3. US Passport
4. (Home Land security), Transportation Workers Identification Credential (TWIC)
5. Naturalization paperwork
6. Drivers License
7. Social Security Card
Installation Access for Visitors/Contractors
All visitors/contractors having a valid purpose for access shall submit a completed and signed Form 5512/1 to their identified Government sponsor 14 working days prior to the date of their required visit.
The entire document shall be completed and form dated/signed by the visitor/contractor.
Visitor/Contractor shall retain a copy of the form 5512/1 to present on the first day at the installation.
Note: It is critical that start/end dates/work hours are identified, accurate, and short term visitors/contractors are not granted extended or after-hours access if not required Reporting to PNY-A for the first time
Visitor/Contractor Responsibility
Visitor shall report to the location designated by their sponsor (Security Office or other designated location, Pass and ID office) or if operating a Commercial Vehicle requiring inspection; to the Vehicle Inspection Station.
Visitor/Contractor shall present their completed and signed by 5512/1.
The Sentry or Security Assistant shall verify vetting is cleared and issue the appropriate passes. If visitor/contractor has not completed the 5512/1 their access will be delayed until they correct the form.
Code 1122 will review request and when acceptable notify requesting NFPC code/shop to arrange visit.
5.3 Contractor Vehicle Parking: (OPNAV 5530.14E) All contractor commercial vehicles must be visually inspected at “S” Lot prior to entry into any NFPC buildings and are subject to random inspections anywhere on the compound. Vehicles must clearly display an authorized company sign or logo including a company phone number. Vehicles must only be allowed in the compound for transportation of contractors' tools, parts, and materials to and from the work site with the exception of MILCON scope projects. Vehicles must be registered to the company and not to an individual. Parking of POV's is available at “S” lot, which is approximately one mile from the work site. Contractor shall ensure that their vehicles, including delivery trucks, have valid and current vehicle registration and insurance upon arrival to NFPC. Non-valid and outdated or missing vehicle registration and insurance shall result in denied facility access requiring the Contractor to reschedule delivery immediately at the contractor’s expense. Delivery drivers must present two forms of government issued identification.
5.4 Camera cell phones are not allowed in areas where NAVSEA work is being performed.
However, contractors are allowed to use camera devices to take pictures of the OEM drawings.
This action will be supervised by the NFPC escorts.
Camera cell phones are PROHIBITED:
In the CAA (Controlled Access Area), In Restricted Areas (Open Storage Confidential Areas, Secure Rooms, Vaults, etc.) and any location (office, trailer, shop, work area, etc.) where NAVSEA business is conducted.
Cell phones with the camera features disabled are no longer considered to be “camera” cell phones, and none of the restrictions for camera cell phones apply.
- “Disabled” means physical removal/destruction of the lens (drilling out, for instance) and filling the void with a permanent epoxy.
o The “acceptance criteria” is that it must be visually obvious to untrained personnel that the camera feature has been disabled. Accordingly, claiming that the camera feature or function has been “deprogrammed”, “inactivated” (or similar) would NOT be acceptable, since this cannot be readily verified by untrained personnel. Also, the camera feature or function could be reprogrammed or re-activated after inspection.
Cell phone owners should consider locations into which they intend/desire to carry cellphones before permanently modifying them. Modifications to cell phones are solely the decision and the responsibility of the owner.
Personnel camera cell phones are permitted in Personally Owned Vehicles parked outside of the Controlled Access Area. (General parking lots across the street)
Personal camera cell phones are permitted in areas outside of the CAA and where Naval Sea Systems Command (NAVSEA) business of a sensitive nature is NOT conducted.
This means that camera cell phones are PROHIBITED in Secure Rooms (regardless of where any of these areas are located), and in any meeting, discussion or forum where NAVSEA business of a sensitive nature is carried on.
Cellphone lockers/boxes will be placed at the entrance to facilities, or as close to the entrance as possible in order to facilitate this policy.
********CAA-Controlled Access Area is anywhere within the fence line********
5.5. The contractor shall adhere to the facility/base access guidance per the following website:
https://www.cnic.navy.mil/regions/cnrma/om/contractor_verification_system/faqs.html
5.6. The contractor shall ensure that only contractor employees who meet the security requirements stated below perform under this contract at the Government site (e.g. delivery drivers and passengers, etc.). The contractor shall propose and maintain a list of employees whom meet these requirements and be willing to submit this list to the Government, along with the necessary documentation to prove they meet them (e.g. the results of a contractor conducted background check, etc.), for the Government’s security vetting, to include any Government background check, and approval. Once vetted and approved, a list of approved contractor employees must be maintained for the entire period of performance of the contract (i.e. propose new employees, replace existing employees or provide updates to existing employees’ records, as necessary). A minimum of two employees, primary and backup, should be cleared by the Government to perform the necessary functions under this contract (e.g. proposed drivers of a delivery vehicle) throughout the entire period of performance of the contract. Contractors must have the ability to be granted access by ensuring current documentation is available at the submission of their proposal to allow background checks for any proposed driver and passenger under the following criteria:
Felony conviction of any type within 10 years, or felony arrest that has not been adjudicated yet (includes "deferred findings").
Misdemeanor conviction or on-base arrest within 5 years, for any of the following types of crimes (includes "deferred findings"): Crimes of violence, sexual assault, larceny, drugs, or a habitual offender.
On the Sex Offender Registry.
Is barred from any Navy installation.
If a contractor’s employee is denied entry at delivery due to inaccurate or outdated personal and/or vehicle documentation, the Government is absolved of any costs accrued as a result of the denial and the contractor is still pledged to fulfill the contract requirements. Failure to fulfill the contract requirement may result in a termination for default pursuant to FAR 49.4.
6.0 PLACE OF PERFORMANCE
6.1.1. Performance will occur at the following
Naval Foundry and Propeller Center Building 20 Philadelphia, PA
The contractor shall perform the work within four (4) months after receipt of contract award...
The Government point of contact is upon arrival to the site is:
Brian Dougherty 215-620-2990
6.1.2 Access to Government buildings at NFPC is from 0730 to 1800 Monday through Friday, except Federal holidays. Normal work hours are from 0730 to 1800, Monday through Friday.
Contractor employees shall be under Government oversight at all times. Government oversight requires that a Government employee be present in the same building/facility whenever Contractor employee(s) are performing work under the subsequent contract. Contractor personnel are not allowed to access any Government buildings at NFPC outside the hours of 0730 to 1800 without the express approval of the Procuring Contracting Officer (PCO).
6.1.3 Early Dismissal and Closure of Government Facilities
When a Government facility is closed and/or early dismissal of Federal employees is directed due to severe weather, security threat, or a facility related problem that prevents personnel from working, onsite Contractor personnel regularly assigned to work at that facility should follow the same reporting and/or departure directions given to Government personnel. The Contractor shall not direct charge to the contract for time off, but shall follow its own company policies regarding leave. Non-essential Contractor personnel, who are not required to remain at or report to the facility, shall follow their parent company policy regarding whether they should go/stay home or report to another company facility. Subsequent to an early dismissal and during periods of inclement weather, onsite Contractors should monitor radio and television announcements before departing for work to determine if the facility is closed or operating on a delayed arrival basis.
When Federal employees are excused from work due to a holiday or a special event (that is unrelated to severe weather, a security threat, or a facility related problem), on site Contractors will continue working established work hours or take leave in accordance with parent company policy. Those Contractors who take leave shall not direct charge the non-working hours to the contract. Contractors are responsible for predetermining and disclosing their charging practices for early dismissal, delayed openings, and closings in accordance with the FAR, applicable cost accounting standards, and company policy. Contractors shall follow their disclosed charging practices during the contract period of performance, and shall not follow any verbal directions to the contrary. The PCO will make the determination of cost allowability for time lost due to facility closure in accordance with FAR, applicable Cost Accounting Standards, and the Contractor's established accounting policy.
7.0 TRAVEL
Not applicable.
8.0 GOVERNMENT FURNISHED PROPERTY
9.0 GOVERNMENT FURNISHED INFORMATION
Not applicable.
10.0 PURCHASES
Not applicable.
11.0 COUNTERFEIT MATERIAL PREVENTION
Not applicable.
12.0 PERSONNEL
Not applicable.
13.0 NSWCPD ELECTRONIC COST REPORTING AND FINANCIAL TRACKING
(ECRAFT) SYSTEM
14.0 SPECIAL REQUIREMENTS
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been added by full text:
Attachment (1) - Trane Unit T-41 Pictures - This attachment will be referenced in Section 2.0 of the Statement of Work (SOW).
SECTION M - EVALUATION FACTORS FOR AWARD
The following have been modified:
EVALUATION
(a) The Government requires Trane certified personnel to perform the work herein. The contractor shall provide evidence of this with their proposal submission. Failure to provide this evidence may deem your proposal unacceptable.
(b) The Government will award a contract resulting from this solicitation to the responsible contractor whose quote, conforming to the solicitation, is the lowest total price.
(End of provision)
(End of Summary of Changes)