Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lite |
CVN 74 FORWARD O2N2 REPAIR
FFP
CVN 74 FWD O2N2 PRODUCER OVERHAUL See Section C Statement of Work NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
VENDOR PART NR: 100001528235-0040
PURCHASE REQUEST NUMBER: 1300848357
PSC CD: J043
NET AMT
CLAUSES INCORPORATED BY FULL TEXT
B-231-H002 WORKSITE TRAVEL COSTS (NAVSEA) (OCT 2018)
(a) The contractor shall not charge, and the Government shall not pay, as an allowable cost under this contract, any manhour costs (whether straight-time or overtime) for contractor personnel or subcontractor personnel traveling to or from worksites, including travel to worksites other than the contractor's facility for performance of contract work.
(b) Workers being paid under this contract, as prime contractor personnel or subcontractor personnel, will complete a full shift at the worksite, and no compensation will be paid for travel time before or after the shift.
(c) This requirement pertains only to payments for travel time before or after these workers' regular shifts (commuting costs), and does not apply to legitimate travel costs incurred during normal working hours, provided that those costs are otherwise reasonable, allocable and allowable and approved in writing by the Government. This requirement does not apply to manufacturer's representatives or Original Equipment Manufacturer (OEM) representatives when specifically required by the Government work specifications.
(d) Additionally, the contractor shall not charge, and the Government shall not pay, any transportation costs under this contract associated with transporting contractor or subcontractor personnel between the contractor's facility (or subcontractor's facility), and any other worksite to perform ship repair, maintenance or modernization. Transportation costs include, but are not limited to, bus fare, car fare, train fare, or boat fare, paid by the work force, or paid by the contractor on behalf of the work force.
(End of text)
Section C - Descriptions and Specifications
STATEMENT OF WORK
STATEMENT OF WORK
A. TITLE
Perform repairs on the FWD O2N2 producer and associated Cryogenic Storage Tanks on board CVN-74 USS JOHN C STENNIS.
1.0 INTRODUCTION
1.0.1 The Naval Surface Warfare Center Philadelphia Division (NSWCPD) is a Department of Defense entity responsible for research and development, test and evaluation, engineering and fleet support organization for the Navy’s ships, submarines, military watercraft and unmanned vehicles.
This requirement is for NSWCPD Code 41, which is responsible for in-service engineering support, life cycle management, and testing and evaluation for main propulsion steam systems, secondary steam systems, and auxiliary machinery.
1.0.2 This contract is for non-personal services. It does not create employment rights with the U.S.
Government whether actual, inherent, or implied.
1.0.3 Government / Contractor Relationship
(a) The services to be delivered under this Contract are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the Contract between the Government and the Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.
(b) The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence
(c) Contractor personnel under this Contract shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.
(d) Employee Relationship:
1) The services to be performed under this Contract do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.
2) Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.
(e) Inapplicability of Employee Benefits: This Contract does not create an employer-employee relationship. Accordingly, entitlements and benefits applicable to such relationships do not apply.
(f) Notice. It is the Contractor's, as well as the Government's, responsibility to monitor Contract activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.
1) The Contractor should notify the Contracting Officer in writing within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the estimate in time by which the Government must respond to this notice to minimize cost, delay, or disruption of performance.
2) The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:
(i) Confirm the conduct is in violation and when necessary direct the mode of further performance,
(ii) Countermand any communication regarded as a violation,
(iii) Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or
(iv) In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.
1.1 BACKGROUND
CVN-74 USS JOHN C STENNIS is equipped with a GEECO Model J-95073 O2N2 producer that produces liquid oxygen and nitrogen and two Storage and Charging Units in the forward O2N2 space. The FWD O2N2 plant will to undergo a ‘Class B’ overhaul during CVN-74’s upcoming Refueling Complex Overhaul (RCOH) onboard. The RCOH availability begins with a Smart Start period in which the ship prepares systems and components for overhaul and long lead items can be removed to be repaired at off-site facilities.
1.2 SCOPE OF WORK
USS John C Stennis CVN-74 RCOH FWD GEECo Low Pressure Oxygen and Nitrogen Producer, RC-5D Tanks, and vacuum-jacketed transfer lines will undergo a mid-life extension program to improve its operation performance throughout the remaining life of the aircraft carrier, this task will be initiated during Smart Start. The FWD O2N2 System will have the panels, insulation, turbo-expander (TBX), ball valve, vane actuator, A23 valve, A41 valve and associated solenoids, cryo pumps and motors, and vacuum pumps and motors removed. The producer will be isolated with blank flanges and the internal piping inspected for additional leaks or damage. The relief valves, vaporizer elements, gauges and isolation valves will be inspected to determine if further repairs are required. The items removed during smart start will be sent to the OEM facility for overhaul and shipped in place.
2.0 APPLICABLE DOCUMENTS
2.1 S9553-CE-MMA-010 Oxygen-Nitrogen System Description, Operation and Maintenance (vol. 1)
2.2 S9553-CE-MMA-020 Oxygen-Nitrogen System Description, Operation and Maintenance (vol. 2)
2.3 MIL-STD-1330D Precision Cleaning and Testing of Shipboard Oxygen, Helium, Helium- Oxygen, Nitrogen, and Hydrogen Systems
2.4 NSTM Ch. 550 Compressed Gas Handling
2.5 S9553-C3-MMO-010 Liquid Oxygen-Nitrogen Producer Shipboard Type, Model No.
J95073, Operation and Maintenance
2.6 S9553-BA-MMA-010 Oxygen-Nitrogen System Description, Operation and Troubleshooting (vol. 1)
3.0 REQUIREMENTS
The contractor shall provide Engineering and Technical Services to complete the following repair/replacement tasks identified in the tables below.
3.1 Tasks Required
The contractor shall conduct the following tasks as part of the overhaul.
Task Number Task Description 1 Remove access panels.
2 Remove and dispose of insulation.
3 Remove Turbo-expander. Disassemble and inspect individual parts at OEM facility.
4 Remove ball valve A5, vane actuator B1, Butterfly valve A23, butterfly valve A41, and associated solenoid valves. Disassemble and inspect valves at OEM facility.
6 Remove cryo pumps and associated motors. Rewind motors at OEM facility.
7 Remove vacuum pumps and motors.
8 Isolate O2N2 producer with blank flanges. Inspect internal piping for leaks or damage.
9 Inspect relief valves, vaporizer elements, gauges and isolation valves. Determine if further repairs are required.
10 Inspect vacuum-jacketed transfer lines for leaks.
3.2 Replacement of GEECO Producer Parts
The contractor shall provide the following items as part of the overhaul.
Task Items Part Numbers Qty 4 Way Solenoid Valve Repair Kit D921-122-100 1 3” TBX Air Inlet Valve Repair Kit D841-1083-100 1 Solenoid Valve Repair Kit D941-029-100 2 4” Air Inlet Valve D841-1085-100 1 Ball Valve Repair Kit D844-1045-100 1 Vane Actuator Repair Kit D841-1080-100 1 Seal, Turbine Housing S65019 1 Seal, Compressor Housing V66344W1P 1 Producer Blanking Flange Kit J95073-BK 1 Compressed Nitrogen gas 1
4.0 TESTING/VERIFICATIONS
Removed components will be opened and inspected at the OEM facility, open and inspect shall be witnessed by c/418 personnel.
4.1 Cleaning
The system cleanliness shall be maintained by using O2 clean parts and following the requirements in MIL-STD-1330D.
5.0 DATA REQUIREMENTS
5.1 Contract Status Report (CDRL A001)
This report shall reflect both prime and Subcontractor data if applicable at the same level of detail.
The CDRL shall be delivered electronically, unless otherwise stated, and while Contractor’s format is acceptable, Government’s approval is required from the COR.
5.2 Travel Report (CDRL A002)
The travel report shall describe the purpose of the trip, relevant observations made during the trip and relevant conclusions based on the trip. The Contractor shall submit travel report in accordance with DI-MISC-81943. The CDRL shall be submitted via electronic mail in microsoft word format that can be read by Microsoft Office 2016 applications (or earlier).
6.0 SECURITY REQUIREMENTS
Contractor will need to be able to obtain base access.
7.0 PLACE OF PERFORMANCE
All work is to be done either on board CVN-74 while pier-side a Naval Station Norfolk, Norfolk, VA or at HII Newport News. Shop work is to be done at contractor facility.
8.0 TRAVEL
Contractor must travel to the Naval Station Norfolk in Norfolk, VA to perform the work on board
CVN-74.
9.0 PURCHASES
Only items directly used and incidental to the services for this Contract and resultant orders issued hereunder and for work within the scope of the SOW, shall be purchased under the Other Direct Cost (ODC) line items. Individual purchases above $10,000 shall be approved by the Contracting Officer prior to purchase by the Contractor. The purchase request and supporting documentation shall submitted via email to the Contracting Officer and the Contracting Officer's Representative (COR) it shall be itemized and contain the cost or price analysis performed by the Contractor to determine the reasonableness of the pricing.
Information Technology (IT) equipment, or services must be approved by the proper approval authority. All IT requirements, regardless of dollar amount, submitted under this contract and resultant orders issued hereunder shall be submitted to the PCO for review and approval prior to purchase. The definition of information technology is identical to that of the Clinger-Cohen Act, that is, any equipment or interconnected system or subsystem of equipment that is used in the automatic acquisition, storage, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information. Information technology includes computers, ancillary equipment, software, firmware and similar procedures, services (including support services), and related resources.
10.0 ENTERPRISE-WIDE CONTRACTING MANPOWER REPORTING
APPLICATION (ECMRA)
The Contractor shall report Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for NSWCPD via a secure data collection site. Contracted services excluded from reporting are based on Product Service Codes (PSCs).
The excluded PSCs are:
(1) W, Lease/Rental of Equipment;
(2) X, Lease/Rental of Facilities;
(3) Y, Construction of Structures and Facilities;
(4) D, Automatic Data Processing and Telecommunications, IT and Telecom- Telecommunications Transmission (D304) and Internet (D322) ONLY;
(5) S, Utilities ONLY;
(6) V, Freight and Shipping ONLY.
The Contractor is required to completely fill in all required data fields using the following web address www.ecmra.mil.
Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at www.ecmra.mil.
C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)
(a) Department means the Department of the Navy.
(b) Commander, Naval Sea Systems Command means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.
(c) References to The Federal Acquisition Regulation (FAR) All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.
(d) National Stock Numbers Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:
(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit nonsignificant number.
(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.
(End of text)
C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA) (OCT 2018)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
C-211-H001 ACCESS TO THE VESSEL(S) (NAVSEA) (OCT 2018)
Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.
C-211-H002 DRY-DOCK CERTIFICATION (NAVSEA) (OCT 2018)
The dry-docking of all vessels shall be accomplished in dry docks certified in accordance with MIL-STD-1625D(SH) dated 27 August 2009 as invoked by NAVSEA Standard Item 009-01 dated 18 November 2016. A copy of Standard Item (SI) 009-01 can be obtained from the internet by going to http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-01.
C-211-H004 HEAVY WEATHER PLAN (NAVSEA) (OCT 2018)
(a) In order to ensure that Naval vessel(s), material and Government property are protected during destructive weather such as gales, storms, hurricanes, high winds, heavy snow, ice and high water, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69 dated 18 November 2016. A copy of Standard Item (SI) 009-69 can be obtained from via the internet by going to: http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-69. In accordance with SI 009-69, the Contractor shall furnish to the cognizant Regional Maintenance Center (RMC), a copy of such HWP, and shall make such changes in the plan as the RMC considers necessary and reasonable to protect and care for vessel(s), material and Government property.
(b) In the event the RMC directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such Government direction.
C-211-H005 PLANT PROTECTION (NAVSEA) (OCT 2018)
(a) In accordance with NAVSEA STANDARD ITEM (SI) 009-72, ( ) the Contractor shall develop, maintain, and implement, as necessary, a Plant Protection Plan ( ) which prescribes the actions and procedures and assigns responsibilities for actions to be taken to provide adequate protection of the ship(s) and the materials and equipment to be installed therein. A copy of SI 009-72 can be obtained from the purchasing office representative listed in Section G of the contract or via the internet by going to http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-72.
(b) The Contractor shall establish and maintain, for its plant and the work in process under this contract, physical security boundaries and other security measures to provide safeguards against hazards, including unauthorized entry, malicious mischief, theft, espionage, sabotage, and terrorism to U.S. Naval Vessels and their crews, in accordance with SI 009-72 and Attachment A thereto. The Contractor shall also provide reasonable safeguards against vandalism and fire.
(c) The Contractor shall meet the requirements of Force Protection Condition NORMAL (as defined in SI 009-72) at all times. In addition, and in accordance with SI 009-72, the Contractor shall meet the requirements of increased levels of Force Protection as may be required or approved by the Contracting Officer, or when notified by the Supervisor, for the protection of its plant and the work in process under this contract against any threats including terrorism, espionage, sabotage, and enemy action.
(d) At the Supervisor’s discretion, the Contractor and the Supervisor shall negotiate a cost rate agreement applicable to each level of increased Force Protection above the NORMAL level. In addition to material costs, the labor cost rates shall be negotiated using the contractor’s and the Supervisor’s accepted common business practices. The labor and material costs to the Contractor for all safeguards so required or approved shall, to the extent allowable and allocable to this contract, be reimbursed to the Contractor in the same manner as if the Contractor has furnished such safeguards pursuant to a change order issued under the clause of this contract entitled "Changes-Fixed Price" (FAR 52.2431) or "Changes-CostReimbursement" (FAR 52.2432), as applicable. Such costs shall not include any allowance on account of overhead expense, except shop overhead charges incident to the construction or installation of such devices or equipment.
(e) Upon payment, in accordance with the Payments provision of this contract, by the Government of the cost to the Contractor for any device or equipment required or approved under paragraph (c) above, title thereto shall vest in the Government, and the Contractor shall comply with the instructions of the Contracting Officer respecting the identification and disposition thereof. No part or item of any such devices or equipment shall be or become a fixture by reason of affixation to any realty not owned by the Government.
(f) The plant protection plan and rate agreements required by this requirement shall be completed and implemented, within sixty (60) days of contract award for new construction and prior to ship arrival for conversion, repair or overhaul.
C-211-H010 TUG AND PILOT SERVICES (NAVSEA) (OCT 2018)
The Contractor shall provide necessary tug and pilot services to move the vessel(s) from the fairway of the plant to the pier or dock, and upon completion of all work from the pier or dock, to the fairway of the plant.
C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018)
(a) Definitions.
(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).
(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.
(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.
None
C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
C-211-H019 COMMONALITY AND STANDARDIZATION (NAVSEA) (FEB 2019)
The Contractor shall develop and implement a Commonality and Standardization Plan, reducing range and increasing depth of like equipment, to enhance supportability, minimize life cycle costs, and increase system readiness and interoperability across ships/ship classes through the selection of equipment and components which are, to the maximum extent possible, (1) common for application within the Class and (2) common with equipment/components currently installed in U.S. Navy ships. The Contractor shall utilize both Industry (e.g., the Common Parts Catalog) and Government (e.g., NAVSEA Enterprise Commonality Virtual Shelf and the Hull, Mechanical and Electrical Equipment Data Research System (HEDRS)) tools to implement its Commonality and Standardization Plan. For selecting Hull Mechanical and Electrical (HM&E) equipment/components, the Contractor shall utilize NAVSEA Enterprise Commonality Virtual Shelf before other tools, if the items meet the contract requirements. The Virtual Shelf is a web-based repository of HM&E equipment/components that meet cross-platform requirements and specifications and provide superior Total Ownership Cost (TOC). Information to gain access to the Virtual Shelf is located on the following web site: https://www.dau.mil/team/virtualshelf/SitePages/Home.aspx.
C-211-H020 PROTECTION OF THE VESSEL (NAVSEA) (MAR 2019)
(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been offloaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.
(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirtyfive degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipelines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.
(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.
(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.
(End of Text)
C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (APR 2019)
(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST 5510.2D.
(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:
(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.
(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.
(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.
(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.
(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.
(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.
(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.
(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.
(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.
(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-U.S. citizens of hostile and/or communist-controlled countries.
(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "Default (Fixed-Price Supply and Service)" (FAR 52.249-8), "Default (Fixed-Price Research and Development)" (FAR 52.249-9) or "Termination (Cost Reimbursement)" (FAR 52.249-6), as applicable.
(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.
(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.
(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.) except that, with respect to access to the vessel and worksite, the restrictions shall not apply to uniformed U.S. Navy personnel who are non-U.S. citizens and who are either assigned to the ship or require access to the ship to perform their duties.
C-223-H002 SAFETY, HEALTH AND FIRE REQUIREMENTS FOR SHIP REPAIR (NAVSEA) (JAN 2019)
(a) Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.13). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.
(b) SAFETY INSPECTOR/FIRE MARSHAL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshal who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety Representative. This Inspector or Fire Marshal shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved Safety Plan.
(c) PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:
(1) Protective hard hats that meet the following specifications:
(i) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated by the Contractor to be equally effective.
(ii) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National Standard Safety requirements for Industrial Head Protection," Z89.1-1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR 1910.135 Head Protection]
(2) Approved type Plano or prescription glasses meeting the following specifications:
(i) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.
(ii) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1-1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF 1910.133 Protective eye and face devices.]
(3) Safety toe shoes, with built-in protective toe box that meet the following specifications:
(i) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.
(ii) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]
C-223-H004 MANAGEMENT AND DISPOSAL OF HAZARDOUS WASTE (NAVSEA) (MAR 2019)
(a) General
(1) The Contractor shall comply with the Resource Conservation and Recovery Act (RCRA), the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), 10 U.S.C. 7311 and all other applicable Federal, State and local laws, codes, ordinances and regulations for the management and disposal of hazardous waste.
(2) Nothing contained in this special contract requirement shall relieve the Contractor from complying with applicable Federal, State, and local Laws, codes, ordinances, and regulations, including obtaining licenses and permits, giving notices and submitting reports, in connection with hazardous waste management and disposal in the performance of this contract. Nothing contained herein shall serve to alter either party's liability or responsibility under CERCLA.
(3) Materials contained in ship systems are not waste until after removal from the system.
(b) Identification of Hazardous Wastes of this contract identifies the types and amounts of hazardous wastes that are required to be removed by the Contractor, or that are expected to be generated, during the performance of work under this contract.
(c) Generator Identification Numbers
(1) Documentation related to hazardous waste generated solely by the physical actions of ship's force or Navy employees on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law.
(2) Documentation related to hazardous waste generated solely by the physical actions of Contractor personnel shall only bear a generator identification number issued to the Contractor pursuant to applicable law. Regardless of the presence of other materials in or on the shipboard systems or structures which may have qualified a waste stream as hazardous, where the Contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator identification number issued to the Contractor.
(3) Documentation related to hazardous waste generated by the combined physical actions of Navy and Contractor personnel shall bear a generator identification number issued to the Contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law.
(4) Notwithstanding paragraphs (c)(1) - (c)(3) above, hazardous wastes are considered to be co-generated in cases where: (a) the Contractor merely drains a system and such drainage creates hazardous waste or (b) the Contractor performs work on a system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste. Documentation related to such co-generated waste shall bear a generator identification number in accordance with the provisions of paragraph (c)(3) above.
(5) In the event of a failure by the parties to agree to the assignment of a generator identification number to any hazardous waste as set forth in paragraphs (c)(1) through (c)(4) above, the Government may direct which party or parties shall provide generator identification numbers for the waste and such number(s) shall be used on all required documentation. Any disagreement with this direction shall be a dispute within the meaning of clause of this contract entitled "Disputes" (FAR 52.233-1). However, the Contractor shall not stop any work but shall continue with performance of all work under this contract as specified in the "DISPUTES" clause.
(6) Hazardous Waste Manifests For wastes described in (c)(2), (c)(3), and (c)(4) above (and (c)(5) as applicable), the Contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the Manifest is required for disposal. The Contractor shall obtain concurrence with the categorization of wastes under paragraphs (c)(3) and (c)(4) above before completion of the manifest. Manifests prepared pursuant to paragraph (c)(1) above shall be presented to the for completion after the hazardous waste has been identified.
(7) For purposes of paragraphs (c)(2) and (3) herein, if the Contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the State in which the availability will be performed, the Contractor shall notify within 3 business days of receipt of written notification by the State. After obtaining approval, the Contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located. For purposes of paragraph (c)(1) herein, if the work is being performed at a contractor facility and the Government cannot obtain a separate generator identification number for the State, the Government shall use the Contractor site generator identification number and shall cite in the remarks block a Navy generator identification number. In both instances described above, the Contractor shall prepare the Uniform Hazardous Waste Manifest described in paragraph (c)(6) above and present it to for completion.
C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)
The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) A001-A003, attached hereto.
C-227-H013 REPORTING THE INTENDED USE OF GOVERNMENT-UNIQUE MARKS (NAVSEA)(JAN 2020)
(a) Government-unique mark, as used herein, means any mark that identifies and distinguishes goods first developed or manufactured in performance of a Government contract or that identifies and distinguishes services first rendered in performance of a Government contract.
(b) The Contractor must notify the Contracting Officer in writing of its intent to assert rights in, or file an application to register, a Government-unique mark. The Contractor's notification shall be in writing and shall identify the Government-unique mark (including the word, name, symbol, or design), provide a statement as to its intended use(s) in commerce, and list the particular classes of goods or services in which registration will be sought.
(c) Failure of the Government to respond to the notification does not waive the Government's right under the Trademark Act to contest the Contractor's assertion of rights or application.
(d) Nothing contained herein provides authorization or consent, express or implied, by the Government regarding the Contractor's use of any mark, including a Government-unique mark.
(e) Recommended Number (IAW FAR 52.1 and DFARS 252.103):
C-228-H001 INDEMNIFICATION FOR ACCESS TO VESSEL (NAVSEA) (DEC 2018)
Notwithstanding any provision in the "Access to Vessel" clause (DFARS 252.217- 7011), or any other clause of the contract, the Contractor agrees to allow officers, employees, and associates of the Government, or other prime contractors with the Government and their subcontractors, and officers, employees, and associates of offerors on other contemplated work, admission to the Contractor's facilities and access to the vessel without any further request for indemnification from any party, which has not been previously included in the contract price.
C-237-H001 ENTERPRISE-WIDE CONTRACTOR MANPOWER REPORTING APPLICATION (NAVSEA) (OCT 2018)
(a) The contractor shall report contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for CVN 74 FWD O2N2 PRODUCER OVERHAULvia a secure data collection site. Contracted services excluded from reporting are based on Product Service Codes (PSCs). The excluded PSCs are:
(1) W, Lease/Rental of Equipment;
(2) X, Lease/Rental of Facilities;
(3) Y, Construction of Structures and Facilities; (4) D, Automatic Data Processing and Telecommunications, IT and Telecom- Telecommunications Transmission (D304) and Internet (D322) ONLY;
(5) S, Utilities ONLY;
(6) V, Freight and Shipping ONLY.
(b) The contractor is required to completely fill in all required data fields using the following web address https://www.ecmra.mil.
(c) Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://dod.ecmra.support.desk@mail.mil.
C-245-H006 ADDITIONAL REQUIREMENTS RELATING TO GOVERNMENT PROPERTY (NAVSEA) (OCT 2018)
(a) For purposes of paragraph (h) of the clause entitled "Government Property" (FAR 52.245-1) in addition to those items of property defined in that clause as Government Property, the following shall also be included within the definition of Government Property:
(1) the vessel;
(2) the equipment on the vessel;
(3) movable stores;
(4) cargo; and
(5) other material on the vessel
(b) For purposes of paragraph (b) of the clause entitled "Government Property", notwithstanding any other requirement of this contract, the following shall not be considered Government Property:
(1) the vessel;
(2) the equipment on the vessel;
(3) movable stores; and
(4) other material on the vessel
C-247-H001 PERMITS AND RESPONSIBILITIES (NAVSEA) (DEC 2018)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits for complying with any applicable Federal, State, and Municipal laws, codes, and regulations for shipping and transportation including, but not limited to, any movement over public highways of overweight/over dimensional materials.
(End of text)
Section D - Packaging and Marking
D-211-H001 PACKAGING OF DATA (NAVSEA) (OCT 2018)
Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.
All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.
Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), DOD 5220.22-M…
This is the start of the file's text. The full file is on GovTribe.