About this file
This is a Brand Name/Sole Source Justification form from the Naval Surface Warfare Center, Corona Division Contracts Department for replacement speakers and related mounting equipment from Adaptive Technologies. The justification lists 9 specific items including adapters, mounting arms, bands, safety anchors, and locking brackets, with quantities ranging from 14 to 112 units per item.
The justification cites FAR 13.106-1(b)(ii) for particular brand-name items, indicating the speakers must be compatible with existing infrastructure and equipment. The document explains that these items are replacing damaged equipment that has already been tested and verified for compatibility. The rationale states that procuring alternate brands would result in substantial cost duplication due to required system redesign, new infrastructure specifications, documentation updates, and additional testing. A contract specialist (Steve Cortes) and contracting officer (Graham Conlon) certified the justification under contract N6426725Q4041:BNJ to Adaptive Technologies.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQ N6426725Q4041.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVAL SURFACE WARFARE CENTER, CORONA DIVISION
CONTRACTS DEPARTMENT
BRAND NAME/SOLE SOURCE JUSTIFICATION (SAM) SAT
LIMITED-SOURCES JUSTIFICATION (GSA) SAT
JUSTIFICATION FOR AN EXCEPTION TO FAIR OPPORTUNITY
(ID/IQ TASK ORDER/DELIVERY ORDER) SAT
1. Description of Supplies/Services.
These speakers are replacing existing speakers and need to be this model in order to be compatible with the existing infrastructure and equipment and to satisfy the customers’ requirements.
The requested supplies services represent the minimum requirements of the Government, which have been verified by the certifying technical and requirements personnel.
2 | 5
2. Regulatory Authority Permitting Other Than Full and Open Competition.
SAM
FAR 13.106-1(b)(i) Soliciting from a single source
FAR 13.106-1(b)(ii) Particular brand-name item
GSA
FAR 8.405-6(a)(i)(1)(A) An urgent and compelling need exists
FAR 8.405-6(a)(i)(1)(B) Only one source is capable of providing the supplies or services required at the level of quality required because the supplies or services are unique or highly specialized
FAR 8.405-6(a)(i)(1)(C) In the interest of economy and efficiency, the new work is a logical follow-on to an original Federal Supply Schedule order provided that the original order was placed in accordance with the applicable Federal Supply Schedule ordering procedures (the original order or BPA must not have been previously issued under sole-source or limited-sources procedures).
FAR 8.405-6 (b) Items peculiar to one manufacturer (brand-name item) ID/IQ Task Order/Delivery Order (e.g. NASA SEWP or ARMY CHESS)
FAR 16.505(b)(2)(i)(A) The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays.
FAR 16.505(b)(2)(i)(B) Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized
FAR 16.505(b)(2)(i)(C) The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order. [When utilizing this exception, the rationale shall describe why the relationship between the initial order and the follow-on is logical (e.g., in terms of scope, period of performance, or value).]
FAR 16.505(b)(2)(i)(D) It is necessary to place an order to satisfy a minimum guarantee.
FAR 16.505(b)(2)(i)(E) For orders exceeding the simplified acquisition threshold, a statute expressly authorizes or requires that the purchase be made from a specified source.
FAR 16.505(b)(2)(i)(F) In accordance with section 1331 of Public Law 111-240 ( 15 U.S.C.
644(r)), contracting officers may, at their discretion, set aside orders for any of the small business concerns identified in 19.000(a)(3). When setting aside orders for small business concerns, the specific small business program eligibility requirements identified in part 19 apply.
FAR 16.505(b)(2)(i)(G) For DoD, NASA, and the Coast Guard, the order satisfies one of the exceptions permitting the use of other than full and open competition listed in 6.302 ( 10 U.S.C.
3406(c)(5)). The public interest exception shall not be used unless Congress is notified in accordance with 10 U.S.C. 3204(a)(7).
3 | 5
3. Rationale Justifying Use of Cited Regulatory Authority.
a.) The Items Described in Paragraph 1 Must Be Compatible In All Aspects (Form, Fit And Function) With Existing Systems Presently Installed.
b.) A Patent, Copyright, or Proprietary Data Limits Competition.
c.) The Items Described in Paragraph 1 are “Direct Replacements” Parts/Components for Existing Equipment.
d.) Foreign Military Sales (FMS) Supported By A Case Letter.
e.) Unusual and Compelling Urgency.
f.) Other: If required, discuss any other rationale that supports the use of a brand name/sole source for this effort.
4. Implication of Procuring Another Brand/Manufacturer.
a.) Unacceptable Delays in Fulfilling the Agency’s Requirements.
b.) Substantial Duplication Of Cost To The Government That Is Not Expected To Be Recovered Through Competition.
The equipment listed in section 1 will replace existing equipment that was damaged The system has been tested, compatibility has been verified, and it was up and running. If we receive different equipment, This would require NSWC Corona to
4 | 5 c.) Other: If required, discuss any other implication of procuring another brand/manufacturer.
5. Actions to Remove Barriers to Competition.
If an alternate brand name is procured under this contract, it will
The new management and radio equipment may require
Additional government funds
Maintenance personnel will require
The estimated total in labor Level of effort and estimated costs are described in Table 1.
TABLE 1
EFFORT HOURS LABOR RATE COST
Develop new infrastructure specifications
System Redesign Prepare system documentation including system drawings, user manuals, test and implementation plans
System Testing and Installation
Total Cost
For the reasons described in Paragraph 3a and 4b, NSWC Corona has no plans at this time to compete future contracts for the types of supplies/services covered by this document. If another potential source emerges, NSWC Corona will assess whether competition for future requirements is feasible.
5 | 5
CERTIFICATION
I certify that the facts and representations under my cognizance, which are included in this justification and its supporting data/documentation, are complete and accurate to the best of my knowledge and belief.
CUSTOMER:
Name, Title, Code Phone No. Date
APPROVALS
I certify that the Customer representations above have been verified, and are complete and correct to the best of my knowledge. I understand that the processing of this brand name/sole-source justification precludes the use of full and open competition.
CONTRACT ADMINISTRATOR/SPECIALIST:
, Code Phone No. Date
I certify that this justification is accurate and complete to the best of my knowledge and belief, and that completing this purchase as a brand name/sole source is in the best interest of the Government.
CONTRACTING OFFICER:
, Code Phone No. Date
File details come from the government source that posted it. Updated .