1 | 4
Measurement Science and Engineering Department VLS Drill Fixture
1. INTRODUCTION
The Naval Surface Warfare Center Corona (NSWCCO) Division, Measurement Science
& Engineering Department, Interface Engineering & Assessment Division (MS22) requires six (6) Drill Fixtures (drawings 5497609-9, 5597854) for the Vertical Launching
System (VLS).
2. BACKGROUND
Naval Sea System Command (NAVSEA) Integrated Weapons System (IWS) Code 3L has a requirement to procure 6 Drill Fixtures of drawings 5497609-9 and 5597854 for the
MK41 Launcher. The MK41 Launcher is a modular launcher concept that can accommodate different canisters in various modules.
3. SCOPE
4. This Statement of Work (SOW) defines the requirements for equipment that is part of
VLS. In order to meet this requirement, NAVSEA IWS 3L requires the equipment listed below on Section 5 of this SOW.
5.
4. APPLICABLE DOCUMENTS
DRAWINGS DESCRIPTION QTY
5497609-9/
5597854 Drill Fixture and Drill Fixture Weldment 6
5. REQUIREMENTS
The Offeror shall provide a quantity of 6 Drill Fixtures of drawings 5497609-9/ 5597854.
5.1 The vendor shall host the Government personnel to perform periodic inspections at the vendor’s facility during manufacture of the Drill Fixture.
5.2 Final inspection and acceptance will be performed at NSWCCO Division prior to payment. NSWCCO may allow final inspection and acceptance using a qualified and certified vendor inspection in lieu of a final inspection and acceptance at NSWCCO.
5.3 If the drill and installation fixture does not meet the Government’s requirements as identified in the SOW, it will be returned to the vendor for repair at no additional cost to the Government.
5.4 Any deviations from drawings 5497609-9/ 5597854 must be coordinated with
NSWCCO Government MS22 personnel for approval prior to manufacturing of the
2 | 4 drill and installation fixture. Acceptance is contingent upon inspection and approval of any Request for Variation (RFV).
6. GOVERNMENT FURNISHED PROPERTY
6.1 Government Furnished Material
N/A
6.2 Government Furnished Equipment
N/A
6.3 Government Furnished Information
N/A
7. DELIVERABLES
N/A
8. ACRONYM LIST
N/A
3 | 4
ADDITIONAL INFORMATION
A. PERIOD OF PERFORMANCE / REQUIRED DELIVERY DATES
Two (2) Drill Fixtures required 4 months after award; with one (1) Drill Fixture required each year for four (4) years.