VLS Drill Fixture less pins and plates with storage container Statement of Work
PURCHASE REQUEST NUMBER:
1.0 INTRODUCTION
The Naval Surface Warfare Center (NSWC), Corona Division, Measurement Science and Engineering Department requires the acquisition of: one each Vertical Launching System (VLS) Drill Fixture per drawing 5497609-9 with 4 x 6 heat treated lumber skid and ½ inch plywood covered transport/storage container.
Drill fixture to be manufactured less pins and plates items listed below:
5599096-1 Table, Plate 5598168-1 Table, Plate 5599023-1 Table, Plate 5599024-1 Table, Plate 5599106-1 Pin, Pull Note: pins and plates will be manufactured and installed by NSWC, Corona Division
2.0 BACKGROUND
The MK41 Launcher is fitted to ships in modules. MK41 VLS is a modular Launcher concept which can accommodate different "canisters" in various modules. In order to install the launchers a drill fixture is needed during the install process. The Launcher Program has a requirement for an additional drill fixture for installation of the VLS Modules.
In order to meet this requirement, NWSC Corona Division requires the Manufacturer to meet or exceed the requirements for the drill and Installation fixture listed in the attached technical drawings, specifications and revision documents, including Module Assembly Install and Drill Fixture Drawing 5497609-9, as well as the Module Assembly Install and Drill Fixture Weldment Drawing 5597854. The fixture is used by government personnel, government contracted personnel and is intended for use during the installation of a module to drill holes in order to secure the module in place.
· NSWC Corona government personnel will perform periodic inspections at the contractor’s facilities during manufacture of the drill fixture.
· Final Inspection and Acceptance to be performed at NSWC Corona prior to payment. NSWC Corona at their discretion may allow Final Inspection and Acceptance using qualified and certified vendor inspection equipment/facilities in lieu of Final Inspection and Acceptance at NSWC Corona.
· If the delivered drill and installation fixture does not meet the drawing specifications, it will be returned to the vendor for repair at no additional cost to the government.
· Any deviations from the drawing must be submitted and approved as coordinated thru NSWC Corona government MS-22 personnel before manufacturing of the drill and installation fixture and acceptance/final acceptance is contingent upon inspection and approval of any Request for Variation (RFV) and final acceptance
3.0 SPECIFICATIONS
All equipment must be NEW with all warranties meeting or exceeding the original equipment manufacturers (OEM) offerings.
| Qty |
| Brand |
| Model # |
| Description |
Drawing Number 5497609 Rev D
(-9 configuration ) The fixture is machined steel Weldment/ assembly with sub-components and hardware in accordance with technical specification Drawing 5497609 Rev D (-9 configuration) and lower level Drawings and specifications listed in the technical Drawings.
Shipping:
FOB Destination
4.1 Acceptance of the Vertical Launching System (VLS) Drill Fixture per drawing 5497609-9 with 4 x 6 heat treated lumber skid and ½ inch plywood covered transport/storage container in Section 2.0, shall be performed by Government personnel. All equipment must be NEW with all warranties meeting or exceeding the equipment per drawing 5497609-9.