This is a Statement of Work (SOW) for inspection and cleaning services of a forward ventilation system on a naval submarine.
The contractor shall inspect and clean sections of the forward ventilation system connected to the Number 2 Electrostatic Precipitator (ESP) on an NSSN Class Submarine, including Parts A1 through A19 and A28, encompassing all ventilation ducting, fans, associated cleanouts, and connections as specified in referenced drawings. Work shall be performed at Submarine Base New London, Connecticut, with cleaning conducted in accordance with procedures approved by NAVSEA Code 05Z and the Carderock Division Life Cycle Manager. The contractor must establish baseline CO2 and O2 readings in all accessible compartments before operations begin, then monitor and record readings continuously throughout each day's activities. Cleaning operations shall cease immediately if CO2 readings exceed 3000 ppm or O2 levels drop below 19.6%, and may only resume once CO2 is reduced below 2000 ppm and O2 is restored above 19.6%. All contractor personnel must be U.S. citizens possessing valid DOD Secret Security clearances and DBIDS credentials for base access, with background checks completed via SECNAV 5512/1 forms. The contractor shall supply all materials and equipment required for the work and comply with all applicable local, state, and federal occupational safety, health, and environmental protection regulations. No government-furnished material is provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - N6278927Q0003.pdf | ||
| Urgent Justification.pdf | ||
| Wage-Determination-Groton.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ORIGINATOR: Russ Joyner
DATE: 29 October 2026
NAICS: 336611
1. SCOPE:
Title: INSPECT AND CLEAN SECTIONS OF THE FWD VENTILATION SYSTEM
2. REFERENCE/PLANS:
2.1 Naval Surface Warfare Center, Carderock Division ltr 9514 Ser 9210/021 of 20 May 2009
2.2 NSSN Class Submarine Ventilation Galley and Scullery DWG# 7067246 Rev XA
2.3 Ventilation Aft Fan Room DWG# 7067266 REV XA
3. REQUIREMENTS:
3.1 Ventilation cleaning shall be conducted in accordance with procedures approved by NAVSEA
Code 05Z and the Life Cycle Manager, Carderock Division, Naval Surface Warfare Center
(NSWCCD-SSES) Code 921.
3.2 Clean Ventilation System that is connected to the Number 2 Electrostatic Precipitator (ESP).
Cleaning will include Parts A1 through A19 and A28. Cleaning shall include all ventilation ducting, fans, associated cleanouts, and connections associated with the listed parts in references 2.2 and 2.3.
3.3. Baseline CO2 and O2 readings shall be taken prior to starting any dry ice cleaning operations in every accessible compartment on the vessel.
3.4 All CO2 and O2 readings shall be taken before and after vent cleaning operations each day.
3.5 CO2 and O2 readings shall be monitored and recorded continuously and in every accessible compartment on the vessel during vent cleaning operations.
3.6 Cleaning shall cease anytime CO2 readings exceed 3000 ppm or O2 level drops below
19.6%. When the cleaning process has been stopped, identify the deficiency and correct. Once corrected and CO2 readings are below 2000 ppm and O2 readings are above 19.6%, then cleaning may be resumed.
3.7 In addition to the monitoring CO2 and O2 levels, all standard shipboard safety procedures shall be followed.
3.8 All workers must possess a valid DOD Secret Security clearance.
4. NOTES:
4.1 The performance location will be at a pier at the Submarine Base, New London, CT.
4.2 The Contractor shall comply with all local, state, and federal Occupational Safety and Health
(OSH) and Environmental Protection (EP) rules and regulations as directed by local implementation plans.
4.3 All Contractor personnel shall be a citizen of the United States of America.
4.4 The Contractor shall provide all material and equipment required to complete all requirements of this specification.
4.5 For Contractor personnel that do not have a CAC card or a NCACS card, the following is required to obtain DBIDS credentials to gain access to the base:
a. Ensure you provide the names of personnel requiring access to the SUBASE to the NSSF POC. NSSF will pass the information to the SUBASE Pass and ID office as your government sponsor.
b. Upon arrival at SUBASE, Present valid identification, Real ID Act-compliant state driver's license. If you don’t have a Real ID compliant driver’s license, you can use a passport. If you don’t have a passport, you will be required to have an original birth certificate and your social security card (not just your number).
c. Present a completed copy of the SECNAV 5512/1 form to obtain your background check. A copy of SECNAV 5512/1 can be obtained by contacting the NSSF POC.
d. Upon completion of the background check, the Visitor Control Center representative will complete the DBIDS enrollment process, which includes your photo, fingerprints, base restrictions, and several other assessments; after all this is done, you will be provided with your new DBIDS credential. You may now proceed to enter the base.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 None.
1. SCOPE:
File details come from the government source that posted it. Updated .