N6264925RA065.pdf

PDF 691 KB Posted

Attached to
USS PREBLE (DDG-88) Surface Incremental Availability (SIA) (Yokosuka, Japan)
Solicitation number
N6264925RA065
Issued by

About this file

This is a Request for Proposal (RFP) for ship repair services for the USS PREBLE (DDG-88) at Yokosuka Naval Base in Japan. The solicitation is a non-mandatory synopsis intended only for sources authorized to operate in Japan, issued by NAVSUP Fleet Logistics Center Yokosuka. The contract is for a surface incremental availability (SIA) to accomplish repair and maintenance work defined in a single Task Group Instruction (TGI), with a performance period from September 1-15, 2025.

Offerors must have an active Master Ship Repair Agreement (MSRA) or Agreement for Boat Repair (ABR) with the U.S. Navy to be eligible. The contract will be firm-fixed-price, with proposals to be submitted electronically by July 7, 2025 at 10:00 AM Japan Standard Time. Award will be made to the responsible, technically acceptable offeror with the lowest evaluated price. Proposals must include a completed price breakdown, current MSRA/ABR certification, and documentation demonstrating authorization to do business in Japan. The government intends to award without discussions but reserves the right to conduct them if necessary.

View the file

Other files

File Type Posted
Att III GFP Listings.xlsx XLSX spreadsheet
Att II Price Proposal Form N6264925RA065.xlsx XLSX spreadsheet
Att IV Request for Information Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 10:00 AM local time 07 Jul 2025

X

A

X B

X C

D

EX

X

G

F 33 - 43

44 - 48

X H 49 - 50 josabeth.a.brizuela.civ@us.navy .mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA

FAR (48 CFR) 53.214(c)

1 50

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N62649 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and via email conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

JOSABETH A. BRIZUELA 315-243-5387

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

1 - 2

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

4 - 16 J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 19 - 21 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 22 - 25 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

26 - 31

PART II - CO NTRACT CLAUSES

NAVSUP FLC YOKOSUKA

(CODE 200)

CONTRACTING DEPARTMENT

PSC 473 BOX 11

FPO AP 96349-0011

315-243-7733

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.

N6264925331122

5. DATE ISSUED

23 Jun 2025

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N6264925RA065

Section A - Solicitation/Contract Form

SECTION A

SOLICITATION/CONTRACT FORM

MASTER AGREEMENT FOR THE REPAIR AND ALTERATION OF VESSELS (MARAV): In the event the successful offeror possesses an active Master Agreement for Repair and Alteration of Vessels (MARAV) with the U.S. Navy in the form of either a Master Ship Repair Agreement (MSRA) or an Agreement for Boat Repair

(ABR), award for this requirement will be made in the form of a firm fixed price job order under the applicable agreement and all of the terms and conditions of the offer’s existing MARAV will apply.

MSRA/ABR Number

Firms who do not possess an active U.S. Navy MSRA/ABR as a Prime Contractor are ineligible for award.

Pursuant to FAR 5.202(a)(12), this is a non-mandatory synopsis. This solicitation is intended only for sources duly authorized to operate and do business in Japan as prescribed by DFARS 252.225-7042.

1. USS PREBLE (DDG-88): NAVSUP Fleet Logistics Center Yokosuka (NAVSUP FLCY) has a new requirement in support of the USS PREBLE DDG-88. The repair and maintenance package of work items are included as Task Group Instruction (TGI) provided in ATTACHMENT (I).

2. PERIOD OF PERFORMANCE: From 1 Sep 2025 – 15 Sep 2025

3. PLACE OF PERFORMANCE: Yokosuka Naval Base

4. OFFER: Offerors must provide all information required by this solicitation no later than 7 July 2025 at 10:00

AM Japan Standard Time (JST).

5. Access to the work specification package listed in Section J as ATTACHMENT (I) may only be accessed through DoD SAFE. DoD SAFE is a secure U.S. Government repository which enables the sharing of large files and requires outside users to receive a drop-off request from the U.S. Government. Therefore, any offeror intending to provide a proposal to this solicitation shall request access by sending an email to:

josabeth.a.brizuela.civ@us.navy.mil, neil.s.flint@us.navy.mil by 7 July 2025 10:00 am JST. Once the U.S.

Government receives the offeror’s access request, the U.S. Government will provide the offeror with a link and instructions to retrieve ATTACHMENT (I). Offerors shall note that access is only available for 14 days once sent.

mailto:neil.s.flint@us.navy.mil

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

USS PREBLE DDG 88 SERVICES AND MATERIAL

FFP

The contractor shall accomplish the work requirements of one (1) Task Given

Instruction (TGI) as outlined in the provided drawings and specification, and as attached in Section J ATTACHMENT (I). The contractor will be responsible for ship repair work to include providing the necessary management, scheduling,testing, quality assurance, technical documentations to support USS

PREBLE DDG 88..

The contractor is required to submit an itemized breakdown of the price for each item on the form provided in Section J ATTACHMENT (II). Failure to submit this documentation properly completed by the specified closing date may cause rejection of the offer.

YEN AMOUNT:

Note - The U.S. Dollar amounts shown are for the Government administrative purposes only. FY25 Budget Exchange Rate of JPY145.7323 per USD1.00 applies.

FOB: Destination

MILSTRIP: N6264925A331122

PURCHASE REQUEST NUMBER: N6264925331122

PSC CD: J999

NET AMT

Section C - Descriptions and Specifications

SECTION C

DESCRIPTIONS AND SPECIFICATIONS

C-1.0 GENERAL REQUIREMENTS: The Contractor, under the direction of the U.S. Naval Ship Repair

Facility and Japan Regional Maintenance Center (SRF-JRMC) as an independent Contractor and not as an agent of the Government, shall furnish the material, support (electrical, crane, rigging, etc.) and facilities

(except those furnished by the Government under express provisions of this contract) and provide the management, technical, procurement, production, testing and quality assurance necessary to prepare and accomplish the repairs and maintenance required to complete the USS PREBLE (DDG 88) FY25 5A2

CMAV in accordance with the requirements stated in this Section, the Work Item Specifications / Task

Group Instructions (TGIs) and Work Item Plans, Drawings, and Other References, the Delivery Schedule, and all other terms and conditions set forth in this contract

C-1.1 Technical Description and Specifications: The work to be performed hereunder shall conform to the description of work/work specification described in SECTION B. The Contractor shall accomplish the contract requirements listed in ATTACHMENT (I) of Section J. Actual physical shipboard work shall begin and end in accordance with the dates listed in Section F of this solicitation.

C-1.2 Government Furnished Material: The contractor is to coordinate the delivery and/or pick-up of all Government Furnished Material (GFM) as cited in work specification(s), supporting drawings, references and/or Statement of Work (SOW). The Contractor is required to manage all GFM upon receipt which includes monitoring, inspecting, segregating, determining nonconformance, and returning unused or nonconforming material o the Government for final disposition.

C-1.3 Contractor Furnished Material: The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for procurement, receipt, storage and installation of

Contractor Furnished Material (CFM). All materials must meet the specified standard military performance specifications, Federal performance standards, and may require to be listed on a

Qualified Products List (QPL) for shipboard installations.

C-1.4 Integrated Production Schedule: The Contractor is required to submit a production schedule encompassing, to the maximum extent possible, all contractor work requirements to the

Government at the following milestones:

(1) Work Package Execution Review;

(2) Start of the Availability;

(3) 25% complete conference;

(4) 50% complete conference;

(5) 75% complete conference;

(6) Production Completion Date (PCD);

(7) Work Completion;

(8) Pre-Sea Trials requirements.

C-2.0 AVAILABILITY PREPARATION AND MEETING PARTICIPATION: The Contractor, under the direction of SRF-JRMC shall complete the following efforts after contract award in preparation to execute the ship’s availability. The Contractor shall include meetings attendance as part of their fully-burdened ship repair labor rates.

(a) The contractor shall attend and support the Integrated Project Team Development (IPTD) Work

Package Integration Conference (WPIC) as needed prior to the scheduled availability. The contractor shall support the conference by evaluating the Availability Work Package and pinpointing work requirements or issues that conflict, prevent or impact other work items from being accomplished.

(b) The contractor shall conduct final ship-checks and coordination with assigned Zone Managers (ZMs) and Work Integration Managers (WIMs) who will liaison with the project team.

(c) The contractor shall attend and support the IPTD Work Package Execution Review (WPER) and

Schedule Model Review (SMR) events as needed prior to availability. The contractor shall support the mandated conference executed during planning period leading up to execution of an availability to review work, schedule, and ensure material and resource availability.

(d) The contractor shall support the early start period of availability at the time of award. Contractor is required to begin work and therefore needs time to coordinate and stage materials and equipment prior to starting the physical work.

(e) The contractor is required to order all long lead time structural materials some of which has long duration for fabrication and shipping from United States manufacturers.

(f) The contractor is required to ensure the schedule is submitted to the project team in order to integrate with existing project schedule and mitigate risks due to space/location constraints to avoid work stoppages.

C-3.0 IDENTIFICATION OF CONDITION FOUND: In accordance with the requirements of NSI 009-01, the

Contractor shall identify needed repairs and recommend corrective action during contract performance for work/deficiencies discovered which are not covered by the existing work package. For conditions that impact the critical path(s) /controlling item(s), the Contractor shall notify the Government via electronic media within 24-hours of discovery. This initial notification need not include all content required for a

Condition Found Report (CFR), but must include a description of the condition/deficiency and an estimated timeframe for the offeror's professional recommendation for resolution, which shall not exceed five (5) working days as specified below. Recommended repairs and corrective actions shall be submitted to the

Government in the form of a CFR (intended to represent the "Work Request" described in DFARS

252.217-7028 “Over and Above Work”).

C-3.1 Condition Found Notification to Government: Submit CFRs within five (5) working days via hard copy or approved electronic media to SRF-JRMC after discovery of the condition. At a minimum, the CFR must include the following:

(1) Identify contract, ship, and hull number

(2) Identification of the applicable Work Item number

(3) Date requirement was discovered

(4) Description of the work requirement

(5) Specific location of the work

(6) Recommendation for corrective action

(7) Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change, future CNO or Continuous Maintenance

Availability). Provide supporting rationale for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.

(8) Identification of related changes, if any, to the internal milestones and production and contract completion dates.

C-3.2 Government Review and Response to CFR: The Maintenance Team will review the CFR. If the

CFR is inadequate or incomplete, it will be rejected with time continuing to accrue (relative to five

(5) working day requirement). As appropriate, the Government and contractor shall meet and discuss the recommendation for corrective action further, conducting ship checks as necessary, to determine the full scope of work required prior to final approval of the CFR. Accuracy of CFR submissions may be evaluated in CPARS and utilized for past performance ratings on future requirements.

C-5.0 DELAYS / DISRUPTIONS: The Contractor shall coordinate the work effort with SRF-JRMC Project

Manager on a daily basis to prevent changing situations from causing delays and disruptions. Disruption due to minor delays in obtaining access to spaces and operation of equipment are to be expected. A minor delay is defined as eight clock (8) hours or less in duration (and is not the cumulative effect of labor hour impact). Minor delays and/or disruptions are considered normal rather than unusual occurrences during the performance of tasks ordered under the resulting contract. The Government will not provide any schedule relief for minor delays/disruptions.

C-6.0 NON-NAVY OWNED CRANES:

Sections 11.1 and 11.2 of NAVSUPFLCYINST 4200.9 series are invoked for the incidental use of non-

Navy owned cranes at Navy shore installations.

NAVSUP FLCY STANDARD CONTRACT TEXT “NON-NAVY OWNED CRANES”

CONTRACTOR AND OTHER NON-NAVY OWNED WEIGHT HANDLING EQUIPMENT

11.1 Contractor Operated Cranes (and Multi-Purpose Machines, Materials Handling Equipment

(MHE) and Construction Equipment When Used as Cranes to Lift Suspended Loads) and

Rigging Equipment. Non-Navy-owned cranes, multi-purpose machines, MHE and construction equipment are frequently used on Navy property to lift suspended loads. Rigging equipment may be used with these machines or by itself in contractor weight handling operations. These cranes and equipment can be from a variety of sources and are generally incidental to construction contracts, ship repair contracts, demolition contracts, maintenance and other service contracts and deliveries of supplies and equipment. Numerous organizations, including tenant activities, ships, supply departments and Facilities engineering and Acquisition Division/Resident Office in

Charge of Construction (FEAD/ROICCs) have contracting authority and often the need for cranes is not anticipated when contract documents are written. The following requirements apply to any contracted work utilizing non-Navy-owned cranes (and multi-purpose machines, MHE and construction equipment used to lift loads suspended by rigging gear) and to all rigging equipment used in weight handling operations at a naval activity. These requirements do not apply to shipboard cranes or rigging equipment. These requirements also do not apply to:

commercial truck mounted and articulating boom cranes used solely to deliver material and supplies where the lift consists of moving materials and supplies (not prefabricated components, structural steel or components of a systems-engineered metal building) from a truck or trailer to the ground; to cranes installed on mechanic’s trucks that are utilized solely in the repair of shore-based equipment; to cranes that enter the activity but are not used for lifting; nor other machines not used to lift loads suspended by rigging equipment. The Public Works Office (PRY33) is responsible for the oversight of all contractor cranes on bases within Commander, Fleet

Activities Yokosuka in accordance with COMFEACTINST 11262.1B series. However, any

Weight Handling Equipment (WHE) or crane accidents shall be reported in accordance with paragraphs 11.1.h and 11.1.i:

a. The contractor is required to comply with specific activity regulations pertaining to crane safety and operation (including allowable access routes and ground loading limitations) and to notify the PRY33 office, in advance, of any cranes entering the activity or of any multi-purpose machines, MHE or construction equipment that may be used in a crane-like application to lift suspended loads. For contractor-owned cranes, machines and rigging equipment at naval activities in foreign countries, the contractor-owned cranes, machines and rigging equipment shall comply with the appropriate host nation safety standards. For floating cranes and barge-mounted mobile cranes, require a third party certification from an

Occupational Safety and Health Administration (OSHA) accredited organization (or a third party certification from a state accredited organization for those states with OSHA approved state plans), a load indicating device, a wind speed indicating device and a marine type list and trim indicator readable in one-half degree increments. Third party certification is not required for floating cranes and barge-mounted mobile cranes at Navy activities in foreign countries.

b. For cranes (or other machines used to lift suspended loads) and rigging equipment at naval activities in foreign countries, the contractor shall certify that the crane (or other machine) and the rigging equipment conform to the appropriate host nation safety standards. The contractor shall also certify that all of its crane (or other machine) safety devices are enabled and functioning properly, that all personnel working on the naval activity job site have been trained to not stand under or in the fall zone of a suspended load unless specifically allowed by USACE EM 385-1-1, and that operators have been trained to not bypass safety devices

(e.g., anti-two block devices, Load Moment Indicator’s) during lifting operations. The contractor-owned crane certifications is required to be available on the crane or in the contractor’s on-site office for rigging operations.

c. The contractor-owned mobile cranes, commercial truck mounted cranes and articulating boom cranes with Original Equipment Manufacturer (OEM) rated capacities of greater than

2000 pounds, require that the crane operator be designated as qualified by a source that qualifies crane operators (i.e., a union, a government agency or an organization that tests and qualifies crane operators). Proof of current qualification shall be provided to PRY33.

Operators of cranes used in construction at activities under US jurisdiction shall follow the qualification and certification requirements of 29 CFR 1926.1427. For Navy activities in foreign countries, follow host nation requirements as applicable in lieu of the CFR.

d. The contractor is required to certify (appendix P, figure P-1) that the crane operator is qualified and trained for the operation of the crane or machine to be used.

e. For multi-purpose machines, MHE and construction equipment used to lift loads suspended by rigging equipment, the contractor is required to provide proof of authorization from the machine OEM that the machine is capable of making lifts of loads suspended by rigging equipment. Written approval from a qualified registered professional engineer, after a safety analysis is performed, is allowed in lieu of the OEM’s approval. The contractor is required to demonstrate that the equipment is properly configured to make such lifts and is equipped with a load chart.

Note: MHE attachments covered by and used in accordance with NAVSEA SW023-AH-

WHM-010 have been pre-approved for use with all MHE. These attachments are exempt from the OEM authorization requirement above.

f. The contractor is required to provide all hooks used on cranes, hoists, other machines and rigging gear shall have self-closing latches or the throat opening shall be "moused" (secured with wire, rope, heavy tape, etc.) or otherwise secured to prevent the attached item from coming free of the hook under a slack condition. The following exceptions apply and shall be approved by the contractor’s technical organization (i.e. the Japan Construction

Information Center Foundation) with PRY33 coordination: items where the hook throat is fully obstructed and not available for manual securing; and lifts where securing the hook throat increases the danger to personnel, such as forge shop, dip tank or underwater work.

g. The contractor is required to have a critical lift plan for each of the following lifts: lifts over

75 percent of the capacity of the crane, hoist or other machine (lifts over 50 percent of the capacity of a barge- mounted mobile crane’s hoists) at any radius of lift; lifts involving more than one crane, hoist or other machine; lifts of personnel (lifts of personnel suspended by rigging equipment from multi-purpose machines, MHE or construction equipment shall not be permitted); lifts made in the vicinity of overhead power lines (see subparagraph (7);

erection of cranes; lifts of submerged or partially submerged objects (see exceptions in paragraph 10.4.1.e); lifts involving binding conditions; lifts of hazardous materials (see exceptions in paragraph 10.4.1.a); and lifts involving non-routine rigging or operation, sensitive equipment or unusual safety risks. The plan shall include the following as applicable:

(1) The size and weight of the load to be lifted, including crane (or other machine) equipment and rigging equipment that add to the weight. The OEM's maximum load capacities for the entire range of the lift shall also be provided.

(2) The lift geometry, including the crane (or other machine) position, boom length and angle, height of lift and radius for the entire range of the lift. Applies to both single and multiple-crane/machine lifts.

(3) A rigging plan, showing the lift points, rigging equipment and rigging procedures.

(4) The environmental conditions under which lift operations are to be stopped.

(5) For lifts of personnel, the plan shall demonstrate compliance with the requirements of 29

CFR 1926.1431. For Navy activities in foreign countries follow host nation requirements as applicable in lieu of the CFR.

(6) For barge mounted mobile cranes, barge stability calculations identifying crane placement/footprint; barge list and trim based on anticipated loading; and load charts based on calculated list and trim specific to the barge the crane is mounted on. The amount of list and trim shall be within the crane OEM’s requirements.

(7) For lifts in the vicinity of overhead power lines (i.e., if any part of the crane or other machine, including the fully extended boom of a telescoping boom crane or machine or the load could approach the distances noted in figure 10-3 during a proposed operation), the plan shall demonstrate compliance with 29 CFR 1926.1408-1411. For Navy activities in foreign countries follow host nation requirements as applicable in lieu of the

CFR.

h. The contractor shall notify the PRY33 office as soon as practical, but not later than four hours, after any WHE accident is identified in NAVFAC P-307 section 12. The contractor is required to secure the accident site and protect evidence until released by the PRY33 office.

The contractor shall conduct an investigation to establish the root cause(s) of any WHE accident, near miss or unplanned occurrence. Crane operations shall not proceed until the cause is determined and corrective actions have been implemented to the satisfaction of

PRY33 office and/or the contracting officer. The contractor shall certify (appendix P, figure

P-1) that the operators, riggers and company officials are aware of the actions required in the event of an accident as specified in the contract.

i. The contractor shall provide a report for an accident or near miss within 30 days to the

BSV&E office and the contracting officer using the appropriate form provided in section 12 consisting of a summary of circumstances, an explanation of causes(s), photographs (if available) and corrective actions taken. These notifications and reporting requirements are in addition to those promulgated by OPNAVINST 5100.23 and related command instructions.

j. The contractor shall certify (appendix P, figure P-1) that signal persons employed in construction work are qualified in accordance with 29 CFR 1926.1428. For Navy activities in foreign countries follow host nation requirements as applicable in lieu of the CFR.

k. The contractor shall certify (appendix P, figure P-1) that the riggers are qualified to perform the work by either signing a statement of compliance, providing proof of successful completion of a rigging apprenticeship by a union or other organization providing apprenticeship training or proof of successful completion of training courses from a recognized source such as a trade union, a government agency or an organization that tests and qualifies riggers.

l. The following additional documentation is required for contracts involving tower cranes:

(1) Foundation design and requirements.

(2) Installation instructions.

(3) Assembly and disassembly instructions including climbing/jumping instructions if applicable.

(4) Operating manual, limitations and precautions.

(5) Periodic inspection and maintenance requirements. For tower cranes at Navy activities in foreign countries, the tower cranes shall comply with the appropriate host nation safety standards and industry consensus safety standards (e.g., EN or ISO standards).

m. The following additional requirements apply to contracts involving work on telecommunication towers or with personnel hoists on telecommunication towers:

(1) Base mounted drum hoists used in communication tower work shall comply with TIA-

1019, TIA- 222G, ASME B30.7 and 29 CFR 1926.552 and 29 CFR 1926.553. For Navy activities in foreign countries follow host nation requirements as applicable in lieu of the

CFR.

(2) When used for hoisting personnel, base mounted drum hoists shall comply with OSHA

Instruction CPL 02-01-056; National Association of Tower Erectors standard “Base

Mounted Hoist Mechanism Design Use Standard for Lifting Personnel While Working on Telecommunication Structures”; ANSI/ASSE A10.22; and AMSE B30.23 (or equivalent host nation safety standards for Navy activities in foreign countries).

(3) The use of a pickup truck or any other equipment besides a base mounted drum hoist for hoisting materials and/or personnel is prohibited.

(4) Rough-terrain forklifts, bulldozers and similar equipment may be utilized for towing and anchorage purposes of guys. The use of such equipment for trolley/tag and load lines is prohibited, with the exception of using construction equipment for the sole purpose of anchorage that will not be moved during operations.

(5) Rigging gear utilized in communication tower work shall comply with the applicable

ASME/OSHA standards. Operator, signal person and rigger qualifications shall be in accordance with OSHA standards and this section. For Navy activities in foreign countries, follow host nation requirements as applicable in lieu of the CFR or ASME standards.

n. For construction contracts, follow the Unified Facilities Guide Specification UFGS-01 35 26 and U.S. Army Corps of Engineers EM-385-1-1 in lieu of paragraphs 11.1.a through 11.1.g, 11.1.j through 11.1.m and appendix P, figures P-1 and P-2.

11.2 Contracting Officer Responsibilities

a. The contracting officer will rely on PRY33 office technical expertise for oversight of all contractor-owned crane and rigging operations. Additionally, the PRY33 office to provide oversight of contractor accident investigations and corrective actions. The degree of oversight shall be based upon the risk to personnel and property; however, oversight shall be performed at least once and the minimum periodicity shall be not more than every 30 days.

When critical lifts are involved, oversight periodicity shall be not more than every 14 days.

Appendix P, figure P-2, provides a checklist that shall be used during oversight of contractor crane and rigging operations. Copies of appendix P, figure P-2, shall be kept on file for one year. Personnel performing oversight shall complete the Contractor Crane Awareness training course (see section 7) or the NAVFAC 40-hr Contract Hazard Awareness Training

Course.

b. The PRY33 office will notify the contracting officer via email of any WHE or crane accident upon notification by the contractor. Additionally, the PRY33 office will consolidate the required documents and reports for the contracting officer concurrence and submission to the

Navy Crane Center. Upon receipt of required reporting documents from the PRY33 office, the contracting officer shall notify the Navy Crane Center, by e-mail

(m_nfsh_ncc_accident@navy.mil) of an accident involving a fatality, in-patient hospitalization, overturned crane, collapsed boom or any other major damage to the crane or adjacent property as soon as possible when notified by the contractor. For all other accidents, notify the Navy Crane Center as soon as practical but no later than three working days after the accident.

c. The PRY33 office will provide the contracting officer a copy of every accident and near miss report, regardless of severity, upon receipt from the contractor. These requirements are in addition to any notification and reporting requirements promulgated in OPNAVINST

5100.23 and command instructions. Upon receipt of required documents from the PRY33 office, the contracting officer shall sign all crane and rigging accident and near miss reports to indicate that they are satisfied that the contractor's investigation and corrective action are sufficient.

d. For construction contracts, the forms in U.S. Army Corps of Engineers EM-385-1-1 are acceptable in lieu of paragraph appendix P, figure P-2.

11.3 Host Activity Responsibilities. The host activity shall ensure that contracts contain the above requirements, concur with the contracting officer’s oversight plan, ensure that the oversight plan is being carried out and provide oversight of contractor accident and near miss investigations and corrective actions.

11.4 Other non-Navy-owned cranes and rigging equipment at Naval Activities.

11.4.1 Rented or leased cranes or other WHE Operated by Navy or Base Operation Support

(BOS) contractors and cranes and rigging equipment owned and operated by BOS contractors and by contractors engaged in NAVSEA OP-5 operations in the United States and its territories. Any rented or leased cranes shall be inspected, load tested and certified to the requirements of section 4 prior to use (except for appendix E hook NDT requirements). Other WHE shall be inspected, tested and marked in accordance with section 14 requirements. For third party certified mobile cranes that cannot be load tested to the specified overload tests of this publication due to OEM restrictions or designs that prevent periodic overload tests, the cranes shall be down rated to 90 percent of the OEM's rated capacity (80 percent for non-mobile cranes) and tested to the requirements of this publication. For long term-leases (over 4 months) and for BOS contractor owned cranes, the maintenance and inspection requirements of section 3 and appendix E hook NDT requirements shall also apply. Additionally, an equipment history file in accordance with section 5, containing those documents required by sections 3 and 4 and their applicable appendices, shall be maintained on each crane. These history files shall be retained for one year after the end of the lease (seven years if the crane is involved in a crane or rigging accident). These requirements shall be included in applicable contracts. See paragraph 4.8 for third party certification requirements. Crane operators shall be licensed/qualified in accordance with the requirements of section 8 (this includes BOS contractor personnel). Crane operations and accident reporting shall be in accordance with sections 9, 10, and 12 (BOS contractor crane and rigging accidents shall be treated and reported as Navy crane and rigging accidents). Rigging equipment and usage practices shall be in accordance with section 14.

C-7.0 The following NAVSUP local text is hereby made part of the statement of work/performance work statement:

CONTRACTOR UNCLASSIFIED ACCESS TO FEDERALLY CONTROLLED FACILITIES,

SENSITIVE INFORMATION, INFORMATION TECHNOLOGY (IT) SYSTEMS OR

PROTECTED HEALTH INFORMATION

Executive Order 13467, Reforming Processes Related to Suitability for Government Employee, Fitness for Contractor Employees and Eligibility for Access to Classified National Security Information, Homeland Security Presidential Directive (HSPD)-12, requires government agencies to develop and implement Federal security standards for Federal employees and contractors. The 5 CFR 32 Part 157 in concert with DoD Manual 1000.13, Vol 1, implements the Federal Standards.

APPLICABILITY

This text applies to all DoD sponsored individuals who require CAC eligibility (or login and P/W if acceptable per contract) for: Physical access to DoD facilities or non-DoD facilities on behalf of DoD;

Logical access to information systems (whether on site or remotely); or remote access to DoD networks that use only the CAC logon for user authentication, or access to sensitive and protected information. This applies to the Office of the Secretary of Defense, the Military Departments, the Office of the Chairman of the Joint Chiefs of Staff and the Joint Staff, the Combatant Commands, the Office of the Inspector General of the DoD, the Defense Agencies, the DoD Field Activities and all other organizational entities within the

DoD (hereinafter referred to collectively as the "DoD Components").

Each contractor employee providing services at a Navy Command under this contract is required to obtain a Department of Defense Common Access Card (DoD CAC). Additionally, depending on the level of computer/network access, the contract employee will require a successful investigation as detailed below.

ACCESS TO FEDERAL FACILITIES

Definition. As used in this clause - Military installation means a base, camp, post, station, yard, center, or other activity under the jurisdiction of the Secretary of a military department, or, in the case of an activity in a foreign country, under the operational control of the Secretary of a military department or the Secretary of Defense (see 10 U.S.C. 2801(c)(4)).

Per HSPD-12 and implementing guidance, all contractor employees working at a federally controlled base, facility or activity under this clause will require a DoD CAC. When access to a base, facility or activity is required contractor employees shall in-process with the Command’s Security Manager upon arrival to the

Command and shall out-process prior to their departure at the completion of the individual’s performance under the contract.

Training. Contractor employees who require routine physical access to a Federally controlled facility or military installation shall complete “Level I Antiterrorism Awareness Training” prior to gaining access to a facility and annually thereafter in accordance with DoDI O-2000.16 Vol. 1. In accordance with Department of Defense Instruction O-2000.16 Volume 1, DoD Antiterrorism (AT) Program Implementation: DoD AT

Standards, Level I Antiterrorism Awareness Training shall be completed by:

1. Completion of “Level I Antiterrorism Awareness Training” available at https://jkodirect.jten.mil/pdf/atl1/launch.html; or

2. Under the instruction of a qualified Level I Antiterrorism Awareness instructor; or https://jkodirect.jten.mil/pdf/atl1/launch.html

3. By providing a training certificate for “Level I Antiterrorism Awareness Training” training showing completion within the last calendar year.

The contractor will submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, prior to being granted access to a Federally controlled facility or military installation.

Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts, including subcontracts for commercial items, when subcontractor performance requires routine physical access to a Federally-controlled facility or military installation.

OPERATION SECURITY (OPSEC)

It is DoD policy according to DoD Directive 5205.02E, “DoD Operations Security (OPSEC) Program,”

June 20, 2012, as amended to establish and maintain OPSEC programs to ensure national security-related missions and functions are protected.

Training: Contractor employees shall comply with all DoD OPSEC requirements and complete “OPSEC

Awareness for Military Members, DoD Employees and Contractor” training within 30 days of onboarding the contract and annual refresher training thereafter. Training shall be completed through a DoD sponsored and certified computer or web-based learning instruction available at https://securityawareness.usalearning.gov/opsec/index.htm.

The contractor will submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after training is completed by all employees and subcontractor personnel.

START-UP PERIOD

All contractor resource onboarding documents must be submitted via the prime contractor. The prime contractor shall make all necessary preparations to assume full responsibility for productive performance of the performance start date.

Definition of “productive”:

a. OF-306 signed by contractor employee

b. FD-258 Fingerprint Card (Contingent upon availability of electronic fingerprinting submission)

c. Completed EQIP (Electronic Investigation)

d. All contractor employees with need for a Common Access Card (CAC) must have an active Defense

Information System for Security (DISS) profile

e. Common Access Card (CAC)

f. DISS Visit Request submitted (Contingent upon classification of work being performed, Confidential, Secret, Top Secret)

Note (1): Invoicing by the contractor will begin as of the commencement of the performance period of services and no reimbursement will be paid by the government for efforts expended during the start-up period.

Note (2): Foreign Nationals are not allowed access to the functional/system side of Enterprise Resource

Planning (ERP).

ACCESS TO DOD INFORMATION TECHNOLOGY (IT) SYSTEMS

https://securityawareness.usalearning.gov/opsec/index.htm

In accordance with DON CIO Memorandum (IT LEVEL DESIGNATION ON DD FORM 2875 SYSTEM

AUTHORIZATION ACCESS REQUEST) 08 September 2020, contractor employees who require access to Department of the Navy (DoN) or DoD networks are categorized as Privileged, Enhanced, or

Authorized users. All user level accesses may include positions which require access to Controlled

Unclassified Information (CUI). CUI includes sensitive information protected under the Privacy Act, to include Protected Health Information (PHI). IT System levels are determined by the requiring activity's

Command Information System Security Manager (ISSM)/Information Assurance Manager (IAM).

Contractor employees requiring privileged access, (when specified by the terms of the contract) require a

Tier 5 (T5) or T5R equivalent investigation, which is a higher level investigation than the Tier 3 (T3) and

T3R described below. Due to the privileged system access, an investigation suitable for High Risk national security positions is required. Individuals who have access to system control, monitoring, or administration functions (e.g. system administrator, database administrator) require training and certification to

Information Assurance (IA) Technical Level 1, and must be trained and certified on the Operating System or Computing Environment they are required to maintain.

Contractors requiring Enhanced access, (when specified by the terms of the contract) require a T3, T3R, or equivalent investigation, which is a higher level investigation than the Tier 1 (T1) described below. Due to the enhanced system access, an investigation suitable for Moderate Risk national security positions is required.

Access to sensitive IT systems is contingent upon a favorably adjudicated background investigation.

When access to IT systems is required for performance of the contractor employee’s duties, such employees shall in-process with the Navy Command’s CSM and ISSM/IAM upon arrival to the Navy command and shall out-process prior to their departure at the completion of the individual’s performance under the contract. Completion and approval of a System Authorization Access Request Navy (SAAR-N) form is required for all individuals accessing Navy Information Technology resources. The decision to authorize access to a government IT system/network is inherently governmental. The contractor supervisor is not authorized to sign the SAAR-N; therefore, the government employee with knowledge of the system/network access required or the COR shall sign the SAAR-N as the “supervisor”.

The SAAR-N shall be forwarded to the CSM upon contractor employee acquiring a Common Access Card

(CAC) credential. Failure to obtain a CAC credential may result in delaying the individual's start date.

When required to maintain access to required IT systems or networks, the contractor shall ensure that all contractor employees requiring access complete annual Cyber Awareness training, and maintain a current requisite background investigation. The Contractor’s Security Representative shall contact the Command

Security Manager for guidance when reinvestigations are required.

INTERIM ACCESS

The Command's Security Manager may authorize issuance of a DoD CAC and interim access to a DoN or

DoD unclassified computer/network upon a favorable review of the investigative questionnaire and advance favorable fingerprint results. When the results of the investigation are received and a favorable determination is not made, the contractor employee working on the contract under interim access will be denied access to the computer network and this denial will not relieve the contractor of his/her responsibility to perform.

DENIAL OR TERMINATION OF ACCESS

The potential consequences of any requirement under this clause including denial or termination of physical or system access in no way relieves the contractor from the requirement to execute performance under the contract within the timeframes specified in the contract. Contractors shall plan ahead in processing their employees and subcontractor employees. The contractor shall insert this clause in all subcontracts when the subcontractor is permitted to have unclassified access to a federally controlled facility, federally-controlled information system/network and/or to government information, meaning information not authorized for public release.

ACCESS TO CONTROLLED UNCLASSIFIED INFORMATION

Safeguarding sensitive unclassified information is critical to achieve NAVSUP Modernization efforts and deliver cutting-edge and uncompromised capabilities. The Secretary of Defense’s operations security

(OPSEC) campaign plan stresses the importance of protecting controlled unclassified information (CUI).

CUI encompasses OPSEC, critical technology, intelligence, and personally identifiable information that, if not properly identified, marked, and controlled, could impair NAVSUP’s ability to conduct its mission.

Contractor employees with access to Controlled Unclassified Information (CUI) shall comply with DoDI

5200.48 - Controlled Unclassified Information (CUI) and complete DoD approved initial and annual refresher CUI training.

a. Whenever Government provides CUI to, or CUI is generated by, non-DoD entities, all CUI records must be handled as required by the approved mandatory disposition authority.

b. All CUI records must follow the approved mandatory disposition authority whenever the Government provides CUI to, or CUI is generated by, non-DoD entities in accordance with Section 1220-1236 of

Title 36, CFR, Section 3301a of Title 44, U.S.C., and the DoDI 5200.48.

c. Contractor employees shall monitor CUI aggregation and compilation based on the potential to generate classified information pursuant to security classification guidance addressing the accumulation of unclassified data or information

d. Contractor employees shall submit unclassified government information for review and approval for release in accordance with the Standard DoD Component Processes, DoDI 5230.09, and DoDM

5205.07, Volume 1.

CONTRACTOR’S SECURITY REPRESENTATIVE

The contractor shall designate an employee to serve as the Contractor’s Security Representative. Within three work days after contract award, the contractor shall provide to the requiring activity’s Security

Manager and the Contracting Officer, in writing, the name, title, address and phone number for the

Contractor’s Security Representative. The Contractor’s Security Representative shall be the primary point of contact on any security matter. The Contractor’s Security Representative shall not be replaced or removed without prior notice to the Contracting Officer and Command Security Manager.

BACKGROUND INVESTIGATION REQUIREMENTS AND SECURITY APPROVAL PROCESS

FOR CONTRACTORS ASSIGNED TO NATIONAL SECURITY POSITIONS OR PERFORMING

SENSITIVE DUTIES

Navy security policy requires that all positions be given a sensitivity value based on level of risk factors to ensure appropriate protective measures are applied. If the Security Office validates the contractor’s position is Non-Critical Sensitive or if the IT system user level is determined to be Enhanced, at a minimum, each contractor employee must be a US citizen and have a favorably completed T3, T3R, or equivalent investigation to obtain a favorable determination for assignment to a non-critical sensitive or Enhanced position. The investigation consists of a standard National Agency Check and a FBI fingerprint check plus law enforcement checks and credit check. Each contractor employee filling a non-critical sensitive or

Enhanced position is required to complete:

SF-86 Questionnaire for National Security Positions (or equivalent Office of Personnel

Management (OPM) investigative product)

Two FD-258 Applicant Fingerprint Cards or electronic fingerprint submission (preferred))

Original Signed Release Statements

Failure to provide the required documentation at least thirty (30) days prior to the individual’s start date shall result in delaying the individual’s start date. Background investigations shall be reinitiated as required to ensure investigations remain current (not older than ten (10) years) throughout the contract performance period. The Contractor’s Security Representative shall contact the CSM for guidance when reinvestigations are required.

Regardless of their duties or IT access requirements ALL contractor employees shall in-process with the

CSM upon arrival to the command and shall out-process prior to their departure at the completion of the individual’s performance under the contract. Employees requiring IT access shall also check-in and check-out with the Navy Command’s ISSM/IAM. Completion and approval of a System Authorization Access

Request Navy (SAAR-N) form is required for all individuals accessing Navy IT resources. The SAAR-N shall be forwarded to the CSM upon the contractor employee acquiring a Common Access Card (CAC) credential. Failure to obtain a CAC credential or provide the required documentation shall result in delaying the individual’s start date.

The contractor shall ensure that each contract employee requiring access to IT systems or networks complete annual Cyber Awareness training, and maintain a current requisite background investigation.

Contractor employees shall accurately complete the required investigative forms prior to submission to the

CSM. The CSM will review the submitted documentation for completeness prior to submitting it to the

OPM. Potential suitability or security issues identified may render the contractor employee ineligible for the assignment. An unfavorable determination is final (subject to SF-86 appeal procedures) and such a determination does not relieve the contractor from meeting any contractual obligation under the contract.

The CSM will forward the required forms to OPM for processing. Once the investigation is complete, the results will be forwarded by OPM to the DoD Central Adjudication Facility (CAF) for a determination.

For classified contracts, if the contractor employee already possesses a current favorably adjudicated investigation, the contractor shall submit a Visit Access Request (VAR) via the Defense Information

Security System (DISS). If the contractor employee does not have a current favorably adjudicated investigation, the contractor shall submit the Visit Access Request in DISS until the contractor employee has at a minimum an interim clearance.